CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Lewisham
Audit and Risk Committee, Thursday 25 June 2026 at 7.00pm

Corporate Risk Register

Noted Finance 2 papers

AI summaryLewisham Audit and Risk Committee noted the Corporate Risk Register and asked for further detailed reports on cyber security, IT partnership risk, housing management software, risk-scoring and climate resilience.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedFive specific topics to be reported on during the year
MoneyNoneDelivered within existing budgets
What happens nextFurther reports during the yearOn five named topics
Who it affectsCouncil risk managementAcross all directorates and registers

What was decided

The Committee noted the Corporate Risk Register report.

The Committee requested further detailed reports during the year on cyber security, business continuity and response to attacks; IT partnership risk; housing management software implementation; risk-scoring methodology; and climate resilience/Helios exercise outcomes.

Why

Risk management remains a developing discipline within the Council, focusing on continuous improvement, and the report sets out recent work by the risk management team. Report 6.1

Recent work includes completed risk workshops for several directorates, a BDO audit of Enterprise Risk Management, development of a fraud risk register, new scoring guidance and a review of World Economic Forum global risks. Report P2, P3, P4, P5, P6

What happens next

Further detailed reports to come to the Audit and Risk Committee during the year on the five topics listed in the decision.

A revamped risk management strategy will come to the Audit and Risk Committee for approval, incorporating the new scoring guidance. Report P5

Risk workshops for the Place directorate are scheduled for July. Report P2

Implications

  • Financial: None arising; risk management is delivered within existing budgets. Report P7
  • Legal: None arising directly from this report. Report P8
  • Equalities: None arising directly from this report. Report P8
  • Climate: None arising directly from this report; climate resilience is to be covered in a future Helios exercise outcomes report. Report P8
  • Risk: The report is to note and has no risk implications directly arising; it instead describes the current risk management work. Report P8

Who and where

  • Corporate Resources, Chief Executive's Directorate, Children and Young People, and Adult Social Care and Health directorates (risk workshops completed) Report P2
  • Place directorate (risk workshops scheduled for July) Report P2
  • Council risk owners across all risk registers Report P6
  • Anti-Fraud and Corruption Team (fraud risk register development) Report P4

Timeline

  • February: Findings of the World Economic Forum Global Risks Report review presented to EMT. Report P6
  • July: Risk workshops scheduled for the Place directorate. Report P2
  • During the year: Further detailed reports requested on cyber security, IT partnership risk, housing management software, risk-scoring methodology and climate resilience/Helios exercise outcomes.

Plain English for the jargon

  • EMT: Executive Management Team
  • STS: Shared Technology Service
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13

Resolved

that the report outlining the be noted and the Committee requested further detailed reports during the year on: • Cyber security, business continuity and response to attacks • IT partnership risk • Housing management software implementation • Risk-scoring methodology and • Climate resilience/Helios exercise outcomes.
Word for word from the decision Lewisham published for this meeting. Source: councilmeetings.lewisham.gov.uk

Follow this further

Built from Lewisham's papers

What the report saysPro

Report to Audit and Risk Committee

Audit and Risk Committee

Risk Management and Corporate Risk Register update June 2026 Date: 25 June 2026

Key decision: No.

Class: Part 1

Ward(s) affected: All

Contributors: Richard Benjamin, Head of Assurance Colin Burns, Audit and Risk Manager Kelly Thompson, Risk Officer

Outline and recommendations The report presents the current Corporate Risk Register and provides additional detail on the Council’s developing risk management approach. It highlights that risk management remains a live and evolving discipline and sets out the progress made, along with the work completed by the risk management team to strengthen practice across the organisation. The accompanying appendix provides an overview of the Corporate Risk Register.

We ask Members to note the report.

Timeline of engagement and decision-making Risk registers are reviewed and updated by risk owners on a regular basis. The current presentation of the Corporate Risk Register is as of 15 June 2026.

Previous versions were reviewed and discussed at various officer and Member briefings:

11 November 2025: Last presentation to the Audit & Risk Committee 03 June 2026: Risk register presented to Executive Management Team 09 June 2026: Risk register presented at Cabinet Briefing 25 June 2026: Current presentation to the Audit & Risk Committee 1. Summary 1.1. This report and appendix, provides an update on corporate risk at the London Borough of Lewisham. The report also details current progress of risk management across the council. 2. Recommendations 2.1. We ask Members to note the report. 3. Policy Context 3.1. This report aligns with the ambitions and priorities of the administration elected in May 2026, as reflected within the Council’s emerging corporate delivery plan, including: • Safe, affordable homes • Cleaner streets and greener neighbourhoods • An economy of care • Healthier, happier communities • Justice, sanctuary and care 4. Background 4.1. The Corporate Risk Register is updated regularly by senior management and reported to EMT, Cabinet and then to Audit and Risk Committee. 4.2. The Council continues to manage its risk via our risk management software, Pentana Risk. The system captures a full audit trail for each risk. 4.3. Outside of the Corporate Risk Register there are several other registers to manage risks across the whole Council. Other risk registers include Directorate registers, Service Registers and Cross-Service registers. 5. Corporate Risk Register 5.1. The current Corporate Risk Register in its entirety, is contained at Appendix A. 5.2. There are 16 risks on the Corporate Risk Register, of which nine are rated as “Very High” or “High”. 5.3. The highest risk remains “Significant Cyber Security Breach” (LBL009). 5.4. Since the last presentation three risks have increased in score and five risks have decreased in score. The following should be noted: • The risk ‘Workforce attraction’ (CEX-LCG004, previously LBL004), has been removed from the corporate risk register to be managed at directorate level following a wider review of People and Organisational Development (OD) risk

Is this report easy to understand? Please give us feedback so we can improve. Go to https://lewisham.gov.uk/contact-us/send-us-feedback-on-our-reports registers. This review included a full review of all controls, mitigating actions as well as ensuring all the risk causes and impacts were detailed out to identify any gaps.

• The risk ‘Workforce retention and engagement’ (CEX-STE005, previously LBL005) has also been removed from the corporate risk register to be managed at directorate level following the wider review of the People and OD risk registers. The scoring was updated subsequently in line with the new scoring guidance.

• The risk relating to significant disruption to IT partner (LBL023) has had a likelihood score increase. This is because Southwark have given notice to leave the partnership in 2028. An exit project will be set up, and the STS governance will change to accommodate.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
13a, Appendix A: Corporate Risk RegisterAppendix 214 KB Download
PDF
Corporate Risk RegisterReport 98 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 9 attended
HF
Councillor Heather FarnworthChair, present
EF
Councillor El FryVice-Chair, present
TD
Councillor Tanya DunneCommittee Member, present
GM
Councillor Gavin MooreCommittee Member, present
JR
Councillor James RathboneCommittee Member, present
CW
Councillor Claire WillsCommittee Member, present
AJ
Andrew JonesCo-Optee, in attendance
MM
Mark McLaughlinCo-Optee, in attendance
MO
Marcus O’TooleCo-Optee, in attendance

On this subject at Lewisham

Search all
  1. Corporate Risk RegisterThis decision
  2. Risk Management and Corporate Risk Register UpdateNoted

More from Lewisham Audit and Risk Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Apologies for AbsenceApologies were received from Councillor Tanya Dunne and Councillor El Fry. Decided Open
8 Sep 2026 Declarations of InterestCouncillor Rathbone declared during Item 6: Risk Management and Corporate Risk Register Update that he is an employee... Decided Open
8 Sep 2026 MinutesRESOLVED that the minutes of the meeting of the Audit and Risk Committee held on 25 June 2026 be confirmed and signed... Noted Open
8 Sep 2026 External Audit UpdateRESOLVED that the contents of the report be noted. Noted Open
8 Sep 2026 Internal Audit Progress Update (delivery of the 2026/27 plan)RESOLVED that the Internal Audit Progress Report be noted. With this additional recommendation agreed: • The findings... Noted Open