Cabinet, Monday 13 July 2026 at 6.00pm

Year-End Performance and Delivery Report 2025/26

Approved Executive 5 papers

AI summaryLichfield District Council Cabinet approved the 2025/26 year-end performance report and the 2026/27 delivery plan, with 72% of 78 corporate performance indicators meeting target.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApproved
MoneyNo direct financial implicationsAll planned activities built into financial planning
What happens nextQ2 2026/27Next performance report to Cabinet due after Q2 2026/27
Who it affectsAll Lichfield district residents and businessesCouncil-wide performance and delivery plan monitoring

What was decided

Cabinet approved the Q4 Year 2 Delivery Plan outturn of the Lichfield District 2050 Strategy and the Q2 KPIs report, as set out in Appendices A and C. Report P4

Cabinet reviewed and approved the Housing, Homelessness and Rough Sleeping Strategy Delivery Plan at Appendix B. Report P4, P20

Cabinet reviewed and approved the Year 3 Lichfield District 2050 Delivery Plan at Appendix D. Report P4, P36

Why

The report provides the year-end performance position for 2025/26 against the Lichfield District 2050 Year 2 Delivery Plan, the council's corporate KPIs, and the Housing, Homelessness and Rough Sleeping Strategy 2025-2030. Report P2, P5

Of 78 KPIs, 56 (72%) are rated green, an improvement on the 2024/25 outturn of 52%. Of 35 Q4 actions, 25 (71.4%) are green, 10 are red and 4 are on hold. Report P2, P6, P22, 3.21

The council has continued to deliver during increasing service demand, financial pressures, national policy changes and Local Government Reorganisation preparations. Report P2, P3

What happens next

The Delivery Plan and KPIs will continue to be monitored quarterly by the Leadership Team, with the next Cabinet performance report due after Q2 2026/27. Report 3.13, 3.26, P36

Improvement plans are in place for KPIs rated amber or red, and performance will continue to be monitored throughout 2026/27. Report 3.25, P34

Officers will work to ensure LD2050 aims and objectives are reflected in strategic plans for the new unitary authority under Local Government Reorganisation. Report P49

The money

  • £1.4 million Invested into community infrastructure projects including sports facilities, parks and play areas Report P2, P7
  • £1,247,196 Disabled Facilities Grant adaptations delivered, helping 120 residents remain independent Report P2, 3.22
  • £4.899m Total investment identified for temporary accommodation, with 22 properties purchased and fully occupied Report P2
  • more than £250,000 Delivered through the Community and Voluntary Sector Funding Programme Report P2
  • more than £2 million Additional social value generated for local communities through procurement activity Report 3.22
  • more than £120,000 Awarded to seven rural businesses through the Rural England Prosperity Fund Report P8
  • almost £256,678 Funding distributed through the 3-year Community and Voluntary Sector funding scheme in first two quarters of 25/26 Report P8
  • more than £1.24 million Disabled Facilities Grant adaptations delivered by LWM, with 135 adaptations Report 3.11

Options considered

  • Chosen: Approve the Q4 Year 2 Delivery Plan outturn and Q2 KPIs report. Recommended to provide performance assurance and oversight Report P4, P37
  • Chosen: Approve the Housing, Homelessness and Rough Sleeping Strategy Delivery Plan. Recommended to support strategy delivery Report P4, P20
  • Chosen: Approve the Year 3 Lichfield District 2050 Delivery Plan. Recommended to maintain delivery momentum Report P4, P36
  • Rejected: Cabinet could approve a different approach to performance reporting. This would delay approval and adoption Report P37

Implications

  • Financial: No direct financial implications arising from the strategy or performance report; all planned activities built into financial planning. Report P39
  • Legal: No direct legal implications arising from the report. Report P40
  • Equalities: Due to the strategic nature of the plan, an Equality Impact Assessment is of limited benefit for the strategic plan itself, but detailed delivery plans and thematic strategies should complete an EIA. Report P43
  • Climate: Creating the greenest district in the country is one of the four ambitions of Lichfield District 2050. Report P46, P47
  • Risk: Local Government Reorganisation creates uncertainty around the council's ability to complete longer-term LD2050 milestones; the risk is rated Red for likelihood and Yellow for impact. Report P49
  • Other: No crime and safety or GDPR/privacy issues arise from the production of the strategic plan and accompanying performance report. Report P45, P48

Who and where

  • All residents of Lichfield district Report P1, P2
  • Local businesses and voluntary sector organisations receiving funding or support Report P2, P8
  • Residents presenting as homeless or rough sleeping Report P2, 3.22
  • Disabled residents receiving home adaptations Report P2, 3.22
  • Visitors and users of the new Lichfield Leisure Centre Report P2, P7
  • Users of the new Greenway walking and cycling route Report P2, P7
  • Tenants of privately rented homes subject to inspections Report 3.22
  • Applicants for planning applications, particularly those requiring legal agreements Report P29

Timeline

  • 14 May 2024: Lichfield District 2050 Strategy adopted by Full Council Report P6, P50
  • 23 June 2025: Year 2 Delivery Plan approved by Cabinet; Housing, Homelessness and Rough Sleeping Strategy 2025-2030 approved by Cabinet Report P6, P20, P50
  • 2 December 2025: Quarter 2 2025/26 Performance report considered by Cabinet Report P50
  • January 2026: New Lichfield Leisure Centre opened Report P2, P7
  • Q4 2025/26 (year end): 72% of 78 KPIs rated green; 25 of 35 Q4 actions rated green Report P2, P6, P22
  • May 2026: Council won iESE Public Sector Transformation Awards 2026 Report P2
  • 13 July 2026: Cabinet approved year-end performance report, Housing Strategy Delivery Plan and Year 3 Delivery Plan Report P1
  • After Q2 2026/27: Next Cabinet performance report due Report 3.13, 3.26, P36

Plain English for the jargon

  • LD2050: Lichfield District 2050 Strategy, the council's primary strategic plan adopted in May 2024, with four ambitions: Confident, Prosperous, Active and Greener Communities.
  • KPI: Key Performance Indicator, a corporate measure used to track operational performance and service quality.
  • RAG rating: Red, Amber, Green status used to indicate whether a Delivery Plan action is on track (Green), at minor risk (Amber), or at risk (Red).
  • Disabled Facilities Grant: A grant to help disabled people adapt their homes to remain independent.
  • LGR: Local Government Reorganisation, the planned restructuring of local councils in England, creating uncertainty for the district's longer-term planning.
  • LWM / LWMTS: Lichfield Walsall Management, the council's wholly owned trading company that delivers services and supports council priorities.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item3

Resolved

The Cabinet: 2.1 Discussed and approved the Q4 Year 2 Delivery Plan outturn of the Lichfield District 2050 Strategy and Q2 Key performance indicators (KPIs) report as set out in Appendix A and Appendix C. 2.2 Reviewed and approved the Housing, Homelessness and Rough Sleeping Strategy Delivery Plan at Appendix B. 2.3 Reviewed and approved the Year 3 Lichfield District 2050 Delivery Plan at Appendix D.
Word for word from the decision Lichfield published for this meeting. Source: democracy.lichfielddc.gov.uk

Follow this further

Built from Lichfield's papers

What the report saysPro

Report to Cabinet

Year-End Performance and Delivery Report 2025/26 Leader of the Council Councillor Doug Pullen Date: 13th July 2026 Agenda item: 3 Contact officer: Kerry Dove / Lucy Robinson Tel number: 01543 308068 / 01543 308710 CABINET Email: [email protected]/ [email protected]/ Key decision? YES Local ward All members

1. Executive summary 1.1 This report provides the year-end performance position for 2025/26 against the Lichfield District 2050 Year 2 Delivery Plan, the council’s corporate Key Performance Indicators (KPIs) and the Housing, Homelessness and Rough Sleeping Strategy 2025-2030. 1.2 The Lichfield District 2050 Delivery Plan for Year 3 (2026/27) is included as an appendix. 1.3 2025/26 has been a significant year of delivery for Lichfield District Council. Despite increasing demand for services, continuing financial pressures, national policy changes and preparations for Local Government Reorganisation, the council has continued to make progress against the ambitions set out within Lichfield District 2050 whilst maintaining strong operational performance. 1.4 We continue to set ambitious and stretching targets designed to challenge ourselves and maximise outcomes for residents, communities and businesses. Whilst not every target has been achieved, significant progress has been made across all four strategic ambitions. 1.5 Key highlights from 2025/26 include: • Thousands of residents are now benefiting from the new Lichfield Leisure Centre, one of the council's biggest investments in community wellbeing. • The Greenway has transformed a former railway corridor into a 6.5km walking route connecting communities across the district. • £1.4 million has been invested into community infrastructure projects including sports facilities, parks and play areas across the district. • Supporting 100% of residents presenting as homeless on the same day they contacted the council. • Delivering £1,247,196 of Disabled Facilities Grant adaptations, helping 120 residents remain independent in their own homes. • Progressing major regeneration priorities including Birmingham Road, the city centre cinema development, the linear park and the Burntwood Masterplan. • Supporting local communities, businesses and young people through a range of district-wide initiatives and investment programmes. • Supporting every resident who presented as homeless on the same day they contacted the council and continuing to provide rapid support to rough sleepers.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
LD2050 Delivery plan performanceAppendix A 95 KB Download
PDF
Housing homelessness and rough sleeping strategy: oveview performance report: Y1Appendix B 202 KB Download
PDF
KPIs performance updateAppendix C 143 KB Download
PDF
Year 3 Delivery PlanAppendix D 65 KB Download
PDF
Year-End Performance and Delivery Report 2025/26Report 245 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 11 attended
RC
Councillor Richard CoxCommittee Member, present
AF
Councillor Alex FarrellCommittee Member, present
RH
Councillor Richard HollandCommittee Member, present
DP
Councillor Doug PullenChair, present
JS
Councillor Janice Silvester-HallCommittee Member, present
AS
Councillor Andrew SmithCommittee Member, present
RS
Councillor Richard StephensonCommittee Member, present
RS
Councillor Rob StrachanCommittee Member, present
PW
Councillor Phil WhitehouseCommittee Member, present
KD
Kerry DoveSecretary, present
MH
Mark HooperClerk, present

On this subject at Lichfield

Search all
  1. Year-End Performance and Delivery Report 2025/26This decision
  2. Lichfield District 2050 Strategy - End of Year Financial & Performance UpdateNoted
  3. Report on Performance Against the Delivery Plan – End of Year 2018/19Noted

More from Lichfield Cabinet

All decisions
MeetingDecisionOutcome
13 Jul 2026 Confirmation of Scheme of Delegation for New Local PlanThe Cabinet: Delegated authority to the Cabinet Member for Housing and Local Plan in conjunction with the Chief Execu... Decided Open
13 Jul 2026 Community infrastructure Levy (CIL) Allocations 2026The Cabinet: 2.1 Approved the following CIL allocations: · £100,000 to Wigginton and Hopwas Parish council towards th... Approved Open
13 Jul 2026 Money Matters: 2025/26 Financial MonitoringThe Cabinet: 2.1. Reviewed the report including the level of general and earmarked reserves and issues raised within ... Approved Open
13 Jul 2026 Procurement Matters Update 2025/26The Cabinet: 2.1. Reviewed the contents of this report and the progress against planned actions in the Action Plan fo... Approved Open