AI summaryLichfield Cabinet reviews 2025/26 procurement performance, delegates authority to approve the 2026/27 procurement pipeline, and approves changes to key performance indicators.
Money£84,919 cashable savingsPlus £312,622.26 non-cashable, 93.21% paid in 30 days
What happens nextFuture Procurement Plan 2026/27Pipeline for approval by Cabinet Member and S151
Who it affectsSuppliers, service areas, residentsAcross Lichfield District and wider Staffordshire
What was decided
Cabinet reviewed the 2025/26 action plan, key performance indicators, self-assessment against the National Procurement Strategy and procurement project progress.
Authority was delegated to the relevant Cabinet Member and the Director of Finance, Environment and Community (S151) to approve the Future Procurement Plan and Pipeline for 2026/27, allowing procurements to proceed.
Cabinet approved suggested amendments to the key performance indicators, including a merged local spend measure and a new indicator on small and medium-sized enterprise spend.
Why
The second Procurement and Commissioning Strategy was approved in September 2025 to cover 2025 to 2029, and the Procurement Matters Update is a regular review of progress against it.
During 2025/26 there was a 15.34 per cent increase in procurement projects and a 20 per cent improvement in the National Procurement Strategy Maturity Assessment, with payment, savings and social value indicators all exceeded. Report 3.26
Officers wanted to capture small business activity under the Procurement Act 2023 and simplify the local and county spend indicators by combining them.
What happens next
The Future Procurement Plan and Pipeline for 2026/27 will be approved by the relevant Cabinet Member and the S151 Director, with individual contract awards going through Cabinet Member Decision or Cabinet as appropriate. Report 1.4
Two new key performance indicators will take effect: merged percentage of spend within Staffordshire including Lichfield District (baseline 37 per cent) and percentage of spend with small and medium-sized enterprises, to be baselined during 2026/27.
The Procurement and Commissioning team will continue to support embedding the Procurement Act 2023, including the new requirement for suppliers of contracts above £25,000 to hold a Public Procurement Organisation Number.
The money
£84,919 Cashable procurement savings achieved in 2025/26 Report P13
£312,622.26 Non-cashable savings (cost avoidance) in 2025/26
£30,289 Savings against an original Medium Term Financial Strategy budget of £30,120 Report P13
£2,694,825 Social value generated through procurement in 2025/26 Report P50
£2.7 million Estimated value of defined Social Value commitments across 24 contracts
£3,800,000 Estimated value of Waste Partnership Temporary Labour re-tender in 2026/27 Report P39
£3,500,000 Estimated value of Fuel Supply Framework re-tender in 2026/27 Report P39
Options considered
Rejected: Develop a new Procurement and Commissioning Strategy with different outcomes. Existing 2025 to 2029 strategy was approved in September 2025 and is delivering improvements Report P11
Rejected: Develop a new Social Value Policy with different outcomes. Social Value Policy and Guidance was approved by Cabinet on 8 April 2025 and is being implemented Report P11
Chosen: Merge the Lichfield District and Staffordshire spend indicators and add a small and medium-sized enterprise spend indicator. To simplify reporting and reflect the Procurement Act 2023's focus on small and medium-sized enterprises
Implications
Financial: Procurement savings of £84,919 cashable and £312,622.26 non-cashable achieved in 2025/26 against a £30,120 savings target. Report P13
Legal: The Procurement Act 2023 came into force on 24 February 2025 and the Council has updated templates, guidance and the contracts register to comply; suppliers on contracts over £25,000 now need a Public Procurement Organisation Number.
Equalities: An Equalities Impact Assessment has been completed for the Social Value Policy. Report P17
Climate: Environmental sustainability is built into procurement evaluation criteria and the Procurement and Commissioning Manager sits on the Council's Climate and Environment Group, contributing to the Internal Carbon Reduction Plan. Report P19
Risk: Risk register shows reduced likelihood and impact scores following the strategy and pipeline work, particularly for non-compliance, reactive procurement and unrealised savings. Report P20, P21
Other: No modern slavery or human trafficking issues or non-compliance were identified in procurement and commissioning activities during 2025/26.
Who and where
Local suppliers, small and medium-sized enterprises and voluntary and community sector organisations bidding for Council contracts
Council service areas running procurement projects, particularly Operational Services, Health and Safety, Resident and Business Services Report P37, P38
Residents and communities receiving social value benefits, including employment, training, volunteering and donations Report P50, P51, P52
Taxpayers and the Council's Medium Term Financial Strategy through delivery of procurement savings Report P13
Timeline
December 2020: Original Procurement Strategy approved by Cabinet Report P22
24 February 2025: Procurement Act 2023 came into force
8 April 2025: Social Value Policy and Guidance approved by Cabinet Report P22
8 September 2025: Second Procurement and Commissioning Strategy covering 2025 to 2029 approved by Cabinet
2025/26: 233 procurement projects delivered, 61 per cent awarded or complete, 36 per cent ongoing, 3 per cent pending Report 3.26, P9
13 July 2026: Cabinet considered the seventh Procurement Matters Update report and approved the actions set out in the decision Report 1.4
2026/27: Future Procurement Plan and Pipeline to be approved under delegated authority, with new key performance indicator baselines set
Plain English for the jargon
CIPS: Chartered Institute of Procurement and Supply, the professional body for procurement.
ITT: Invitation to Tender, the formal document used to seek competitive bids for a contract.
KPI: Key Performance Indicator, a measurable value showing how effectively objectives are being met.
NPS: National Procurement Strategy, the Local Government Association framework used for the Maturity Assessment.
PA23: Procurement Act 2023, the UK legislation that replaced previous procurement regulations and came into force on 24 February 2025.
RFQ: Request for Quotation, a simpler competitive process used for lower value procurements.
S151 Officer: The local authority officer with statutory responsibility for financial administration, here the Director of Finance, Environment and Community.
Social Value TOMs: Themes, Outcomes and Measures, the national framework for measuring social value in contracts.
VCSE: Voluntary, Community and Social Enterprise organisations.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
The Cabinet: 2.1. Reviewed the contents of this report and the progress against planned actions in the Action Plan for 2025/26, Key Performance Indicators for 2025/26, the updated self-assessment against the National Procurement Strategy and progress on Procurement projects for 2025/2026. 2.2. Delegated authority to the relevant Cabinet Member and Director of Finance, Environment and Community (S151) to approve the Future Procurement Plan/Pipeline for 2026/27, as set out in APPENDIX E. This will enable procurement exercises to proceed, with contract awards being approved either through a Cabinet Member Decision or Cabinet Approval, as appropriate. 2.3. Reviewed the update on Modern Slavery and Human Trafficking for 2025/26. 2.4. Approved the suggested amendments to KPI’s.
Word for word from the decision Lichfield published for this meeting.Source: democracy.lichfielddc.gov.uk
Procurement Matters Update 2025/26 Cabinet Member for Finance and Commissioning Date: 13/07/2026 Agenda item: 7 Contact officer: Anthony Thomas / Oliver Shaw Tel number: 01543 308 012 / 01543 308 026 Email: [email protected] CABINET [email protected] Key decision? NO Local ward members Full Council
1. Executive Summary 1.1 The Procurement Team was established in Oct/Nov 2020 with the original Procurement Strategy being approved in December 2020. 1.2 In September 2025 the second Procurement and Commissioning Strategy was approved by Cabinet to cover 2025-2029 and builds on the solid foundations established through the previous strategy. 1.3 During 2025/2026 there was an increase in procurement projects of 15.34% with improvements to the National Procurement Strategy Maturity Assessment of 20%. The 30-day payment, savings and social value KPI’s have all been exceeded.
1.4This is the seventh Procurement Matters report to Cabinet covering 2025/26 and provides: • An update against the Procurement Action Plan in APPENDIX A • APPENDIX B outlines the 2025/26 outcomes and establishes KPI baselines for 2026 onwards. • The fifth self-assessment against the National Procurement Strategy Maturity Assessment in APPENDIX C • An update on the progress made on Procurement projects for 2025/26 in APPENDIX D • The Future Procurement Plan/Pipeline for 2026/27 at APPENDIX E for approval. Please note, all procurements listed in the pipeline will still require budgetary approval and relevant Directorate/Leadership approval based on the Contract Procedure Rules. • An update on Modern Slavery and Human Trafficking in 2025/26. • An update of Social Value progress for 2025/26 at APPENDIX F. • An update on the commencement and implementation of the Procurement Act 2023. 2. Recommendations 2.1. To review the contents of this report and the progress against planned actions in the Action Plan for 2025/26, Key Performance Indicators for 2025/26, the updated self-assessment against the National Procurement Strategy and progress on Procurement projects for 2025/2026. 2.2. Approval is sought to delegate authority to the relevant Cabinet Member and Director of Finance, Environment and Community (S151) to approve the Future Procurement Plan/Pipeline for 2026/27, as set out in APPENDIX E. This will enable procurement exercises to proceed, with contract awards being approved either through a Cabinet Member Decision or Cabinet Approval, as appropriate. 2.3. To review the update on Modern Slavery and Human Trafficking for 2025/26. 2.4. To approve the suggested amendments to KPI’s.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.