1.1To provide members with a progress report on the strategic projects, against their milestones for the third quarter of 2017/18.
2. Programme Summary
2.1There are currently 20 strategic projects being monitored.
2.218 projects are currently on track in terms of their physical and financial milestones and risk profiles.
Of these 8 projects have been completed and are currently awaiting a Post Implementation Review to be submitted and signed off.
2.3There are no projects off track in terms of all three of the areas of monitoring: physical progress, financial position or risk analysis.
2.4There are 2 projects currently off track in either one or two of the areas of monitoring above and beyond just a missing PIR.
CCTV Upgrade – Works schedule, Staff Training, and contracts milestones have missed deadlines but work is drawing to an end. Compulsory Acquisition - 13 Albany Terrace – 5 missed milestones, primarily relating to the legal aspects
It has been concluded that there are no projects of sufficient concern to bring to CMT’s attention.
3. New Projects Approved
3.11 new project was reviewed and recommended to the Executive for approval in the third quarter.
Land and Buildings Acquisition
This project is an outcome of the Asset Rationalisation report presented to the Executive on 8th January 2018.
The project is to purchase a piece of land and building under construction within the city that is expected to generate surplus revenue income for the Council. This scheme was reported to Executive on 8th January 2018 (minute no.112).
4. Completed Projects and those awaiting PIR’s
4.1Where it is felt appropriate and beneficial for continuous improvement at the conclusion of a project a completion report and post implementation review (PIR) will be produced. Once they are received and reviewed a project is considered to be complete.
4.2Strategic Projects awaiting completion of a PIR
There are eight projects which have completed their defined actions and just now await the completion of a PIR
Car Park Safety - Broadgate Car Park improvements New Build Scheme – Birchwood Bungalows, 20 new build affordable units Phase 2 Proposed alterations – City Hall improvements Replace CMS Depot Master – (Servitor project) updated software St Botolphs Court – Modernisation project at Sheltered Housing Complex New Surface Car Parks – Purchase of two new surface car parks in the city
The following projects have submitted an initial PIR, but additional data was requested, so they will be finalised in the next quarter
DR and back up Bereavement Services improvements to facilities
4.3There were no projects signed off as completed during the third quarter.
5. Mega Project Update – Western Growth Corridor
5.1The public consultation on the proposed masterplan ended on 15 November 2017 and this feedback is being fully considered alongside the results of the updated highway traffic modelling work which we received at the beginning of January 2018.
The key concern from the consultation has been the traffic impact so it is important to ensure that the most suitable transport and movement strategy is identified and incorporated into the Masterplan. Once this has been agreed in principle with the statutory organisations an updated version of the masterplan will be produced.
At this point, a revised project plan (including a timetable for delivery, cost plan and a schedule of proposed Member briefings and public consultation/workshops) will be prepared for consideration by the Executive (expected to be in early Summer 2018).
5.2Mega Project Update – Transport HUB
Multi Storey Car Park
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Strategic Projects Implementation: Quarter 3Report | 87 KB | DownloadRead as text |
Follow Performance Scrutiny Committee at Lincoln and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Aug 2026 | Confirmation of Minutes - 9 July 2026RESOLVED that the minutes of the meeting held on 9 July 2026 be confirmed subject to the following amendment: - Counc... | Decided | Open |
| 13 Aug 2026 | To Receive the Minutes of Housing Scrutiny Sub-Committee - 4 June 2026RESOLVED that the minutes of the Housing Scrutiny Sub-Committee meeting held on 4 June 2026 be received. | Decided | Open |
| 13 Aug 2026 | Financial Performance - Quarterly MonitoringRESOLVED that this item be deferred to the next meeting of the Performance Scrutiny Committee. | Deferred | Open |
| 13 Aug 2026 | Treasury Management & Prudential Code – Quarterly UpdateRESOLVED that this item be deferred to the next meeting of the Performance Scrutiny Committee. | Deferred | Open |
| 13 Aug 2026 | Income and Arrears MonitoringRESOLVED that the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.