Decision (1) That the Council maintains its first approach to charge developers, making a developer responsible for bin provision costs in alignment with previously agreed fees and charges. (2) That, where a developer refuses to pay, this cost be passed to residents directly, explaining the reason for the charge. None. In October 2017 the Executive agreed to charge developers for bin provision and agreed a set of charges as set out at paragraph 5.1 of the report. The Council would continue to ask developers to cover these costs but in those cases where developers refused to pay the new residents would be approached directly to pay, explaining that they were being asked due to the refusal of the developer to pay. It was noted that the legislation permitting charging of residents was clear and beyond challenge. A comparison of the state of charging by some other authorities was attached to the report at Appendix A. Whilst not all Councils charged, it was understood that many other authorities did and of those that did not many were in the process of considering this option due to financial pressures. It was expected that this would be standard practice in due course.
Word for word from the decision Lincoln published for this meeting.Source: democratic.lincoln.gov.uk
1.1To provide a clarification to a decision taken by Executive last year in relation to the costs of providing waste bins in new developments, making clear that this is for the provision of the bin only, not the ongoing service, and that developers are the first choice for payment.
Executive summary
2.1In October 2017 the Executive received a report on the costs incurred by the Council for the supply of waste/recycling receptacles. The report noted that across the city the cost was considerable, and that this was having an adverse impact on budgets. It noted that an alternative way of considering the issue was for developers to provide the bins as a part of the development, at their cost.
2.2This report therefore seeks agreement to maintain the original approach to developers at the outset, but where a developer refuses to pay, then the council is to write to the new occupants of the properties explaining that the developer has refused to pay, and inviting them to either pay themselves, or to take the matter up with their developer.
Background
3.1As has been the backdrop for budget planning in recent years, the Council continues to operate in a difficult financial environment. Significant national reforms about future funding allocations to local government, and the implementation of new funding mechanisms, are set to detrimentally impact on the Council’s financial position. In addition, the impact of Brexit and the consequent impact on the economic and political landscapes poses significant uncertainty for local government resources.
3.2Furthermore the Council continues to face financial challenges due to changes in the use of and demand for its services as well as escalating costs. In response to these funding reductions and pressures, the Council is undertaking continual reviews of its services, which has led to a reduction in its annual expenditure. However, the Council still has further significant annual savings to deliver if it is to meet the targets set out in the current MTFS. 4.0 Service background
4.1The Council currently provides waste services by way of a tailored service. That is to say it considers the needs of a property’s residents, and the practicalities of collection, before deciding the type of receptacle for the waste.
4.2When a new property is built or a property is redeveloped, the Council should have input to what waste storage system is appropriate. When the property is sold or let, the Council provides suitable waste disposal receptacles as required. This may be bags, 140 litre, 240 litre, or communal 660 litre or 1100 litre bins.
4.3This report identifies the burden that this places on the Council’s existing bin purchase budget, which frequently overspends, and suggests making a charge to developers of new or redeveloped properties where a new waste bin system is required.
4.4In developing a way forwards various options have been explored, including S106 and making bin provision a planning condition. Advice is that whilst it couldn’t be a planning condition, there is potential as a S106 requirement, provided it could be justified under the Central Lincolnshire plan. However, this is in draft currently and will take some time to bring to fruition, with a currently undetermined timescale. It is therefore suggested that an alternative scheme is developed in the meantime, as set out below.
5.0The Proposal
5.1In October 2017 the Executive agreed to charge developers for bin provision. It agreed a set of charges, including delivery.
140 litre bin £22 240 litre bin £26 Communal /1100 litre bin £149
Delivery £10 (up to four bins to one address) or per communal bin.
No concessions.
When considering the overall purchase price of a residential property, and the many professional fees also involved, the above represents a very small additional cost.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Confirmation of Minutes - 18 August 2026RESOLVED that the minutes of the meeting held on 18 August 2026 be confirmed and signed by the Chair as a correct rec...
Updated Rechargeable Repairs PolicyDecision 1. That the policy be implemented and briefing sessions to all staff within customer services and housing on...
Exclusion of the Press and PublicRESOLVED that the press and public be excluded from the meeting during consideration of the following item of busines...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.