City of Lincoln Council
Executive, Monday 17 October 2022 at 6.00pm

Western Growth Corridor-Next Steps

Approved Executive 6 papers

Executive approved this item on Monday 17 October 2022. Below is the council's own wording, with the papers it was decided on.

Item44

Resolved

Decision 1. That procurement by officers be commenced on the Tritton Road bridges and Spine Road so that the Council would still be able to meet the timescales involved in delivering the LUF2 funding requirements should the Council be awarded and accept any funding offer made. 2. That the Council uses compulsory purchase powers to acquire the two identified strips of unregistered land to enable the commencement of the opening-up infrastructure works of Phase 1a of the Western Growth Corridor development. 3. That the power to override third party rights and easements under section 203 of the Housing and Planning Act 2003 be authorised. 4. That authority be delegated to the Strategic Director for Major Developments and the City Solicitor to approve the final form of the application and use of the required compulsory purchase order powers and the decisions about the extent of the land or rights over land to be acquired provided that these were necessary for the purposes of delivering Western Growth Corridor and were within the area identified on the plan, as detailed at Appendix A of the report. 5. That progress to date and the activities outlined in the report to further progress the scheme be supported. None. The Western Growth Corridor (WGC) represented one of four sustainable urban extension (SUE) areas around Lincoln identified and promoted in the Central Lincolnshire Local Plan for development to meet the area’s growth projections up to 2036. It was the closest SUE to the city centre and had the greatest opportunity to achieve real sustainability both within the development and for the surrounding communities. It was the major area for housing and employment growth in the city itself and a key part of delivering Lincoln’s Growth Strategy over the next 20 years. The Central Lincolnshire Local Plan adopted in April 2017 following a robust and thorough examination had now approved the principle for development of the site. Having established the principle of development, the next stage was to consider the key building blocks of the development at a broad rather than a detailed level. The Local Plan allocation was for a new neighbourhood of 3,200 new homes (20% affordable), twenty hectares of commercial/employment space, a new Leisure Village, improvements in accessibility and range of green space, flood mitigation improvements, remediation of the former tip ... view the full minutes text for item 44.
Word for word from the decision Lincoln published for this meeting. Source: democratic.lincoln.gov.uk

Follow this further

Built from Lincoln's papers

What the report saysPro

Report to Executive

Purpose of report

1.1To update Executive on progress since securing planning consent in January 2022 and to seek authority to proceed with the next stages of the delivery of the Western Growth Corridor (WGC) development including:

- Starting the procurement process for the design and build of the Tritton Road bridges and spine road that would complete the transport infrastructure through the site, so that delivery timescales could be met should funding for the Tritton Road bridges from Levelling Up Fund Round 2 (LUF2) be secured; and - The use of Compulsory Purchase Order (CPO) powers to enable delivery of Phase 1a of the development.

Background

2.1The Western Growth Corridor (WGC) is one of 4 sustainable urban extension (SUE) areas around Lincoln identified and promoted in the Central Lincolnshire Local Plan for development to meet the area’s growth projections up to 2036. It is the closest SUE to the city centre and has the greatest opportunity to achieve real sustainability both within the development and for the surrounding communities. It is the major area for housing and employment growth in the city itself and is a key part of delivering Lincoln’s Growth Strategy over the next 20 years.

2.2The Central Lincolnshire Local Plan adopted in April 2017 following a robust and thorough examination has now approved the principle for development of the site. Having established the principle of development, the next stage was to consider the key building blocks of the development at a broad rather than a detailed level. The Local Plan allocation is for a new neighbourhood of 3,200 new homes (20% affordable), 20 hectares of commercial/employment space, a new Leisure Village, improvements in accessibility and range of green space, flood mitigation improvements, remediation of the former tip and a range of improved connectivity (roads, cycle paths and pedestrian routes).

2.3The City Council is a significant landowner (owning about 60% of the site included within the proposed masterplan area) and has been leading on bringing forward development of the area in a viable, sustainable and deliverable way since 2016. WGC is a key priority within the City Council’s Vision 2025 (and Vision 2020 before that) and delivers across all the Council’s priorities and objectives. It is also the single biggest development area within the City boundary.

2.4The remaining development land on WGC is owned by Lindum Western Growth Community Limited (LWGC) which is a subsidiary of the locally owned and based construction/development company Lindum Group. Together the Council and LWGC submitted a planning application for the whole development on 03 April 2019.

2.5Outline planning consent for the wider scheme and detailed consent for the two main access points into the development at Skellingthorpe Road and Tritton Road was obtained on 20 January 2022.

2.6The Council and LWGC work jointly together as the two landowners (the developer team) to shape and progress the development including jointly commissioning work from expert consultants, identifying funding and financing opportunities, reviewing viability and delivery.

3. Project Delivery – Progress Update

3.1Planning Consent: Outline planning consent for the overall development and detailed planning consent for the two access points into the development at Skellingthorpe Road and Tritton Road was considered on 12 January 2022. Following the decision of the Secretary of State to not call in the application, a decision notice was issued on 20 January 2022. A judicial review period then followed which ended without further challenge in March 2022.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
20221017 Executive Next Steps Final_Report 288 KB DownloadRead as text
PDF
Scheme Red Line PlanAppendix A 982 KB Download
PDF
Order LandsAppendix B 364 KB Download
PDF
Draft Statement of Reasons finalAppendix C 565 KB Download
PDF
Draft OrderAppendix D 163 KB Download
PDF
Tritton Road bridges location planAppendix E 177 KB Download

At this meeting

Whole meeting

Who was there

6 of 6 attended
RM
Councillor Ric MetcalfeChair, present
DN
Councillor Donald NannestadVice-Chair, present
CB
Councillor Chris BurkeCommittee Member, present
SB
Councillor Sue BurkeCommittee Member, present
BB
Councillor Bob BushellCommittee Member, present
NM
Councillor Neil MurrayCommittee Member, present

On this subject at Lincoln

Search all
  1. Western Growth Corridor-Next StepsThis decision
  2. Planning Committee Arrangements - Western Growth CorridorDecided
  3. Western Growth Corridor, Skellingthorpe Road, Lincoln - SubstationApproved
  4. Western Growth Corridor Scheme DeliveryApproved
  5. Planning Committee Protocol - Western Growth Corridor ApplicationApproved
  6. Western Growth Corridor - Planning Application SubmissionApproved

More from Lincoln Executive

All decisions
MeetingDecisionOutcome
15 Sep 2026 Confirmation of Minutes - 18 August 2026RESOLVED that the minutes of the meeting held on 18 August 2026 be confirmed and signed by the Chair as a correct rec... Decided Open
15 Sep 2026 Variation to the Constitution – Responsibility for Functions; Adoption of National Scheme of Delegation and Amendments to Planning ProtocolsDecision 1. That a variation to Part 3 – Responsibility for Functions of the Council’s Constitution to reflect the ch... Approved Open
15 Sep 2026 Updated Rechargeable Repairs PolicyDecision 1. That the policy be implemented and briefing sessions to all staff within customer services and housing on... Approved Open
15 Sep 2026 Playground FundingDecision That the progression of this new project and inclusion of a capital estimate of £511,335 in the General Inve... Approved Open
15 Sep 2026 Exclusion of the Press and PublicRESOLVED that the press and public be excluded from the meeting during consideration of the following item of busines... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies