Western Growth Corridor Scheme Delivery

Approved Executive 1 paper

Executive approved this item on Monday 5 June 2023. Below is the council's own wording, with the papers it was decided on.

Item13

Resolved

Decision 1. That the use of LUF2 funds to support the first stage of design work in respect of the proposed bridges and road link, which would form the eastern access point into the Western Growth Corridor site from Tritton Road be approved. 2. That the proposed delivery arrangements to progress this work via the appointment of a lead contractor, procured under the Pagabo Civils Framework be approved. None were considered. On 20 th February 2023, a report entitled was presented to Executive, setting out the proposed delivery arrangements for the Skellingthorpe Road – Southern Access works and for a first phase of housing delivery to follow. The report also acknowledged the award of £20m funding under the Levelling Up Fund Round 2 (LUF2), which had been secured by the City Council in conjunction with Karl McCartney, to support the delivery of the Eastern Access, connecting the site with Tritton Road. This included the construction of a new all vehicular/cycle/pedestrian bridge over the railway and a pedestrian/cycle bridge replacing the existing pedestrian rail crossing at Oak Farm (opposite the new LN6 development). Plans to procure a specialist contractor to undertake the project on a design and build basis were set out, in order to ensure deliverability within the LUF2 programme timescales, as summarised in the following extract: The Council proposes to procure a lead contractor, to undertake the substantive design process to achieve all technical approvals for the bridges and access road. The proposed scope of works would also include the detailed design of the spine road to allow for delivery in the future, if additional funding can be secured. This detailed design work, would be delivered under a Pre-Construction Services Agreement (PCSA) with the purpose being to demonstrate the technical and financial feasibility of the works, to enable the Council to enter into a contract for delivery on a design and build basis. The decision to proceed with a full contract for delivery would be subject to Executive approval ... view the full minutes text for item 13.
Word for word from the decision Lincoln published for this meeting. Source: democratic.lincoln.gov.uk

Follow this further

Built from Lincoln's papers

What the report saysPro

Report to Executive

Purpose of report

1.1To seek authority to proceed with the first stage of design work, in respect of the proposed bridges and road link, which will form the eastern access point into the Western Growth Corridor site from Tritton Road.

1.2This work is proposed to be funded by the Levelling Up Fund Round 2 (LUF2) grant and is necessary to determine the technical and financial feasibility of the project, prior to the technical design and approval stage.

1.3The decision to proceed with the technical design and ultimately, with the delivery of the project, will be subject to subsequent Executive approvals in each case.

1.4This proposal follows the report to Executive of 20th February 2023, which set out the plans for the early-phase delivery of the Western Growth Corridor project.

Background

2.1On 20th February 2023, a report entitled Western Growth Corridor Scheme Delivery was presented to Executive, setting out the proposed delivery arrangements for the Skellingthorpe Road – Southern Access works and for a first phase of housing delivery to follow.

2.2The report also acknowledged the award of £20m funding under the Levelling Up Fund Round 2 (LUF2), which had been secured by the City Council in conjunction with Karl McCartney, to support the delivery of the Eastern Access, connecting the site with Tritton Road. This includes the construction of a new all vehicular/cycle/pedestrian bridge over the railway and a pedestrian/cycle bridge replacing the existing pedestrian rail crossing at Oak Farm (opposite the new LN6 development).

2.3Plans to procure a specialist contractor to undertake the project on a design and build basis were set out, in order to ensure deliverability within the LUF2 programme timescales. This is summarised in the following extract:

The Council proposes to procure a lead contractor, to undertake the substantive design process to achieve all technical approvals for the bridges and access road. The proposed scope of works would also include the detailed design of the spine road to allow for delivery in the future, if additional funding can be secured. This detailed design work, would be delivered under a Pre-Construction Services Agreement (PCSA) with the purpose being to demonstrate the technical and financial feasibility of the works, to enable the Council to enter into a contract for delivery on a design and build basis. The decision to proceed with a full contract for delivery would be subject to Executive approval at the end of the pre- construction phase. This pre-construction work is proposed to be funded via the main LUF2 grant, subject to the Memorandum of Understanding (MoU), which will set out the terms for this funding.

(Western Growth Corridor Scheme Delivery, Executive Report, 20th February 2023, Section 4.5)

3. Eastern Access – Funding & Progress

3.1The Council confirmed its acceptance of the LUF2 funding award on 1st March 2023, via a Memorandum of Understanding (MoU) with the Department for Transport.

3.2Officers then proceeded with a procurement exercise to secure a lead contractor for the project. This was undertaken via the Pagabo Civils Framework, and a preferred contractor, with extensive experience in delivering road, rail and bridge structures, has now been selected.

3.3Following the selection and due diligence process, the Council now proposes to enter into a Pre-Construction Services Agreement with the preferred contractor to undertake the design of the structures and access road in stages as follows:

Stage 1 – Design Review & Value Engineering Opportunities Stage 2 – Technical Approval – Proposed Submission Stage 3 – Technical Approval & Final Contract for Works

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Western Growth Corridor Scheme DeliveryReport 258 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 6 attended
RM
Councillor Ric MetcalfeChair, present
DN
Councillor Donald NannestadVice-Chair, present
SB
Councillor Sue BurkeCommittee Member, present
BB
Councillor Bob BushellCommittee Member, present
RL
Councillor Rebecca LongbottomCommittee Member, present
NT
Councillor Naomi TweddleCommittee Member, present

On this subject at Lincoln

Search all
  1. Western Growth Corridor Scheme DeliveryThis decision
  2. Planning Committee Arrangements - Western Growth CorridorDecided
  3. Western Growth Corridor, Skellingthorpe Road, Lincoln - SubstationApproved
  4. Western Growth Corridor-Next StepsApproved
  5. Planning Committee Protocol - Western Growth Corridor ApplicationApproved
  6. Western Growth Corridor - Planning Application SubmissionApproved

More from Lincoln Executive

All decisions
MeetingDecisionOutcome
15 Sep 2026 Confirmation of Minutes - 18 August 2026RESOLVED that the minutes of the meeting held on 18 August 2026 be confirmed and signed by the Chair as a correct rec... Decided Open
15 Sep 2026 Variation to the Constitution – Responsibility for Functions; Adoption of National Scheme of Delegation and Amendments to Planning ProtocolsDecision 1. That a variation to Part 3 – Responsibility for Functions of the Council’s Constitution to reflect the ch... Approved Open
15 Sep 2026 Updated Rechargeable Repairs PolicyDecision 1. That the policy be implemented and briefing sessions to all staff within customer services and housing on... Approved Open
15 Sep 2026 Playground FundingDecision That the progression of this new project and inclusion of a capital estimate of £511,335 in the General Inve... Approved Open
15 Sep 2026 Exclusion of the Press and PublicRESOLVED that the press and public be excluded from the meeting during consideration of the following item of busines... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies