1.1To present to PSC the first quarter’s performance (up to 30th June), on the Council’s:
General Fund Housing Revenue Account Housing Repairs Service Capital Programmes
And to seek approval for changes to the capital programmes.
1.2Financial Procedure Rules require members to receive, on a quarterly basis, a report prepared jointly by the Chief Finance Officer and Corporate Management Team commenting on financial performance to date. This report is designed to meet this requirement.
2.1This report covers the General Fund Revenue, Housing Revenue Account budgets and Investment Programmes for the current financial year.
2.2While there are still a number of variables, which are subject to a level of uncertainty, based on the latest set of assumptions as at the end of the first quarter (up to 30 June) the forecast financial position of the Council for 2024/25 is:
2024/25 Revenue Accounts Budget Forecast @ Variance @ Q1 Q1 £’000 £’000 £’000 General Fund – Contribution (to)/from (147) (151) (4) balances Housing Revenue Account – Contribution 101 (506) (608) (to)/from balances Housing Repairs Service – (surplus)/deficit 0 355 355* *any HRS variance is repatriated to the HRA and as such included within the HRA balances above 2024/25 Capital Programmes Opening Revised Movement Budget Budget @ @ Q1 £’000 Q1 £’000 £’000 General Investment Programme 23,151 23,455 304 Housing Investment Programme 22,763 17,650 (5,112)
2024/25 Balances Budgeted Forecast Forecast Balance @ Balance @ Movement 31/03/25 31/03/25 £’000 £’000 £’000 General Fund Balances (2,392) (2,396) (4) Housing Revenue Account Balances (1,030) (1,638) (608)
2024/25 Reserves Opening Forecast Forecast Balance @ Balance @ Movement 01/04/24 31/03/25 £’000 £’000 £’000 General Fund Earmarked Reserves (8,234) (7,085) 1,149 HRA Earmarked Reserves (4,507) (4,289) 218
2.3The detailed financial position is shown in sections 3-7 and accompanying appendices.
3. General Fund Revenue Account
3.1For 2024/25 the Council’s net General Fund revenue budget was set at £15,427,670 including a planned contribution to balances of £146,820 resulting in an estimated level of general balances at the year-end of £2,391,979 (after allowing for the 2023/24 outturn position).
3.2The General Fund Summary is currently projecting a forecast underspend of £3,530 (Appendix A provides a forecast General Fund Summary), resulting in general balance at the year-end of £2,395,509. This position maintains balances above the prudent minimum of c.£1.5-£2m.
3.3There are a number of forecast year-end variations in income and expenditure against the approved budget, full details of the main variances are provided in Appendix B while the table below sets out the key variances: General Fund Forecast Forecast year-end key variances: £’000 National proposed pay award settlement 184 Increased non recoverable supported accommodation and other 292 housing benefit costs, reduction in DWP grant funding and unbudgeted Discretionary Housing Payment Trend in reducing crematorium income shortfall plus additional 250 interim management & administration costs Less: Release of Inflation Volatility reserve (184) Reduced Borrowing Costs (310) Increased Investment Interest (97) Net other variances (139) Overall forecast budget deficit/(surplus) (4)
3.4A number of the key forecast variances have arisen as a result of external variables e.g. economic factors, service demands etc, which differ from the budgeted assumptions. These main variances, both positive and negative cover:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Financial Performance- Quarterly MonitoringReport | 970 KB | DownloadRead as text |
Follow Performance Scrutiny Committee at Lincoln and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Aug 2026 | Confirmation of Minutes - 9 July 2026RESOLVED that the minutes of the meeting held on 9 July 2026 be confirmed subject to the following amendment: - Counc... | Decided | Open |
| 13 Aug 2026 | To Receive the Minutes of Housing Scrutiny Sub-Committee - 4 June 2026RESOLVED that the minutes of the Housing Scrutiny Sub-Committee meeting held on 4 June 2026 be received. | Decided | Open |
| 13 Aug 2026 | Financial Performance - Quarterly MonitoringRESOLVED that this item be deferred to the next meeting of the Performance Scrutiny Committee. | Deferred | Open |
| 13 Aug 2026 | Treasury Management & Prudential Code – Quarterly UpdateRESOLVED that this item be deferred to the next meeting of the Performance Scrutiny Committee. | Deferred | Open |
| 13 Aug 2026 | Income and Arrears MonitoringRESOLVED that the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.