Resolved
RESOLVED that the Strategic Risk Register as at the end of the third quarter 2024/25 be noted.
Performance Scrutiny Committee noted this item on Thursday 20 February 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Strategic Risk Register as at the end of the third quarter 2024/25 be noted.
1.1To provide Members with a status report of the revised Strategic Risk Register as at the end of the third quarter 2024/25.
2.1An update of the Strategic Risk Register, developed under the risk management approach of ‘risk appetite’, was last presented Members in November 2024 and contained fifteen strategic risks.
2.2Since reporting to Members in November, the Strategic Risk Register has been refreshed and updated by the Risk Owners and Corporate Management Team. This update has reviewed each risk in terms of the level of assessed risk, control measures in place and mitigating actions required, and has identified that there have been some positive movement in the Risk Register. It has also considered whether there are new risks that need to be assessed.
2.3This updated register is contained with Part B of this agenda, it contains fifteen strategic risks which are listed below, along with details of relevant mitigations.
3. Strategic Risks
3.1The Strategic Risk Register contains fifteen risks, as follows:
1) Failure to engage & influence effectively the Council’s strategic partners, council staff and all stakeholders to deliver against the Council’s new Vision 2030.
2) Failure to deliver a sustainable Medium-Term Financial Strategy that supports delivery of the Council’s Vision (specifically in relation to the General Fund).
3) Failure to deliver the Towards Financial Sustainability Programme.
4) Failure to ensure compliance with existing and new statutory duties/functions.
5) Failure to protect the local authority's long term vision due to changing structures and relationships in local government and impact on size, scale and scope of the Council. 6) Unable to meet the emerging changes required in the Council’s culture, behaviour and skills to support the delivery of the council’s vision, transformational journey to one Council approach and service delivery.
7) Insufficient levels of resilience, capability and capacity exist in order to deliver key strategic projects & services within the Council.
8) Decline in the economic prosperity within the City Centre.
9) Failure to deliver key strategic projects.
10) Failure of the Council’s key contractors and partners to remain sustainable and continue to deliver value for money to the Council.
11) Failure to protect the vulnerable in relation to the Council’s PREVENT and compliance with safeguarding and domestic abuse duties.
12) Failure to mitigate against the risk of a successful cyber-attack against the council
13) Impacts of the uncertainty of Government’s policies on migration policy, asylum dispersal, early prison release etc on the Council’s service delivery, capacity and MTFS as well as the impacts on housing, communities and the economic vitality of the City Centre.
14) Failure to deliver critical services in an emergency situation.
15) Failure of service delivery leading to reputational impacts on the Council and adverse financial implications.
3.2Each risk includes a number of control measures in order to avoid, seek, modify, transfer or retain the risks, these include actions already in place and further actions required with the relevant timescales for implementation. These control actions continue to be implemented, and the risks managed accordingly.
3.3Each risk is evaluated in terms of the level of assessed risk (likelihood and impact), taking into consideration any changes in control measures and the wider environment in which the Council operates. While there have been some positive movements in terms of the implementation of control measures, there has also been external factors which has resulted in a change to the assessed levels of likelihood and/or impact of two of the risks, as follows:
Risk 1 has increased from Amber: Possible/Major to Amber: Probable/Major.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Strategic Risk Register: Quarterly ReviewReport | 330 KB | DownloadRead as text |
Follow Performance Scrutiny Committee at Lincoln and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Aug 2026 | Confirmation of Minutes - 9 July 2026RESOLVED that the minutes of the meeting held on 9 July 2026 be confirmed subject to the following amendment: - Counc... | Decided | Open |
| 13 Aug 2026 | To Receive the Minutes of Housing Scrutiny Sub-Committee - 4 June 2026RESOLVED that the minutes of the Housing Scrutiny Sub-Committee meeting held on 4 June 2026 be received. | Decided | Open |
| 13 Aug 2026 | Financial Performance - Quarterly MonitoringRESOLVED that this item be deferred to the next meeting of the Performance Scrutiny Committee. | Deferred | Open |
| 13 Aug 2026 | Treasury Management & Prudential Code – Quarterly UpdateRESOLVED that this item be deferred to the next meeting of the Performance Scrutiny Committee. | Deferred | Open |
| 13 Aug 2026 | Income and Arrears MonitoringRESOLVED that the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.