Resolved
RESOLVED that the progress made under the Remarkable Place Vision strategic theme alongside the more detailed reports from both ... view the full minutes text for item 36.
Performance Scrutiny Committee decided this item on Thursday 25 September 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the progress made under the Remarkable Place Vision strategic theme alongside the more detailed reports from both ... view the full minutes text for item 36.
Appendix A Remarkable Place Monitoring Table – Updated August 2025
Project name Project Original Milestones CMT Champion update of RAGB Budget and Additional manager progress against milestones spend to notes date Sincil Bank streets for people Paul Key Environmental based Priorities: theme Carrick - create green spaces in the area PH - Councillor Joshua Wells - create green corridors through the area, - plant urban trees, - alter the traffic flows through the area to remove “rat runs” and hand the streets back to local residents.
Focus is on:
• Sincil Bank Residents Parking Scheme –With regards to further expansion - early kerbside assessments have been undertaken to ascertain levels of commuter parking in adjacent areas. This work has been assessed and a request to LLC has now been made for the RPS extension (13/06/2025).
• Work has progressed to develop Sincil Bank as a green corridor. This will see the provision of a new green corridor for cyclists and pedestrians along Sincil Bank. The works include the provision of a northbound cycleway; planted areas; and the resurfacing of several sections of footway and carriageway. There is also be a revised one-way system that will work in conjunction with the residents parking scheme.
Latest position is at:
Lincoln Sincil Bank rejuvenation – Lincolnshire County Council As of late August 2025, the Highways element of this scheme is now complete but the planters which should be installed on Sincil Bank before the end of June have been delayed until end of October 2025 as they have required modification due to uneven ground conditions at the chosen locations. Contractor will maintain them for first 12 months and LCC then exploring options for on-going maintenance.
Alongside these improvements, final designs have been received to improve four of the key gateways into the area) Portland St/High Street, Portland St/Canwick Rd, Tentercroft St/Sincil Bank and St Appendix A Remarkable Place Monitoring Table – Updated August 2025
Project name Project Original Milestones CMT Champion update of RAGB Budget and Additional manager progress against milestones spend to notes date Catherines/football club). As of late August 2025 - gateway signage and pocket park at end of Portland Street still to be delivered. Planned now for end of November 2025.
Events programme for the City Claire Events for 2025 agreed Programme for 2025: Green £275k pa McDowall and signed off. (incl • Festival of History 3rd 5th provision for May- successfully annual PH - Councillor Joshua Wells delivered. Xmas lights). • Lincoln Live 30th Aug -1st Sept - successfully delivered.
• Focus now on developing the approach for Christmas 2025.
Supported events the Council are involved with through sponsorship:
• Pride • Steampunk.
Greening the city: Steve Bird Hope Wood Update 1/9/25: Green From April 2025 PH - Councillor Rebecca Longbottom Cut and clear completed. £5,000pa revenue Preparations for Autumn/winter funding from 2025 taking place. The new Appendix A Remarkable Place Monitoring Table – Updated August 2025
Project name Project Original Milestones CMT Champion update of RAGB Budget and Additional manager progress against milestones spend to notes date expanded orchard planting existing already being considered. budgets.
Simon Greening the City Centre Five core demonstration projects Amber Walters remain on the ‘wish list’:
a) Small parklet outside Bus Station b) Removal of planters on High Street c) Re branding/re- purposing of green spaces in city centre. d) University campus masterplan and interface of green spaces into city centre e) Support with crowd funding promotion for additional bio havens around Brayford pool.
HLF bid for Nature Towns & Cities was submitted on 14th April but bid was unsuccessful.
Further works with partners commissioned to look at environmental and street scape improvements on High Street pedestrian area. It will incorporate greening Appendix A Remarkable Place Monitoring Table – Updated August 2025
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appx A Remarkable Place Monitoring SheetReport | 146 KB | DownloadRead as text |
PDF |
Vision 2030: Remarkable Place Progress ReportReport | 122 KB | Download |
Follow Performance Scrutiny Committee at Lincoln and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Aug 2026 | Confirmation of Minutes - 9 July 2026RESOLVED that the minutes of the meeting held on 9 July 2026 be confirmed subject to the following amendment: - Counc... | Decided | Open |
| 13 Aug 2026 | To Receive the Minutes of Housing Scrutiny Sub-Committee - 4 June 2026RESOLVED that the minutes of the Housing Scrutiny Sub-Committee meeting held on 4 June 2026 be received. | Decided | Open |
| 13 Aug 2026 | Financial Performance - Quarterly MonitoringRESOLVED that this item be deferred to the next meeting of the Performance Scrutiny Committee. | Deferred | Open |
| 13 Aug 2026 | Treasury Management & Prudential Code – Quarterly UpdateRESOLVED that this item be deferred to the next meeting of the Performance Scrutiny Committee. | Deferred | Open |
| 13 Aug 2026 | Income and Arrears MonitoringRESOLVED that the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.