Package X and Package Y Public Realm Update

Noted Executive 1 paper

Executive Board noted this item on Friday 13 June 2003. Below is the council's own wording, with the papers it was decided on.

Item37

Resolved

Resolved that – (i) the progress of the project be noted; (ii) authority be granted to adjust the City Council’s capital programme to reflect the revised expenditure profile on these projects to a maximum of £5,535,909 for Package X and £4,609,546 for Package Y phased over the financial years 2003/04 (Package X £4,624,926 and Package Y £3,851,340) and 2004/05 (Package X £910,983 and Package Y £758,206); (iii) it be confirmed that all areas within the Core Area Public Realm Phase 1 (known as Package X and Package Y) shall be maintained to the refurbished upgraded standard for a minimum of ten years from Practical Completion. Maintenance shall be in accordance with an agreed maintenance plan and shall include: · prompt repairs to any damaged infrastructure within the adopted highway including paving, street furniture, lighting and public art; · maintenance of the Williamson Square Fountain in an operational condition; and · maintenance of trees; (iv) Land and Development Services be instructed to negotiate, and on completion of an agreement that satisfies LCC requirements, grant a lease under the Public Health Act, 1875 to the Hewitts Place Management Company for a period of 10 years from Practical Completion to manage and maintain the new square; (v) in the event that the lease agreement for the management of Hewitts Place cannot be satisfactorily negotiated, the square be adopted under Section 38 of the Highways Act and, Enterprise-Liverpool maintain the square to an agreed standard through the highways maintenance agreement; (vi) the Executive Director (Regeneration) be authorised (subject to the receipt of offer letters from SRB6, NWDA and GONW and hence having a complete funding package) to - · accept a grant up to a maximum of £5,535,909 for Package X and £4,609,546 for Package Y phased over the financial years 2002/03 and 2003/04 to contribute towards the full cost of the Project (Stage 3); · accept tenders of £5,186,268 for Package X and £4,318,693 for Package Y for work contracts; and (vii) commit expenditure up to a maximum of £5,535,909 for Package X and £4,609,546 for Package Y for both work contracts and fees.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 17 pages

Executive summary

Purpose of report

1.1The purpose of this report is to:

I. Update Members on the progress of the public realm scheme known as Package X and Package Y including programme, design and consultation.

II. To advise Members of and seek approval for the revised financial implications and contract sums for both Package X and Package Y.

III. To advise Members of and seek approval for various management and maintenance mechanisms associated with the project.

Background

2.1A report (EDR/422/2002) was submitted to Members in November 2002 that provided a background to the Package X and Y public realm project and sought Members approval to implement the scheme.

2.2Following this report, the project has progressed to detail design, secondary consultation and tender action. Funding bids were submitted and progressed and costs have been refined as the design developed. A series of site visits and design workshops with Members have also taken place to develop the design proposals.

3 Project Update

(a) Programme Update

3.1Tenders were issued in January 2003 and after submission in March, were evaluated on both quality and price by the respective consultant teams via the LCC Procurement Unit. Short-listed contractors were then interviewed and the appraisal was completed on 4 April. The two successful contractors have now been provisionally nominated.

3.2Detailed funding bids were submitted to the North West Development Agency (NWDA) and Government Office for the North West (GONW) (via the European Team) in November 2002. The City Focus Board approved the SRB6 element on 30 September 2002 (subject to the NWDA approval process). The NWDA carried out the technical check for all bids on behalf of NWDA, GONW and City Focus. All final funding bids have now been approved and LCC are awaiting formal offer letters.

3.3Subject to the approval of this report and acceptance of offer letters, LCC will be able to award and let contracts in early June leading to a 6 week mobilisation period and a start on site in July 2003.

3.4Both Package X and Y have a 40 week contract period resulting in a completion date of March 2004 for Package Y, and May 2004 for Package X. The latter is delayed due to an eight week Christmas shopping shut down period in the Williamson Square/Cavern Quarter retail areas and, a weeks closedown for the Mathew Street festival/Beetles week celebration.

3.5A summarised programme is contained in the Timescale for Action section.

(b) Design Update

Detail design drawings and sample materials are available for Members at request.

Package X

3.6Following on from the previous report (ERD/422/2002), Members have convened to discuss the design of Williamson Square including the exact location of the fountain and text to be inlaid into the granite surround. The text will embody a poem especially commissioned for the square. An approach is currently being made to a well known local poet.

3.7Two trial samples have been constructed/erected to help develop the detailed design; a sample of the overhead lighting system has been erected in Matthew Street within the Cavern Quarter (with favourable response from the Assistant Executive Member for Regeneration, the Cavern Quarter Gold Zone, LCC Conservation and Liverpool Vision) and, a trial panel of the granite paving is now completed within Williamson Street. Members should note that the granite setts are not the correct colour as it was not available at the time of the trial. Package Y

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Package X and Package Y Public Realm UpdateReport 17 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Package X and Package Y Public Realm UpdateThis decision
  2. Knowledge Quarter Public Realm Package 2: Brownlow Hill and Wilderness Area (A&D/58)Approved
  3. City Centre Movement Strategy – Package 2A Traffic Regulation OrderDecided
  4. City Centre Movement Strategy (CCMS) Package 2a - Waterfront Neighbourhood CommitteeAgreed
  5. City Centre Movement Strategy (CCMS) Package 2aAgreed
  6. CCMS North Package 2Noted

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies