Knowledge Quarter Public Realm Package 2: Brownlow Hill and Wilderness Area (A&D/58)

Approved Executive 1 paper

Executive Board approved this item on Friday 13 March 2009. Below is the council's own wording, with the papers it was decided on.

Item146f

Resolved

Resolved that (i) the proposal for the Knowledge Quarter Public Realm Package 2 Brownlow Hill and Wilderness Area project in the total sum of £2,803,716 be approved. (£400,807 2008/09 funded by NWDA grant & £2,402,909 2009/10 funded by NWDA £2,182,909, LJMU £40,000, Science Park £30,000, LCC £150,000, (This will be first call on the resources to be allocated to the CCMS programme in 2009/10 )); (ii) the Executive Director (Regeneration) be authorised to accept a capital grant from NWDA of up to £2,583,716 subject to the receipt of the offer letter. The City Council will thereby accept the role of accountable body and ensure that the grant is administered appropriately; (iii) the Highways Projects Team Manager be appointed as the nominated officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises; (iv) the Executive Director (Regeneration) be authorised to enter into Contribution Agreements with Liverpool John Moores University of up to £40,000 and with Neptune Developments on behalf of the Science Park of up to £30,000; (v) expenditure on the contract works stages of the project be only incurred after the receipt of confirmation of funding from the relevant bodies upon which this project relies for income and the finalisation of all other relevant documents.; and (vi) on receipt of the grant offer letter - · the City Council’s capital programme be amended to reflect a revised expenditure profile of £400,807 (£400,807 NWDA) in the financial year 2008/09 and £2,402,909 (£2,182,909 NWDA, £70,000 Private contribution and £150,000 LCC) in 2009/10; · authority be given to accept the target cost sum submitted by Birse for the scheme, provided it does not exceed the stated budget, and to let the task order; and · authority be given to commit the expenditure. A&D/59
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 14 pages

Executive summary

Purpose

The purpose of this report is to inform members of the context and design of the Brownlow Hill and Wilderness Area public realm project and to seek authority to accept grant funding for the project.

1.0Background and Project Context

The Brownlow Hill and Wilderness Area public realm project has been developed in a partnership between Liverpool City Council, Liverpool Vision, Liverpool John Moores University, the Science Park, University of Liverpool and the Archdiocese.

The proposed project is Phase Two of a programme of public realm improvements (included in Liverpool Vision’s transitional programme), which will deliver improvements to public realm within the Liverpool Knowledge Quarter and its connections to the City Centre. The wider programme of improvements has been identified and prioritised through the NWDA funded Urban Design Framework and Public Realm Implementation Plan for the Knowledge Quarter produced by consultants URBED.

Public realm improvement work will include improvements to Brownlow Hill, a new public space between the Liverpool Metropolitan Cathedral and LJMU Design Academy, and an enhanced pedestrian/cycling route including a second public space.

The interventions which are identified in the Urban Design Framework, seek to improve connectivity between the area and the City Centre and Waterfront, and within the area itself. Improvements to key routes into the city centre are identified including Brownlow Hill and Mount Pleasant. Brownlow Hill in particular is a busy bus route into the city centre where vehicular traffic dominates and pedestrian connectivity is currently poor. The Clarence Street junction on this key route currently lacks a pedestrian phase in the traffic lights and the busy pedestrian crossing close to the Design Academy and St Nicholas School needs upgrading.

The project will complement the extensive redevelopment of this area, by providing new and improved public realm around the following major developments:

• LJMU Design Academy, on site, £23.5m • University of Liverpool’s Dept of Engineering, recently completed, £29m • Liverpool Science Park Phase 2, on site, £8.5m • University of Liverpool’s Victoria Building refurbishment, recently completed, £7m • Archdiocese – Cathedral Crypt and podium improvements, currently on site

2.0Project Description

The project comprises three elements, located around Brownlow Hill, the highest priority road improvement project as identified by URBED. The elements are set out as follows:

• Brownlow Hill highway improvements. The poor quality public realm creates a negative image of the area detracting from other parts which contain fine buildings and spaces. Brownlow Hill links to the City Centre and to the motorway network and does not provide an attractive route into the City Centre or for people walking between the key educational and cultural landmarks. NWDA funding will be used for a comprehensive improvement of the road corridor (surface materials/traffic light junction/lighting) with enhanced facilities for all types of travel. The delivery of streetscape improvements to this stretch of the road consolidates the work undertaken to a short section of Brownlow Hill via the Package 1 project University Square. The City Council are contributing £150,000 towards the cost of this. This element of the project will cost a total of £1,562,243, funded by £1,412,243 NWDA grant and £150,000 City Council funding.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Knowledge Quarter Public Realm Package 2: Brownlow Hill and Wilderness Area (A&D/58)Report 14 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Knowledge Quarter Public Realm Package 2: Brownlow Hill and Wilderness Area (A&D/58)This decision
  2. Upper Central (Formerly Knowledge Quarter Gateway) Spatial Regeneration Framework – Public Consultation Feedback and Endorsement of Final SRF (M/46)Decided
  3. Knowledge Quarter Development Company (Sciontec Liverpool) (M/55)Decided
  4. Knowledge Quarter Gateway - Further update (M/37)Agreed
  5. Knowledge Quarter Gateway Masterplan and approval of "In Principle" CPO Powers (RTC/38)Approved
  6. Knowledge Quarter Public Realm Phase 3 - Mount Pleasant and Links (A&D/24)Approved

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies