Resolved that – (i) authority be given to commit those schemes identified in Annex C submitted against approved allocations of funding; (ii) authority be given to commit funds from available capital resources in 2003/04 to the delivery of those new projects identified in Annex D submitted; (iii) the financing arrangements for new projects as set out in Annex D submitted be approved; (iv) the Targeted Capital approval from the DfES of £1.2m in respect of Matthew Arnold/Greenways be accepted. The phasing of the funding to be as follows: · 2003/04 - £270,000 · 2004/05 - £700,000 · 2005/06 - £230,000 (v) the funding for Devolved Formula Capital for 2003/04 set out in Annex A submitted be uplifted to £3,865,000 in accordance with the revised allocation from the DfES ; (vi) the Education CERA allocation of £1,442,000 be included in the Education Capital Programme; and (vii) the Education Capital Programme be amended in accordance with the information set out in Annexes A-E submitted.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Executive summary: The purpose of the report is to:
1. advise Members of current commitments from the available capital funds for 2003/04 to support projects within the existing Education and Lifelong Learning Service’s Capital Programme as set out in Annex B
2. seek authority to incur additional expenditure in relation to projects within the existing programme as set out in Annex C;
3. seek authority for the new projects identified in Annex D to be included within the Education and Lifelong Learning Service Capital Programme for 2003/04 to be funded from the remaining balances of capital funds.
Report No FMS/18/03 of the Executive Member for Resources to the Executive Board in March 2003 set out the proposed Capital Programme for the Authority for the financial year 2003/04. The Education programme outlined in the report is this year the largest ever with a value in excess of £29m representing an increase of 33% on 2002/03 and over 40% on the 1999/2000 programme. It should be recognised that to fund this programme it has been necessary to make significant calls on Council general resources of £4.7m over and above the specific Education Capital allocations from the DfES. A summary is attached in Annex A.
The size of the Education capital programme is a reflection not only of the additional commitment and funding from Central Government to support schools, but also of the efforts within ELLS to tackle a deteriorating building stock and maximise the available funding to support strategically important projects identified as part of the Asset Management Planning process.
In order to support this significant and far reaching programme it has been necessary to commit a substantial portion of the resources made available from the DfES for 2003/04 to existing projects. These resources are in the form of formulaic allocations targeted at the condition of the stock (e.g. New Deal For Schools Condition and Modernisation Funds and Schools Access Initiative) and specific capital grants aimed at raising standards (e.g. Seed Challenge). The allocations for 2003/04 are summarised below.
Funding 2003/04 £ Type
NDS Condition 2,749,472 Grant Modernisation 1,740,199 SCA Seed Challenge 574,965 Grant Schools Access Initiative 725,000 BCA Basic Need 253,000 BCA Planned Maintenance 1,442,000 Education Revenue
Commitments from 2003/04 allocations have been the subject of previous reports to Members on a project by project basis and are summarised in Annex B.
Additional Commitments
In addition to the commitments already reported a number of other previously unforeseen costs have arisen in relation to existing projects. These are set out in Annex C and authority is now sought to incur the additional expenditure together with the proposed financing of that expenditure and amend the Capital Programme accordingly.
An explanation of the additional costs incurred is also set out in Annex C.
New Projects for 2003/04
As a result of those existing and additional commitments from available resources for 2003/04 identified above there is only a small balance available from the specific Education funding sources summarised above to initiate new schemes and to cover contingencies. It is proposed to allocate these resources towards urgent condition works identified from AMP surveys that have already been deferred from previous years. Authority is therefore sought for the projects identified in Annex D to be included within the ELLS Capital Programme for 2003/04.
Targeted Capital
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.