Resolved that – (i) authority be granted to finance those project overspends set out in the report submitted from remaining contingency of un-committed NDS Condition and Seed Challenge funds for 2003/04; (ii) authority be granted to commit £86,000 from the remaining contingency of un-committed NDS Condition for 2003/04 to fund replacement windows at Broadgreen Primary School ; (iii) authority be granted to commit £30,000 from the remaining contingency of un-committed Planned Maintenance for 2003/04 towards the costs of refurbishment the playground at Blackmoor Park Junior School ; (iv) authority be granted to allocate £65,000 from NDS Resources for 2004/05 towards the financing of works at Holy Trinity; (v) authority be granted to allocate £100,000 from NDS Resources for 2004/05 towards the financing of the final phase of works at Fazakerley Primary School ; and (vi) the Education Capital programme be amended accordingly.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Executive summary: The purpose of the report is to:
1. update Members on the current progress of the Education Capital Programme for 2003/04
2. seek approval for additional commitments from the remaining balances of specific Educational Capital Resources for 2003/04 to cover overspends on existing projects identified in this report.
3. seek authority to commit resources from the additional remaining balances of specific Educational Capital Resources for 2003/04 to new projects identified within the report
4. seek authority to commit from specific Educational Capital Resources for 2004/05 to fund further phases of works and identified funding gaps on existing projects.
Report No DE/086/03 to the Executive Member for Education, Library and Sports set out the current position regarding the Education Capital Programme for 2003/04. This report provides information on the progress of the capital programme as part of a new process of ongoing regular updates.
1. Update on Capital Programme 2003/04
Annex A is provided for information purposes and sets out the position with respect to all projects that are currently ‘live’, projects within the approved programme that are yet to commence and older schemes that are effectively complete but are contained within the programme because there is still an element of expenditure outstanding.
It also provides information on projects in relation to VA schools that are funded in the main through the LEA Co-ordinated Voluntary Aided Programme (LCVAP). These latter projects are not identified within the Approved Programme since the funding is drawn down direct from the DfES by the schools for each project. The LEA, Archdiocese and Diocese do, however, agree the overall programme. 2. Additional project overspends The additional overspends set out below have been identified since report No DE/086/03 was considered by Members. It is proposed that the cost of these overspends is met from the remaining contingency of uncommitted Education capital resources for 2003/04 as indicated below: Capital Code Project Overspend (£) Funding BEENC86 Holly Lodge Phase 2 880.03 Seed BEEAY79 Archbishop Beck 23,039.50 NDS BEELX37 St John Almond 4,935.00 NDS BEENN75 King David Primary 941.23 NDS BEEJE58 Alsop Phase 2 2,100.00 NDS BEENN75 Sacred Heart 919.84 NDS BEENC86 Holly Lodge Phase 2 37,000.00 Seed BEEKM29 Lawrence CP 21,000.00 NDS Total 90,815.60 3. New Projects The following projects have been deferred from 2002/03. The works have been identified as essential from the Asset Management Plan surveys and a further delay will have a detrimental effect on the operation of the schools concerned. Authority is therefore sought to set aside budget for the works from the remaining contingency of un-committed NDS Condition funds and Planned Maintenance for 2003/04. The contract price will be reported once tenders for the works have been received. With respect to Blackmoor Juniors the Council had programmed some window replacements this summer (set out in report DE/086/03 to be funded from 2003/04 NDS Condition). However, it has been agreed with the school that there is a need to attend to several urgent health and safety related works and consequently the school will allocate its Devolved Formula Capital for 2003/04 towards these and the Council will allocate £30,000 from its Planned Maintenance Budget for 2003/4 towards the resurfacing of the playground since this has a higher priority than works to the windows. The works to the windows will be removed from the current programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.