Resolved that – (i) the tender in the sum of £525,000 from WH Snow Limited be accepted and authority be given to enter into a contract to undertake the works at Park Primary School ; (ii) fees in the sum of £53,813 from 20:20 Liverpool be accepted and added to the total cost of the project; (iii) a virement of £17,079 from the St. Sebastian’s SSA project (BEENS88) be approved to cover the shortfall in funding; and (iv) the Education Capital Programme be amended accordingly.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
The alternative options to the use of the grant were set out in report DE/096/03.
Consultation
The school has been fully consulted in the design of the facilities.
Financial implications
The total cost of the project, including fees, will be £578,813. Space for Sport and Arts had originally approved £430,000 for the project which would leave a gap of £148,813 and Space for Sport and Arts has agreed that this gap can be funded from the redistributed grant after the removal of the St. Hugh’s scheme from the programme.
A small amount of enabling work was undertaken in 2002/03 for security and fencing and this was financed by the SSA grant in that year. It is intended to cover the shortfall of funding, £17,079 from a virement from the St. Sebastian’s scheme. This is possible due to fees in the initial stages of the St. Sebastian’s scheme being financed from other funding which was not taken account when the tender was submitted for approval, therefore leaving a surplus of funding on this scheme.
20:20 Liverpool has advised that the spend profile of the project would be as follows:
Originally, conditions of the grant stipulated that it had to be fully spent/claimed by March 2004, however, Space for Sport and Arts have now comfirmed that projects can slip into 2004/05 and 2005/06. Best Value:
The scheme has been the subject of competitive tender to obtain the best price.
Equality implications
The scheme has been designed to be fully accessible to the disabled and in line with the current requirements for the DDA.
Corporate strategy:
The Space for Sport and Arts programme is aimed at increasing sporting activities in children as well as providing additional facilities related to the curriculum. This is in line with Corporate aims of both improving the quality of education and promoting healthier citizens.
Budget and Policy Framework:
The programme is within the Portfolio’s budget and policy framework.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.