Resolved
Resolved that authority be granted to transfer the City Council’s interest in the site at Stanley Street, to Liverpool Housing Trust at an open market price of £58,000;
Executive Board decided this item on Friday 12 December 2003. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that authority be granted to transfer the City Council’s interest in the site at Stanley Street, to Liverpool Housing Trust at an open market price of £58,000;
The Garston Neighbourhood Renewal Strategy incorporates the acquisition and demolition of privately owned properties in Stanley Street with a view to their replacement with new housing.
The formally privately owned properties in Stanley Street were accordingly acquired by South Liverpool Housing (SLH) on behalf of Liverpool City Council, the council providing grant funding to do so. SLH has provided local management services during the site assembly period and is now to transfer these back to the City at nil cost.
The remaining properties within the site were owned by Liverpool Housing Trust (LHT) which intends to redevelop the site, providing 26 new homes for rent. These homes form part of the overall rehousing provision in the area, primarily for local people displaced by the City’s local regeneration programme. The scheme is supported by grant funding from the Housing Corporation’s Approved Development Programme, itself previously approved by the City Council.
Both sets of houses were demolished in Winter 2003 to create a cleared site for development. It now remains for the land to be transferred into LHT’s ownership in order for it to begin the development of the new homes. Authority is therefore sought for the City Council to take receipt of its interest in the site from SLH at no cost and to then sell on to LHT for an agreed sum of £58000. This sum has been determined by officers from Liverpool 2020 acting for the City Council. The transfer will be effected through a back to back agreement between SLH, the City Council and LHT. Executive Member/Director recommendation (Charlie Parker)
That authority be given to transfer Liverpool City Council’s interest in the site at Stanley Street, Liverpool 19 to Liverpool Housing Trust at an open market price of £58000;
Key Decision?
No.
Forward Plan/5 days notice/special urgency
No this scheme has not been individually referenced in the Forward Plan but is included within the overall regeneration strategy for Garston.
Implementation effective from:
19 December 2003
Timescale for action:
The disposal of the City Council’s interest in the Stanley Street site will take place immediately, subsequent development by Liverpool Housing Trust will begin in the new year (Jan 04) and is expected to take in the region of 12-15 months to complete.
Reason(s) for Recommendation
The development of new housing at Stanley Street forms part of the new housing provision to supply rehousing opportunities for local people being displaced by the City council’s main regeneration proposals in the area..
As the City Council is part owner of the site and on a pepperpotted basis, there is no realistic alternative to disposal to Liverpool Housing Trust. By agreement with LHT, the site could be marketed for private development. However at this stage in the areas development, its location effectively precludes such interest. Additionally, the housing to be built by LHT meets a local need that will help to accelerate the major redevelopment in the area. Consultation
The Garston renewal programme has been the subject of widespread and intensive local consultation, culminating in proposals to replace areas of existing housing with new. Stanley Street has been a feature of local proposals throughout and has the support of the local community and other stakeholders.
The disposal of the City Council’s interest at Stanley Street will provide a capital receipt of £58000. Failure to proceed with the transfer would jeopardise the redevelopment scheme and therefore Housing Corporation funding in excess of £900k would be lost to the area.
Best Value:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Disposal of Land at Stanley Street Site, GarstonReport | 4 pages | DownloadRead as text |
Follow Executive Board at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Apr 2010 | Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. | Approved | Open |
| 23 Apr 2010 | New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... | Decided | Open |
| 23 Apr 2010 | 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... | Decided | Open |
| 23 Apr 2010 | Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... | Approved | Open |
| 23 Apr 2010 | Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.