Housing Capital Programme 2003/04

Approved Executive 1 paper

Executive Board approved this item on Friday 23 January 2004. Below is the council's own wording, with the papers it was decided on.

Item48

Resolved

Resolved that – (i) the revised Housing Capital programme as shown in Appendix 1 to the report submitted be approved, resulting in the slippage of £1,136,000 of general resources from 2003/04 to 2004/05, the re-profile of travellers grant of £430,000 and receipt of £34,000 of private sector contributions; (ii) the acquisition of vacant properties in the Ship Streets in Garston for demolition be approved and officers be authorised to commit the £720,000 resources; and (iii) the demolition of vacant properties in Church Road/Railway Street be approved and the £200,000 resources be committed
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 9 pages

Executive summary

At the meeting of the City Council on 10 March 2003 the Housing Capital Programme 2003/04 was approved. Since that time officers have been monitoring the programme to ensure that the expenditure is maximised and schemes remain within the budgets identified.

The programme has recently been reviewed and due to confirmation of additional income from various sources including English Partnerships and the Housing Market Renewal Fund for the Early Action schemes the overall programme now requires amendment.

Attached at Appendix 1 is a table indicating the programmes, the original budget and the proposed revisions based on anticipated expenditure for 2003/04.

Housing Revenue Account

Hector/Argos

This scheme has completed and the final account payment has now been confirmed at £11,000.

Adaptations for Council Tenants

This programme provides funding for Council Tenants who require adaptations to their homes to meet their physical needs. It is recommended that as result of the savings identified within the overall programme this budget should be increased by £50,000 and will be used to provide level access showers. Eastern Fringe

This programme made provision for the acquisition of owner occupied properties in the Gillmoss Area and Dovecot which were identified for demolition. However, as a result of a successful bid to the North West Development Agency for grant funding for the Stonebridge Cross Scheme it is recommended that this budget be reduced by £904,000 to take account of the outstanding acquisitions required in the Dovecot area only.

Norris Village

This programme makes provision for the acquisition of owner occupied properties in the Boot Estate and to undertake site treatment works where demolition has taken place in accordance with the redevelopment of the area. Based on the discussions taking place with those owners who have now reached an agreement with the City Council on the purchase of their property the estimated legal completions that can be reasonably expected by the end of the financial year requires provision of £500,000 and a further £250,000 for site treatment works. It is recommended therefore that this programme line be reduced by £1,030,000.

Final Accounts

This programme makes provision for completed schemes where there are outstanding financial commitments. A recent review of the schemes has indicated that the 2003/04 original budget is not required and can be reduced by £650,000 to £400,000 to meet the outstanding commitments. Commitments into 2004/05 will be first call on resources allocated to the Housing Capital programme.

Stock Transfer Dowry Part 2

The City Council is contractually committed to a second and final dowry payment relating to the transfer of the Eastern Fringe Stock due to be paid on 1 April 2004. In view of the savings identified in the 2003/04 programme it is recommended that this payment of £2,500,000 is made on 1 March 2003. This will release these resources for reallocation within the 2004/05 programme and will ensure maximum expenditure of the 2003/04 HRA programme.

Housing General Fund

Dovecot Shopping Parade

This scheme providing environmental works as part of the regeneration of the Shopping parade is to be completed shortly. A review has indicated a reduction in the budget from £102,000 to £79,000 will be adequate to meet the final payments. Stanley Road Shops

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Housing Capital Programme 2003/04Report 9 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Housing Capital Programme 2003/04This decision
  2. Called In Item - Amendments to the Approved Housing Capital Programme 2009/10 at the end of the Third Quarter (SSC/38)Approved
  3. Amendments to the Approved Housing Capital Programme 2009/10 at the end of the Third Quarter (SSC/38)Decided
  4. Housing Capital Programme 2010/13 (SSC/32)Approved
  5. Housing Capital Programme 2009/12 (SSC/6)Approved
  6. Amendments to the Approved Housing Capital Programme 2008/09 (SSC/37)Decided

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies