Connecting Liverpool Signage and Interpretation Project (REG/77)

Decided Executive 1 paper

Executive Board decided this item on Friday 5 March 2004. Below is the council's own wording, with the papers it was decided on.

Item101e

Resolved

Resolved that – (i) authority to be given to the Executive Director (Regeneration)to accept capital grants from the ERDF and SRB totalling up to £1,000,000 during the financial years 2003/04 and 2004/05. The City Council will thereby accept the role of the accountable body and ensure the grant is administered appropriately; (ii) on receipt of offer letters for the ERDF and SRB grants : · the City Council’s capital programme be adjusted to reflect expenditure on this project totalling £1,050,000 in the financial years 2003/4 (£250,000) and 2004/05 (£800,000) and to reflect the increased grant income of £800,000 to finance the project; and · the expenditure of £1,050,000 is committed. (iii) the Team Leader, City Centre Projects Team to be appointed as the nominated officer for monitoring compliance with the terms and conditions of both grants. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises; and (iv) expenditure will only be incurred after the receipt of confirmation of funding from the relevant bodies upon which this project relies for income and the finalisation of all other relevant documents.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 5 pages

Executive summary

The Connecting Liverpool signage and interpretation project forms an important element of the City Centre Movement Strategy. Details of the project have been previously outlined to Members, and have been the subject of an extensive consultation exercise.

Specific aims of the project are to:

• ensure that there is proper integration across the city centre; • ensure that there is strategic continuity of provision of information to enable all visitors to move with ease; • provide a consistency in the information, directions and interpretation that people experience; • highlight the qualities of the City and its architectural and cultural diversity; • develop a simple interface that presents information from diverse sources and mediums as a single seamless service; • enhance Liverpool as a tourist destination; • provide better quality experiences which in turn will encourage greater visitor numbers. Executive Member/Director recommendations (Councillors Peter Millea and Chris Curry/Charlie Parker)

That: -

(i) authority to be given to the Executive Director for Regeneration (Charlie Parker) to accept a capital grants from the ERDF and SRB totalling up to £1,000,000 during the financial years 2003/04 and 2004/05. The City Council will thereby accept the role of the accountable body and ensure the grant is administered appropriately;

(ii) On receipt of offer letters for the ERDF and SRB grants :

• The City Council’s capital programme be adjusted to reflect expenditure on this project totalling £1,050,000 in the financial years 2003/4 (£250,000) and 2004/05 (£800,000) and to reflect the increased grant income of £800,000 to finance the project; and

• the expenditure of £1,050,000 is committed.

(iii) the Team Leader, City Centre Projects Team to be appointed as the nominated officer for monitoring compliance with the terms and conditions of both grants. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises; and

(iv) expenditure will only be incurred after the receipt of confirmation of funding from the relevant bodies upon which this project relies for income and the finalisation of all other relevant documents.

Key Decision:

Yes

Forward Plan:

Yes

Implementation effective from:

12 March 2004 Timescale for action:

The project will proceed upon receipt of full funding and Member approval. Once authority to proceed is received, it is anticipated that work will be complete within 20 weeks.

Reason for recommendation

To enable the delivery of a consistent and branded approach to the presentation of information and directional facilities within Liverpool City Centre, and to provide a world-class way finding and interpretation system.

Alternative options to be considered: 3 alternative options were considered;

To do nothing – This would leave the existing unsatisfactory situation of a network of finger posts which carry out of date information with many of the fingers facing in the wrong direction due to vandalism.

Refurbishment of the existing scheme – This would be significantly cheaper than the option proposed, but would not achieve the same magnitude of improvement in the provision of information to visitors.

Purchase of an ‘off the shelf’ system and an in house development of the scheme – This option would not meet the aspiration of contributing to a world class public realm in keeping with the wider public realm works which the scheme complements.

Consultation

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Connecting Liverpool Signage and Interpretation Project (REG/77)Report 5 pages DownloadRead as text

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies