Resolved that – (i) authority to be given to the Executive Director (Regeneration)to accept capital grants from the ERDF and SRB totalling up to £1,000,000 during the financial years 2003/04 and 2004/05. The City Council will thereby accept the role of the accountable body and ensure the grant is administered appropriately; (ii) on receipt of offer letters for the ERDF and SRB grants : · the City Council’s capital programme be adjusted to reflect expenditure on this project totalling £1,050,000 in the financial years 2003/4 (£250,000) and 2004/05 (£800,000) and to reflect the increased grant income of £800,000 to finance the project; and · the expenditure of £1,050,000 is committed. (iii) the Team Leader, City Centre Projects Team to be appointed as the nominated officer for monitoring compliance with the terms and conditions of both grants. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises; and (iv) expenditure will only be incurred after the receipt of confirmation of funding from the relevant bodies upon which this project relies for income and the finalisation of all other relevant documents.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
The Connecting Liverpool signage and interpretation project forms an important element of the City Centre Movement Strategy. Details of the project have been previously outlined to Members, and have been the subject of an extensive consultation exercise.
Specific aims of the project are to:
• ensure that there is proper integration across the city centre; • ensure that there is strategic continuity of provision of information to enable all visitors to move with ease; • provide a consistency in the information, directions and interpretation that people experience; • highlight the qualities of the City and its architectural and cultural diversity; • develop a simple interface that presents information from diverse sources and mediums as a single seamless service; • enhance Liverpool as a tourist destination; • provide better quality experiences which in turn will encourage greater visitor numbers. Executive Member/Director recommendations (Councillors Peter Millea and Chris Curry/Charlie Parker)
That: -
(i) authority to be given to the Executive Director for Regeneration (Charlie Parker) to accept a capital grants from the ERDF and SRB totalling up to £1,000,000 during the financial years 2003/04 and 2004/05. The City Council will thereby accept the role of the accountable body and ensure the grant is administered appropriately;
(ii) On receipt of offer letters for the ERDF and SRB grants :
• The City Council’s capital programme be adjusted to reflect expenditure on this project totalling £1,050,000 in the financial years 2003/4 (£250,000) and 2004/05 (£800,000) and to reflect the increased grant income of £800,000 to finance the project; and
• the expenditure of £1,050,000 is committed.
(iii) the Team Leader, City Centre Projects Team to be appointed as the nominated officer for monitoring compliance with the terms and conditions of both grants. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises; and
(iv) expenditure will only be incurred after the receipt of confirmation of funding from the relevant bodies upon which this project relies for income and the finalisation of all other relevant documents.
Key Decision:
Yes
Forward Plan:
Yes
Implementation effective from:
12 March 2004 Timescale for action:
The project will proceed upon receipt of full funding and Member approval. Once authority to proceed is received, it is anticipated that work will be complete within 20 weeks.
Reason for recommendation
To enable the delivery of a consistent and branded approach to the presentation of information and directional facilities within Liverpool City Centre, and to provide a world-class way finding and interpretation system.
Alternative options to be considered: 3 alternative options were considered;
To do nothing – This would leave the existing unsatisfactory situation of a network of finger posts which carry out of date information with many of the fingers facing in the wrong direction due to vandalism.
Refurbishment of the existing scheme – This would be significantly cheaper than the option proposed, but would not achieve the same magnitude of improvement in the provision of information to visitors.
Purchase of an ‘off the shelf’ system and an in house development of the scheme – This option would not meet the aspiration of contributing to a world class public realm in keeping with the wider public realm works which the scheme complements.
Consultation
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.