ERDF Support Towards Pre-Development Costs Associated with the 4th Grace and Kings Waterfront Projects (RES/80)

Decided Executive 1 paper

Executive Board decided this item on Friday 5 March 2004. Below is the council's own wording, with the papers it was decided on.

Item103

Resolved

Resolved that – (i) the City Council submits ERDF applications to support pre-development costs for the 4 th Grace and Kings Waterfront projects and act as Accountable Body for £7.822m ERDF grant funding; (ii) the Executive Director (Resources) be authorised to accept ERDF grant awarded towards pre-development costs of the two projects and the Divisional Manager (Regeneration Programmes) be appointed as the nominated officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises; (iii) the City Council’s revenue budget be adjusted to reflect ERDF expenditure on the 4 th Grace and Kings Waterfront pre-development projects as set out in the Financial Implications section of the report submitted; and (iv) grant related expenditure will not be incurred until confirmation of the grant has been received from GONW.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 7 pages

Executive summary

1. The Mid Term Evaluation (MTE) of the Objective One Programme identified the Liverpool waterfront as the focus for future major investment by the 2000–2006 Objective One programme, and in particular the proposed developments at Kings Waterfront and the 4th Grace.

2. Government Office North West (GONW) has very recently indicated that it would welcome ERDF applications against pre-development costs associated with the 4th Grace and Kings Waterfront projects, to cover the period leading up to a start on site for the two schemes in March 2005. Eligible costs will include, inter alia, design and architects fees, project management, planning, environmental and economic impact studies, consultation, enabling works, public sector due diligence, and specialist advisory services.

3. GONW’s invitation to submit applications for activity and costs of this nature is a departure from “standard” ERDF practice, which would normally only be awarded against fully designed and costed schemes, with the applicants/developers having to undertake all the pre-development work at risk and at their own expense. If the City Council does agree to submit applications then GONW require these as a matter of urgency in order that they can be taken to the Objective One Programme Monitoring Committee for approval 22 March .

4. The fact that GONW has invited these applications is a very positive development and the City Council should respond both quickly and positively. This will allow the projects to get early Objective One programme “buy in” and will also give the other major funders, and in particular the North West Development Agency some comfort that GONW is prepared to share the risk of bringing the projects to site. The other clear benefits are that LCC receives income from ERDF sources and that the threat of clawback from Merseyside’s Obj 1 monies to Brussels is reduced as a result of accelerated spend.

5. This report requests approval for Liverpool City Council to act as Accountable Body, on behalf of the public sector partners, for Objective One ERDF grant funding of £4.322m for 4th Grace and £3.5m for Kings Waterfront, against pre-development costs to facilitate a start “on site” for the two projects early next year. An outline of the two projects, including costs, partners and proposed timescales for delivery is included at Annex 1. 6. Applying for ERDF funding and acting as Accountable Body for pre- development costs does not prejudice the City Council from any decision regarding the two schemes in respect of planning permission and the development phases of the projects; nor does it commit the City Council to being Accountable Body for future phases. A further report will brought to Members regarding this as appropriate.

Executive Member/Director recommendation (Councillor Chris Curry/Charlie Parker)

That:

(i) the City Council submit ERDF applications to support pre-development costs for the 4th Grace and Kings Waterfront projects and act as Accountable Body for £7.822m ERDF grant funding;

(ii) the Executive Director Resources be authorised to accept ERDF grant awarded towards pre-development costs of the two projects and the Divisional Manager for Regeneration Programmes is appointed as the nominated officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ERDF Support Towards Pre-Development Costs Associated with the 4th Grace and Kings Waterfront Projects (RES/80)Report 7 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. ERDF Support Towards Pre-Development Costs Associated with the 4th Grace and Kings Waterfront Projects (RES/80)This decision
  2. Approval to Act as Accountable Body for Objective 1, ERDF Grant for Schemes Supported by Liverpool VisionDecided

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open