CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Liverpool City Council
Executive Board, Friday 16 April 2004

City Centre North Phase 1 - Hunter Street/Byrom Street Scheme (Construction and Supervision) (REG/90)

Noted Executive 1 paper

Executive Board noted this item on Friday 16 April 2004. Below is the council's own wording, with the papers it was decided on.

Item168d

Resolved

Resolved that – (i) the progress and planned implementation of the project contained within the report submitted, be noted; (ii) the Executive Director (Regeneration) be authorised to accept the detailed design work when it is completed by 2o2o Liverpool, and providing the designed scheme does not result in project costs exceeding approved funding of £1,612,000, give approval for the construction works to commence on site in April 2004; and (iii) the commitment of £1,753,000 expenditure in 2004/2005 for the Hunter Street/ Byrom Street scheme from the CCMS allocation within the approved Transportation Capital Programme be approved . REG/91
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 8 pages

Executive summary

1. Introduction

1.1This report has been prepared to advise Members of the detailed proposals for City Centre North Phase 1 – Hunter Street / Byrom Street Scheme (HB Scheme). It seeks authority to accept the detailed design proposals and cost estimates for the HB Scheme, compiled by 2o2o Liverpool. 2o2o Liverpool was appointed to undertake the detailed design work following the approval of a previous Committee report dated 16th September 2003.

1.2The previous report sought approval for the initial design of the City Centre North Phase 1 Scheme, of which the HB Scheme was one of two component parts. (Faber Maunsell was appointed to design the other component part, which specifically related to Tithebarn Street and the Churchill Way Flyovers and this aspect is not dealt with in this report).

1.3Acceptance of the HB Scheme detailed design proposals and associated scheme costs is essential if the commencement on site is to follow the intended programme for the implementation of the City Centre Movement Strategy. The HB Scheme is on the critical path of this programme and must be completed before other CCMS Schemes can commence.

2. Background and Project Context

2.1Under CCMS through traffic will be removed from Dale Street. To achieve this a package of highway and public realm works was previously identified within the CCMS North area study. The HB Scheme was part of this and provides improvements to the strategic highway network on Hunter Street, Byrom Street, Leeds Street and Scotland Road, to accommodate the displaced traffic from Dale St and the Churchill Way South Flyover. No Traffic Regulation Orders (TROs) are required for the scheme and construction can start in advance of other parts of the package. This will help minimise the local disruption caused by roadworks. The scheme is to be completed before October 2004 when the Churchill Way (South) Flyover is proposed to be closed under an Experimental TRO.

Detailed Scheme Proposals

2.2The detailed design for the scheme, shown on the attached drawing, has been carried out by 2o2o Liverpool and is summarised below:

o Provision of an additional lane on Hunter Street westbound, approaching Byrom Street (retaining a dedicated left lane to the Queensway Tunnel, and increasing the number of lanes to Byrom Street Northbound from 3 to 4). o Provision of 2 additional lanes on Byrom Street Northbound, (increasing the number of lanes turning left into Leeds Street from 1 to 2, and increasing the number of lanes continuing north onto Scotland Road from 2 to 3). o Provision of 1 additional lane southbound on Scotland Road through the Leeds Street junction, (increasing the number of lanes from 2 to 3 towards Hunter Street). o Improvements to the traffic signal timings on Leeds Street to enhance capacity, (at the junctions with Vauxhall Road, Pall Mall and Old Hall Street). o Improved facilities for cyclists around Byrom Street and Hunter Street. o Improved pedestrian crossing facilities on Byrom Street and Leeds Street.

Scheme Implementation and Programme

2.3The HB Scheme will be procured through the Liverpool CCMS Framework Contracts. The formal tendering procedure for the Framework Contracts is almost complete and Contractors will be appointed in the coming weeks.

2.4Following appointment a period of negotiation will begin with the Contractor most suited to the HB Scheme. During this period of negotiation the Contractor establishes; by agreement with the Consultant Project Manager, the methods and prices for completing the scheme. The result of this will be the issuing of a formal Task Order, after which work on site will commence.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
City Centre North Phase 1: Hunter Street/Byrom Street Scheme (Construction and Supervision) (REG/90)Report 8 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. City Centre North Phase 1 - Hunter Street/Byrom Street Scheme (Construction and Supervision) (REG/90)This decision
  2. City Centre Public Space Protection OrderAgreed
  3. 62-78 Lord Street, City Centre, Liverpool L2 1TD (Central Ward)Agreed
  4. Liverpool City Centre Connectivity Phase 1 (LCCC1) – Update & Authority to Award Contracts RH/7Approved
  5. Closure of Cash Taking Facilities at the City Centre One Stop Shop (DML/4)Decided
  6. City Centre Connectivity Phase 2 Provision of new link road (RTC/31)Agreed

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies