Liverpool City Centre Connectivity programme has been progressing well since the last Cabinet update in July 2019. The first package of works, LCCC1 City Centre, is progressing on site and a detailed progress update is provided in this report. The project team has been preparing to commence with next construction phase. Significant consultation and coordination has taken place with key stakeholders, such as Bus Alliance and Liverpool One, and comments received from the public and key stakeholders have been taken into account and proposals improved where possible. In addition to this, outstanding key issues have been resolved with a detailed update of the outcomes provided in this report. All this progress means that the project team is ready to commence with the next key phase of the programme, arranging an additional Public Information Event followed by site works commencement on The Strand and Lime Street schemes. This report provides a detailed progress update on the scheme and seeks approval to progress with current proposals and authority to procure and award contracts within LCCC1 programme and update financial envelope.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Report Title: Liverpool City Centre Connectivity Phase 1 (LCCC1) – Update & Authority to award contracts
Date: Report No: 24th January 2020 EDR/03/20
Decision Type: Cabinet Key Decision
Executive Summary: Liverpool City Centre Connectivity programme has been progressing well since the last Cabinet update in July 2019. The first package of works, LCCC1 City Centre, is progressing on site and a detailed progress update is provided in this report. The project team has been preparing to commence with next construction phase. Significant consultation and coordination has taken place with key stakeholders, such as Bus Alliance and Liverpool One, and comments received from the public and key stakeholders have been taken into account and proposals improved where possible. In addition to this, outstanding key issues have been resolved with a detailed update of the outcomes provided in this report.
All this progress means that the project team is ready to commence with the next key phase of the programme, arranging an additional Public Information Event followed by site works commencement on The Strand and Lime Street schemes.
This report provides a detailed progress update on the scheme and seeks approval to progress with current proposals and authority to procure and award
V1.1/060919 – 170919 onwards contracts within LCCC1 programme and update financial envelope.
Information: Background Proposals to improve connectivity in Liverpool City Centre, making the city more attractive and easier to navigate, known as Liverpool City Centre Connectivity Phase 1 (LCCC1) are progressing.
The overall aim of this project is to reduce motor traffic dominance on key streets, linked to improved pedestrian facilities and public realm and the provision of safe, direct and attractive cycle facilities. As well as better serving the needs of existing users, these proposals will enable the planned growth in visitors, jobs and housing in and around the City Centre. Failure to address these connectivity issues will make the city less attractive and will generate unnecessary traffic congestion, limiting growth.
LCCC1 proposals contribute to Liverpool City Centre’s status as a World Heritage Site and to the running of major events in the city, especially on the Waterfront and the Lime Street/St Georges areas.
LCCC1 has been divided into different packages in accordance with programme and funding constraints. The current works packages are as follows: City Centre Package Churchill Way Flyovers removal The Strand (Ph1 and Ph2) Lime Street Canning Docks Bridges
The City Centre package commenced in July 2019 and comprises the following schemes (please refer to Appendix A for progress photos): Works completed: o City Bus Hub and Old Haymarket o Victoria Street Phase 1 – eastern end o Moorfields o Churchill Way Flyovers - removal Works progressing on site: o Victoria Street Phase 2 – western end (to be completed March 2020) o Brownlow Hill (to be completed February 2020) o City Coach Park (to be completed March 2020) o Tithebarn Street (to be completed June 2020) o Churchill Way Flyovers – reinstatement works
The City Centre package has been progressing well and it is important to note that the package of works was successfully amended to take into account the urgent need to remove the Churchill Way Flyovers, as clarified in Cabinet report EDR/46/19. Churchill Way Flyovers removal – Implementation as part of LCCC1 The project team, working closely with Legal and Finance departments, agreed with the Liverpool City Region Combined Authority to increase LCCC1 programme budget by £1.75m and reallocate £5m of The Strand funds towards the urgent removal the flyovers, securing a total funding of £6.75m for the flyovers de-construction project.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.