Cabinet 2010/21, Friday 24 January 2020

Liverpool City Centre Connectivity Phase 1 (LCCC1) – Update & Authority to Award Contracts RH/7

Approved Executive 6 papers

Cabinet 2010/21 approved this item on Friday 24 January 2020. Below is the council's own wording, with the papers it was decided on.

Item235c

Resolved

Liverpool City Centre Connectivity programme has been progressing well since the last Cabinet update in July 2019. The first package of works, LCCC1 City Centre, is progressing on site and a detailed progress update is provided in this report. The project team has been preparing to commence with next construction phase. Significant consultation and coordination has taken place with key stakeholders, such as Bus Alliance and Liverpool One, and comments received from the public and key stakeholders have been taken into account and proposals improved where possible. In addition to this, outstanding key issues have been resolved with a detailed update of the outcomes provided in this report. All this progress means that the project team is ready to commence with the next key phase of the programme, arranging an additional Public Information Event followed by site works commencement on The Strand and Lime Street schemes. This report provides a detailed progress update on the scheme and seeks approval to progress with current proposals and authority to procure and award contracts within LCCC1 programme and update financial envelope.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Cabinet 2010/21, 17 pages

CABINET

CITY PUBLIC RH/7

Cabinet Member: Councillor Sharon Connor, Cabinet Member – Regeneration & Highways

Director: Tony Reeves, Chief Executive

Report Title: Liverpool City Centre Connectivity Phase 1 (LCCC1) – Update & Authority to award contracts

Date: Report No: 24th January 2020 EDR/03/20

Decision Type: Cabinet Key Decision

Executive Summary: Liverpool City Centre Connectivity programme has been progressing well since the last Cabinet update in July 2019. The first package of works, LCCC1 City Centre, is progressing on site and a detailed progress update is provided in this report. The project team has been preparing to commence with next construction phase. Significant consultation and coordination has taken place with key stakeholders, such as Bus Alliance and Liverpool One, and comments received from the public and key stakeholders have been taken into account and proposals improved where possible. In addition to this, outstanding key issues have been resolved with a detailed update of the outcomes provided in this report.

All this progress means that the project team is ready to commence with the next key phase of the programme, arranging an additional Public Information Event followed by site works commencement on The Strand and Lime Street schemes.

This report provides a detailed progress update on the scheme and seeks approval to progress with current proposals and authority to procure and award

V1.1/060919 – 170919 onwards contracts within LCCC1 programme and update financial envelope.

Information: Background Proposals to improve connectivity in Liverpool City Centre, making the city more attractive and easier to navigate, known as Liverpool City Centre Connectivity Phase 1 (LCCC1) are progressing.

The overall aim of this project is to reduce motor traffic dominance on key streets, linked to improved pedestrian facilities and public realm and the provision of safe, direct and attractive cycle facilities. As well as better serving the needs of existing users, these proposals will enable the planned growth in visitors, jobs and housing in and around the City Centre. Failure to address these connectivity issues will make the city less attractive and will generate unnecessary traffic congestion, limiting growth.

LCCC1 proposals contribute to Liverpool City Centre’s status as a World Heritage Site and to the running of major events in the city, especially on the Waterfront and the Lime Street/St Georges areas.

LCCC1 has been divided into different packages in accordance with programme and funding constraints. The current works packages are as follows:  City Centre Package  Churchill Way Flyovers removal  The Strand (Ph1 and Ph2)  Lime Street  Canning Docks Bridges

The City Centre package commenced in July 2019 and comprises the following schemes (please refer to Appendix A for progress photos): Works completed: o City Bus Hub and Old Haymarket o Victoria Street Phase 1 – eastern end o Moorfields o Churchill Way Flyovers - removal Works progressing on site: o Victoria Street Phase 2 – western end (to be completed March 2020) o Brownlow Hill (to be completed February 2020) o City Coach Park (to be completed March 2020) o Tithebarn Street (to be completed June 2020) o Churchill Way Flyovers – reinstatement works

The City Centre package has been progressing well and it is important to note that the package of works was successfully amended to take into account the urgent need to remove the Churchill Way Flyovers, as clarified in Cabinet report EDR/46/19. Churchill Way Flyovers removal – Implementation as part of LCCC1 The project team, working closely with Legal and Finance departments, agreed with the Liverpool City Region Combined Authority to increase LCCC1 programme budget by £1.75m and reallocate £5m of The Strand funds towards the urgent removal the flyovers, securing a total funding of £6.75m for the flyovers de-construction project.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 13 pages Download
PDF
Appendix BAppendix B 14 pages Download
PDF
Appendix CAppendix C 64 pages Download
PDF
Appendix DAppendix D 1 pages Download
PDF
Appendix EAppendix E 7 pages Download
PDF
Liverpool City Centre Connectivity Phase 1 (LCCC1): Update & Authority to Award Contracts RH/7Report 17 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Liverpool City Centre Connectivity Phase 1 (LCCC1) – Update & Authority to Award Contracts RH/7This decision
  2. Liverpool City Region and Cheshire Children's Regional Care CooperativeApproved
  3. Liverpool City Region Overnight Visitor Levy (OVL) Progress UpdateAgreed
  4. Liverpool City Council Disability Action PlanNoted
  5. Liverpool City Council - Crisis and Resilience Fund Policy 2026/2027Approved
  6. Grant Funding from the Liverpool City Region Combined Authority for a Music Industry Recovery Fund (CTE/12)Approved

More from Liverpool Cabinet 2010/21

All decisions
MeetingDecisionOutcome
5 Jun 2020 Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. Approved Open
5 Jun 2020 Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... Decided Open
5 Jun 2020 Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... Approved Open
5 Jun 2020 Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open
5 Jun 2020 Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies