Liverpool City Council
Executive Board, Friday 30 April 2004

Kensington Library - Increased Financial Authorisation (REG/99)

Approved Executive 1 paper

Executive Board approved this item on Friday 30 April 2004. Below is the council's own wording, with the papers it was decided on.

Item175e

Resolved

Resolved that – (i) an increase in the contract by £22,738 to £692,801 on the Kensington Library Scheme for the additional works be approved; (ii) the payment of an additional £2,274 to 2o2o Liverpool in respect of fees be approved; and (iii) the transfer £25,012 of savings from the Highways and Street Lighting revenue resources to finance this increased level of capital expenditure be approved. ENV/21
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 3 pages

Executive summary

Members will recall that this contract which was for the refurbishment of Kensington Library, a grade2 listed building, was let for the sum of £570,063 in 2000 to Lockwoods Construction Ltd, and an additional sum of £100,000 was subsequently granted for the works, bringing the total authorised expenditure for the works to £670,063.

Although expenditure was carefully monitored, the cost of additional works provided during the contract had to be subsequently revised when the full extent of the works became evident after the building was opened up. Unforeseen items, such as patches of dry rot, general repairs, and repairs to front and rear entrances had to be addressed before the building could be handed back fit for public use.

There was also a Contractor’s loss and expense claim due to additional disabled access works to the front entrances, and additional security works in the installation of perimeter railings. Therefore, the areas of additional expenditure are as follows:

Contractor’s loss and expense claim for 5 weeks £9,122 Repairs to front entrance steps, walls, gate piers, and gates £4,370 Disabled access to front access £4,506 Remedial work to rear library steps £ 527 Installation of CCTV and external lighting incl. building work £2,269 General repairs incl. eradication of dry rot £1,944 Fees £2,274 Total £25,012

Executive Member/Director recommendation ( Councillors Peter Millea and Chris Curry/ Charlie Parker)

That -

(i) an increase the contract by £22,738 to £692,801 on the Kensington Library Scheme for the additional works be approved; (ii) the payment of an additional £2,274 to 2o2o Liverpool in respect of fees be approved; and

(iii) the transfer £25,012 of savings from the Highways and Street Lighting revenue resources to finance this increased level of capital expenditure be approved. Key Decision

Yes

Forward Plan

No – appropriate notices will be published in accordance with the constitution.

Implementation effective from

10 May 2004

Timescale for action

On approval of the recommendations

Reasons for recommendation

To enable the contract sum to be increased to allow payment due to the contractor and payment of fees to 2o2o.

Alternative options to be considered

There are no alternative options. The contract would not be delivered without these additional works and the building could not be opened for public access.

Consultation

Regeneration Finance Capital Programme Team 2o2o Liverpool Ltd

Financial implications

The additional costs of £25,012 for which authority is requested have not been budgeted for within the capital programme. It will therefore require financing from revenue resources. As this scheme was initially project managed by the Regeneration Portfolio, before handing over to the Library Service, Regeneration has agreed to finance the overspending and has identified savings identified within the Highways and Street Lighting revenue resources which need to be transferred to finance the capital spending. Approval therefore is also sought to the transfer of these resources. Best Value:

The additional work is based on tendered rates and considered to be value for money.

Equality implications

The scheme is a listed building now with disabled access serving the community with library and DISC facilities. Corporate strategy:

The scheme is compliant with the Equality Action Plan.

Budget and Policy Framework

The 2003/04 and 2004/05 Capital Programme are included within the Budget and Policy framework of the City Council

Community safety implications:

The scheme will create a cleaner and safer environment in which people can learn.

Report attached

No

Background papers

Contract papers Regeneration Financial Review 3rd ¼ report FMS/61/03

Signature: ……………………………. Signature: ……………………………. (Executive Member) (Executive Director)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Kensington Library: Increased Financial Authorisation (REG/99)Report 3 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
MS
Councillor Mike Storey CBEChair, present
WB
Councillor Warren BradleyMember, present
JC
Councillor Jeremy ChowingsMember, present
PC
Councillor Paul CleinMember, present
FC
Councillor Flo Clucas OBEMember, present
CC
Councillor Chris CurryMember, present
MF
Councillor Marilyn FieldingMember, present
PM
Councillor Peter MilleaMember, present
CN
Councillor Chris NewbyMember, present
RO
Councillor Richard OglethorpeMember, present

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies