Resolved that – (i) an increase in the contract by £22,738 to £692,801 on the Kensington Library Scheme for the additional works be approved; (ii) the payment of an additional £2,274 to 2o2o Liverpool in respect of fees be approved; and (iii) the transfer £25,012 of savings from the Highways and Street Lighting revenue resources to finance this increased level of capital expenditure be approved. ENV/21
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Members will recall that this contract which was for the refurbishment of Kensington Library, a grade2 listed building, was let for the sum of £570,063 in 2000 to Lockwoods Construction Ltd, and an additional sum of £100,000 was subsequently granted for the works, bringing the total authorised expenditure for the works to £670,063.
Although expenditure was carefully monitored, the cost of additional works provided during the contract had to be subsequently revised when the full extent of the works became evident after the building was opened up. Unforeseen items, such as patches of dry rot, general repairs, and repairs to front and rear entrances had to be addressed before the building could be handed back fit for public use.
There was also a Contractor’s loss and expense claim due to additional disabled access works to the front entrances, and additional security works in the installation of perimeter railings. Therefore, the areas of additional expenditure are as follows:
Contractor’s loss and expense claim for 5 weeks £9,122 Repairs to front entrance steps, walls, gate piers, and gates £4,370 Disabled access to front access £4,506 Remedial work to rear library steps £ 527 Installation of CCTV and external lighting incl. building work £2,269 General repairs incl. eradication of dry rot £1,944 Fees £2,274 Total £25,012
Executive Member/Director recommendation ( Councillors Peter Millea and Chris Curry/ Charlie Parker)
That -
(i) an increase the contract by £22,738 to £692,801 on the Kensington Library Scheme for the additional works be approved; (ii) the payment of an additional £2,274 to 2o2o Liverpool in respect of fees be approved; and
(iii) the transfer £25,012 of savings from the Highways and Street Lighting revenue resources to finance this increased level of capital expenditure be approved. Key Decision
Yes
Forward Plan
No – appropriate notices will be published in accordance with the constitution.
Implementation effective from
10 May 2004
Timescale for action
On approval of the recommendations
Reasons for recommendation
To enable the contract sum to be increased to allow payment due to the contractor and payment of fees to 2o2o.
Alternative options to be considered
There are no alternative options. The contract would not be delivered without these additional works and the building could not be opened for public access.
Consultation
Regeneration Finance Capital Programme Team 2o2o Liverpool Ltd
Financial implications
The additional costs of £25,012 for which authority is requested have not been budgeted for within the capital programme. It will therefore require financing from revenue resources. As this scheme was initially project managed by the Regeneration Portfolio, before handing over to the Library Service, Regeneration has agreed to finance the overspending and has identified savings identified within the Highways and Street Lighting revenue resources which need to be transferred to finance the capital spending. Approval therefore is also sought to the transfer of these resources. Best Value:
The additional work is based on tendered rates and considered to be value for money.
Equality implications
The scheme is a listed building now with disabled access serving the community with library and DISC facilities. Corporate strategy:
The scheme is compliant with the Equality Action Plan.
Budget and Policy Framework
The 2003/04 and 2004/05 Capital Programme are included within the Budget and Policy framework of the City Council
Community safety implications:
The scheme will create a cleaner and safer environment in which people can learn.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.