Resolved
Resolved that t he Lime Street Development Plan as submitted be endorsed and Officers be authorised to support fully the implementation of the Plan. REG/98
Executive Board decided this item on Friday 30 April 2004. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that t he Lime Street Development Plan as submitted be endorsed and Officers be authorised to support fully the implementation of the Plan. REG/98
1.1The purpose of this report is to:
I. To inform the Executive Member of the development of the Lime Street Station Development Plan 2003 - 2013.
II. To advise the Executive Member of and seek approval for various representations associated with the project.
III. To seek endorsement/approval of the Lime Street Station Development Plan 2003 - 2013.
2.1Lime Street Station is the focus of one of the city’s most important hubs for moving in and around the city. The Station itself is a magnificent Grade II Listed building within an exceptional heritage setting, leading to its potential to be a truly unique ‘gateway’ to the city and one that is synonymous with ‘Liverpool’.
2.2However it is widely acknowledged that the Station and its immediate environs have been in decline for some time, with issues relating to the Station itself, its surroundings, accessibility and perceptions of safety & security. It currently projects a poor image as a key exit/entry point into the city, and is not fulfilling its potential role as an economic hub.
2.3Vision’s Strategic Regeneration Framework (SRF) in 2000 recognised the significant latent potential of the Station and its environs to become a uniquely distinguished gateway to the city. Priority objectives to significantly improve the area’s setting, road layout and physical fabric were identified within the SRF, with the objective of creating a more appropriate and people-friendly environment and one which was more sympathetic to its heritage. 2.4 Since 2000 significant progress has been made on a number of fronts towards the overall achievement of these objectives:-
• Following extensive lobbying by all key partners management of the Station has now been transferred to Network Rail Railway Estates (Managed Stations) from the previous franchise arrangement.
• An overall Lime Street Station Steering Group - consisting of the key partners of LCC, Network Rail, Merseytravel and Liverpool Vision - has been established and meets regularly. It is intended that further sub-groups will be formed as and when appropriate to take forward individual schemes, with for example a sub-group having already been established for the new Station ‘gateway’ entrance.
• English Partnerships (EP), with support from Liverpool Vision, have acquired the freehold and long-leasehold interests in the 1960s Concourse House retail units on the Lime Street frontage of the Station Shops, with a view to negotiating voluntary vacant possessions with remaining tenants and then clearing the buildings (5 of the 12 units are now vacant) to allow the creation of a new Station ‘gateway’ entrance.
• EP have appointed a design team to develop full designs and have committed in principle to support the full construction costs of a new ‘gateway’ entrance from the Lime Street frontage, with a subsequent transfer of these land interests to Network Rail for long- term maintenance and management. Development of this design is overseen by a Client Group of which the City Council is a key member.
• Liverpool Vision has brokered ongoing discussions with the private sector owner of Concourse House Tower on behalf of EP with a view to acquire or agree a comprehensive high-quality redevelopment programme for the building.
• Negotiations have been ongoing with LJMU and Cosmopolitan Housing Association (who are shortly to acquire LJMU’s long leasehold interests in Lime Street Chambers) regarding the potential future use of the lower ground floors of Lime Street Chambers and improvements to the overall appearance of the building.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Lime Street Station Development Plan 2003-2013 (REG/97)Report | 30 pages | DownloadRead as text |
Follow Executive Board at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Apr 2010 | Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. | Approved | Open |
| 23 Apr 2010 | New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... | Decided | Open |
| 23 Apr 2010 | 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... | Decided | Open |
| 23 Apr 2010 | Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... | Approved | Open |
| 23 Apr 2010 | Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.