STANLEY PARK AVENUE SOUTH/STANLEY PARK AREA - TRAFFIC CALMING SCHEME
ApprovedCommittee2 papers
Highways and Public Spaces Representation Committee 2020/21 approved this item on Friday 10 September 2004. Below is the council's own wording, with the papers it was decided on.
Resolved that having carefully considered the proposal and all representations, both written and oral the objections be not sustained. The Panel concluded that to overrule would make a substantial increase in traffic, traffic speed and accidents. Therefore the Divisional Manager of 20/20 Liverpool be granted approval to implement the proposed scheme. __________ The Panel agreed to congratulate David Parsons from LCC on the quality and clarity of his presentation.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Report to Highways and Public Spaces Representation Committee 2020/21, 14 pages
Purpose of report
To consider a report on representations received to the proposed Stanley Park Area – Traffic Calming & 20mph Zone Scheme for Bidston Road.
Recommendation
That the representations are not sustained and the Highways Management Service Manager be granted approval to implement the traffic calming measures.
INFORMATION
Background
The proposals submitted for Stanley Park Area form part of Liverpool City Council’s Local Safety Schemes Programme (LSSP). The rationale behind traffic calming schemes introduced through the LSSP is based on the priority ranking of naturally bounded areas. Therefore, the whole of the city has been divided up into 187 such areas, the boundaries of which are based on those roads identified in ‘Merseyside Fire Brigade’s Strategic Route Network’. In
Liverpool City Council – A.I.U / 2020liverpool – Traffic Projects 2020/TP/TO0185 Stanley Park Area Traffic Calming & 20mph Zone Scheme – Representations Report 10th September 2004
-1- terms of the Stanley Park proposal, this is the area bounded by Queens Drive, Utting Avenue, Priory Road, Walton Lane and Walton Hall Avenue.
The current traffic calming priority list, approved by the Regeneration and Environment Select Committee on 27th November 2003, is based on the accident record in all 187 areas for the 3 year period up to the end of July 2002. Each area is prioritised on their combined pedestrian and cyclist accident rate per 10,000 population in the area, with those areas with 10 or more pedestrian and cyclist accidents comprising the priority list. In terms of actual reported injury accidents, there have been 13 reported pedestrian / cyclist accidents in the Stanley Park Area within the 3 year period.
In order to reduce the number of accidents occurring in the Stanley Park Area, 2020 Liverpool Ltd undertook a design commission followed by a consultation exercise which sought the views of local residents, ward councillors and the emergency services and other key stakeholders on their opinions regarding the proposal to traffic calm Stanley Park Area. These measures themselves would consist of 47, 4.7m road humps and 44, 1.9m x 1.9m speed cushions.
In terms of the strategy for putting the proposals forward to the public, it was decided that the area would be broken down into two distinct areas namely;
• Stanley Park Area – Traffic Calming & 20mph Zone • Stanley Park Avenue South – Traffic Calming & 20mph Zone
This approach was adopted due to the fact that Stanley Park Avenue South had existing speed restraint measures in place, namely chicanes which addressed speed via changes to the horizontal alignment of the road.
In summary, the residents of Stanley Park Avenue South were presented with two options namely;
• Option A - Maintain the existing chicanes and in addition implement 4.7m road humps • Option B - Remove the existing chicanes and construct 4.7m road humps.
In the case of the Stanley Park Area, the affected properties were presented with the option to traffic calm the area complemented by a 20mph zone and asked whether or not they would be in favour of this. In the case of Bidston Road which falls within this area 2 objections have been received which have been detailed in this report. No other objections have been received to the scheme.
Consultation Results
Liverpool City Council – A.I.U / 2020liverpool – Traffic Projects 2020/TP/TO0185 Stanley Park Area Traffic Calming & 20mph Zone Scheme – Representations Report 10th September 2004
-2- In respect of consultation, letters were sent out to the affected stakeholders on the following dates;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Highways and Public Spaces Representation Committee 2020/21 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.