Liverpool City Council
Cabinet 2010/21, Friday 22 January 2016

The Anfield Project – Stanley Park Improvement Works (DML/1)

Decided Executive 1 paper

Cabinet 2010/21 decided this item on Friday 22 January 2016. Below is the council's own wording, with the papers it was decided on.

Item76c

Resolved

In June 2015, Cabinet granted authority to invest City Council resources into improvements to Stanley Park Car Park and the immediately adjacent green space, to be completed by July 2016, and to test the market for the feasibility of delivering an energy-generating project via the installation of photovoltaic panels (PVP). This is one of a number of key projects that will support the delivery of the Anfield project, the comprehensive regeneration project lead by the City Council, Your Housing Group and Liverpool Football Club. This report provides an update on the progress made specifically in relation to the Stanley Park Improvement Works, since the last Cabinet Report in June 2015 and seeks authority to proceed with the works and provides for Delegated Authority to Director of Regeneration and Employment in Consultation with Director of Finance and Resources to award the contract(s) for the works.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Cabinet 2010/21, 13 pages

Executive summary

In June 2015, Cabinet granted authority to invest City Council resources into improvements to Stanley Park Car Park and the immediately adjacent green space, to be completed by July 2016, and to test the market for the feasibility of delivering an energy-generating project via the installation of photovoltaic panels (PVP). This is one of a number of key projects that will support the delivery of the Anfield project, the comprehensive regeneration project lead by the City Council, Your Housing Group and Liverpool Football Club.

This report provides an update on the progress made specifically in relation to the Stanley Park Improvement Works, since the last Cabinet Report in June 2015 and seeks authority to proceed with the works and provides for Delegated Authority to Director of Regeneration and Employment in Consultation with Director of Finance and Resources to award the contract(s) for the works.

Background

There are three elements to the Stanley Park Improvement Works as follows :  Works Package 1-The improvements to an existing Stanley Park car park to increase the number of parking spaces and therefore maximise parking income from match days and events for the provision of drainage, lighting and resurfacing of the car park to meet the current standards and health and safety requirements;

 Works Package 2- Landscape improvement works within Stanley Park (east of Mill Lane) including provision of new footpaths, reinstatement of planting along Dahlia Walk, lighting along footpaths, clearance of overgrown hedges, replacement of trees that have passed their useful life and provision of park furniture such as bins and benches along the footpaths, refurbishment of boundary walls, railings and gates, in accordance with requirements for the Grade II listed and Green Flag status; and

 Works Package 3- If proven feasible, the installation and management of solar photovoltaic panels above the car parking area to generate a long-term energy supply and income stream (PVP project). The management and development of that income stream will be for local benefit.

The progress made in relation to each element of the works are as follows:-

 Willmott Dixon has been appointed for works packages 1 and 2 as the preferred contractor with Planit Consultant as principle designers based on a two-stage Design & Build contract (utilising the SCAPE framework contract).

 Following completion of the design to RIBA Stage 3 and subsequent to a public consultation exercise carried out by Planit Consultants on the 21st October 2015, a planning application for works packages 1 and 2 was submitted on the 6th November 2015.

 The detail design to RIBA Stage 4 is currently being developed and sub-contract tenders have been invited. A breakdown of the pre-tender estimates provided by Willmott Dixon is provided in Appendix 1(in the exempt section of the report). This will be firmed up, once the sub- contract tender prices are received. The intention is to award a contract by the end of January 2016, so that these works can be completed by end of July 2016, to coincide with the Liverpool Football Club’s Stadium expansion, which is to be operational by 2016/17-football season.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
The Anfield Project: Stanley Park Improvement Works (DML/1)Report 13 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. The Anfield Project – Stanley Park Improvement Works (DML/1)This decision
  2. Anfield Project - Land acquisitions/disposals, demolitions and land assembly to facilitate environmental works & housing development (M/47)Approved
  3. The Anfield Project (DML/2)Decided
  4. The Anfield Project – Anfield Sports and Community Centre Improvements (H/9)Decided
  5. The Anfield Project – Agreement of Heads of Terms between Liverpool City Council, Liverpool Football Club and Your Housing Group (R/43)Approved
  6. Acceptance of the role of Accountable Body for the Regional Growth Fund - Employment and Housing: Anfield and Queens Bedford Project (H/10)Agreed

More from Liverpool Cabinet 2010/21

All decisions
MeetingDecisionOutcome
5 Jun 2020 Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. Approved Open
5 Jun 2020 Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... Decided Open
5 Jun 2020 Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... Approved Open
5 Jun 2020 Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open
5 Jun 2020 Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies