Resolved that – (i) the lowest tender in the sum of £1,704,086 for the construction of an extension to the Matthew Arnold Primary School building to form a Children’s Centre and Assessment Centre be accepted and the City Council enter into a contract with Thomas Barnes and Sons PLC; (ii) the City Council incur professional fees of £221,531 being 13% of the contract sum and disbursements of £21,955; (iii) an allocation of £501,868 out of the City Council Children’s Centre Capital Grant of £7,124,639 be agreed and added to the financing of the project; (iv) a sum of £245,704 be set aside from the 2005/06 Modernisation Fund (Primary Need) and added to the financing of the project; and (v) the Capital Programme be amended accordingly.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
PRINCES PARK STATUS – PUBLIC LL/15 Portfolios: Education and Lifelong Executive Members: Learning / Resources Cllr Paul Clein / Cllr Keith Turner Date of submission: Subject: Matthew Arnold/Greenways 15 / 17 September 2004 Children’s Centre Report No: DE/054/04 Contact officers: Rob Gilland - 233 2703 Ron Rampling – 233 2752
Executive summary: The purpose of the report is to seek authority for the acceptance of a tender for the construction of a new extension to the Matthew Arnold Primary School building to form a Children’s Centre and an Assessment Centre for Greenways pupils.
On 27 June 2003 the Executive Board approved the acceptance of the award of £1.2m from the DfES Targeted Capital Fund for works to Matthew Arnold to enable Greenways Assessment Centre move from it’s current location at Beechwood Road South in Aigburth to a new facility attached to Matthew Arnold Primary School. During design the opportunity arose to extend the facility to incorporate additional accommodation that would enable the site to be developed as a Children’s Centre. These extra works include provision for additional office accommodation and multi purpose rooms to provide for a range of family and pupil support services such as health and ante-natal care and classes, ‘surgeries’ for Jobcentre Plus/training providers and welfare rights. It was estimated that the extension of the project would add £500,000 to the original cost. Approval was therefore sought from the Sure Start Unit for an allocation from the Council’s Children’s Centre Capital grant of £7,124,639 to fund the additional works. On 2 September 2004 the Sure Start Unit confirmed that an allocation of £501,868 was approved. In accordance with Standing Orders tenders for the project were invited from 6 companies and returned to the Authority on 13 August 2004. After checking for technical and arithmetical errors the lowest priced tender was confirmed from Thomas Barnes and Sons PLC in the sum of £1,704,086. After including professional fees and disbursements the project is £245,704 above the current total available budget. The variance from the original budget is due to rapidly escalating building costs generally, notably the price of steelwork, costs associated with the remedial works of elevated levels of contamination not previously identified, plus some additional requirements of Building Control. Negotiations with the lowest tenderer have failed to identify any savings within the scheme without seriously compromising the nature of the design. In order for the scheme to proceed therefore it is necessary to seek an allocation from 2005/06 Educational Capital Resources in the sum of £245,704. The current programme anticipates a start on site of 25 October, subject to the necessary Council approvals being obtained prior, and the Contract being completed. The construction is forecast to take 35 weeks and the Centre should therefore be open in time for the new school term in September 2005. Executive Director recommendation: Colin Hilton recommends that:
1. The lowest tender in the sum of £1,704,086 for the construction of an extension to the Matthew Arnold Primary School building to form a Children’s Centre and Assessment Centre be accepted and the City Council enter into a contract with Thomas Barnes and Sons PLC 2. The City Council incur professional fees of £221,531 being 13% of the contract sum and disbursements of £21,955 3. An allocation of £501,868 out of the City Council Children’s Centre Capital Grant of £7,124,639 be agreed and added to the financing of the project. 4. A sum of £245,704 be set aside from the 2005/06 Modernisation Fund (Primary Need) and added to the financing of the project. 5. The Capital Programme be amended accordingly
Key Decision: Yes
Forward Plan: No – appropriate Notice will be served under the Constitution
Implementation effective from: 8 October 2004
Time-scale for action:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.