Resolved that in relation to the Upper Parliament Street / Catherine Street public open space project - (i) authority be given to the Executive Director (Regeneration) to accept the £220,000 Land Reclamation Grant, through the City Centre Environmental Improvement Programme, to finance the project; (ii) the Manager City Centre Projects Team, be appointed as the nominated officer for monitoring compliance with the terms and conditions of the grant (this includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises); (iii) subject to the final works contract not exceeding £191,000 authority be given to accept the tender and subsequently appoint a contractor. In addition to this authority and subject to remaining professional fees not exceeding £29,000 and compliance with Standing Orders and Financial Regulations, authority be also given to commit these expenditures on the Upper Parliament Street / Catherine Street public open space project; and (iv) the City Council’s capital programme be re-profiled to reflect expenditure on this project of £88,000 during 2004/05, £132,000 in 2005/6, and that authority be given to commit this expenditure through the City Centre Environmental Improvement Programme. GI/13
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
The site at the junction of Upper Parliament Street / Catherine Street / Princes Road has recently undergone improvement works to aid both traffic movement and pedestrian safety though the busy junction. As a result of these works, a section of Berkley Street has been closed. This scheme aims to take advantage of the road closure by delivering an area of high quality public open space.
The scheme is designed to benefit both local residents and visitors to Liverpool on a number of different levels. The creation of a recognisable gateway to and from Liverpool City Centre will offer a landmark to visitors, and will also enhance the physical image of the surrounding area. The introduction of high quality design and materials within the space will also act as a symbol of investment in the area. The introduction of enhanced lighting will complement the existing CCTV system in the reduction of crime and the fear of crime. Whilst the space is located on a busy junction, it has been designed to provide a useable space for local people, and to support the pedestrian safety improvements that have been delivered by the junction improvement works.
The opportunity to increase the quality of the public realm at this junction was initially highlighted in the ‘City Centre South Implementation Plan Scheme Identification Report’, commissioned by LCC as part of the City Centre Movement Strategy (CCMS). The scheme has been identified for inclusion in the City Centre Environmental Improvement Programme (EIP), and therefore included in the City Centre EIP Performance Plan 2004/5.
The scheme will be 100% funded thorough the City Centre EIP, which is joint funded by the North West Development Agency (NWDA) and English Partnerships (EP). The maintenance of the space will be the responsibility of the City Council as the space will remain adopted highway. Executive Member/Director recommendation (Councillors Peter Millea and Keith Turner / Charlie Parker)
That, in relation to the Upper Parliament St / Catherine Street public open space project:
(i) authority be given to the Executive Director (Regeneration) to accept the £220,000 Land Reclamation Grant, through the City Centre Environmental Improvement Programme, to finance the project;
(ii) the Manager City Centre Projects Team, will be appointed as the nominated officer for monitoring compliance with the terms and conditions of the grant (this includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises);
(iii) subject to the final works contract not exceeding £191,000 authority be given to accept the tender and subsequently appoint a contractor. In addition to this authority and subject to remaining professional fees not exceeding £29,000 and compliance with Standing Orders and Financial Regulations, authority be also given to commit these expenditures on the Upper Parliament Street / Catherine Street public open space project; and
(iv) the City Council’s capital programme be re-profiled to reflect expenditure on this project of £88,000 during 2004/05, £132,000 in 2005/6, and that authority be given to commit this expenditure through the City Centre EIP.
Key Decision No
Forward Plan No
Implementation effective from
31 December 2004
Timescale for action
The project has been identified within the City Centre EIP Performance Plan 2004/5. Works are due to begin in early 2005, and are due to be completed by mid 2005. Reason(s) for Recommendation
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.