Resolved that – (i) the revised Big Lottery Fund PE and Sport Portfolio, be approved and that, the City Councils Capital Programme be adjusted to reflect the revised expenditure phased over years 2004/05 to 2006/07 as detailed in Appendix A submitted. (ii) further reports be submitted on a periodic basis and after tendering for the main works contracts (where appropriate).
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
CITY STATUS – PUBLIC LL/28 Portfolios: Education and Lifelong Executive Members: Learning / Leisure, Sport and Culture / Councillor Paul Clein Resources Councillor Warren Bradley Councillor Keith Turner
Date of submission: Subject: Big Lottery Fund (BLF) PE 3 / 6 / 8 December 2004 and Sport - Further Amendments to Portfolio
Report No./Background papers: Contact Officer: DE/070/04 Stephen Tiffany Ext 233 8135 Mike Kearney Ext 233 6329
Executive summary: The purpose of this report is to advise members of the further unavoidable changes to the BLF PE and Sport Portfolio since the Stage 2 submissions to the Big Lottery Fund and to seek authority for the re-allocation of grant within the Portfolio.
Background Members are aware that at its meeting on 28 May 2004 the Executive Board approved report DE/025/04 (this report identified eleven priority schemes) which outlined the revised principles of the BLF for PE and Sports Initiative in relation to the allocation of £9.217m made to the City Council in November 2001. The following report elaborates on these principles and indicates the current position in relation to the delivery of the City Council’s amended BLF PE and Sport Portfolio.
Progress to date Since the last report, the eleven priority schemes previously identified have all been submitted to the Big Lottery Fund for appraisal. Each scheme (apart from Priority Scheme 10 – Belle Vale CP School) has now been assessed by the BLF technical panel. During this assessment the BLF informed the City Council’s BLF PE and Sport Portfolio Management Steering Group that they could not approve the former Priority 6 scheme at Booker Avenue CP School/Heron Eccles. As a result, officers are seeking an alternative source of funding for this scheme via the Football Foundation. Subsequently, the BLF PE and Sport Portfolio Management Steering Group recommended the approval of the City Council’s revised BLF PE and Sport Portfolio as detailed in Appendix A.
The projects nominated below will become therefore, priorities for development by the City Council. Details of the phasing are given to the Appendix along with the current estimates of cost. In addition, specific reasons are detailed for the withdrawal of the former Priority 6 scheme from the BLF PE and Sport Portfolio. Priority Schemes: 1. Alsop High School: Construction of new dual-use community leisure facility on the site of the existing Queens Drive Recreation Centre. Total estimated cost £4,550,000. BLF PE and Sport application submitted October 2003. Application approved 19 April 2004. Total grant allocation £3,648,000. Demolition work to the existing swimming baths has commenced and is due to be completed by the end of December 2004. Construction of the new facilities is due to start by March 2005 with completion Spring 2006.
2. Gateacre Community Comprehensive School: Construction of new dual-use sports hall, fitness suite adjacent to existing school swimming pool. Facility will operate as a dual-use community leisure facility. Total estimated cost £2,360,000. BLF PE and Sport application submitted March 2004. Application approved September 2004. Total grant request £2,200,000. Members will be aware of the Building Schools for the Future (BSF) initiative which the City Council applied unsuccessfully for Round 1 funding to develop several schools within the City and included Gateacre CC School within the bid documentation. BSF Round 2 funding decisions are due shortly which include Gateacre CC School. The uncertainty of the BSF process together with recently discovered ground problems on the site has delayed progress with this scheme. As a result, Construction work is now due to start summer 2005 with completion summer 2006.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.