Resolved
Agreed that update and the oral report be noted and that the Officers particularly Angela Forshaw and David Seddon be thanked for their work in this matter.
Housing and Community Safety Select Committee 2005/2006 agreed this item on Tuesday 11 January 2005. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that update and the oral report be noted and that the Officers particularly Angela Forshaw and David Seddon be thanked for their work in this matter.
Reports to select committees
Liverpool City Council Report to: Housing & Community Safety Select Committee
Subject: Norris Village (Boot Estate) Update
Report no: EDR/373/04
Date:
Reporting officer: Cath Green AED Housing & Neighbourhoods
Contact officer: Angela Forshaw Alt Valley Neighbourhood Manager Ward: Norris Green
Ward: Norris Green
1. Purpose and recommendations
To provide an update for members on action being taken • to progress the decant and demolition programmes within the Norris Green 'Boot' estate; • to maintain the environment and ensure community safety; and, • in relation to the development proposals within the initial development area.
2. Relevant background information
2.1The principle of developing a master plan for the Boot estate was originally approved in June 1999 and initiated a major consultation exercise in the area. A number of decisions regarding development proposals have since been taken, including decisions about the order of priority for rehousing.
2.2The rehousing of residents from the first decant area began in October 2000. As a result of the detailed and close involvement of Alt Valley Neighbourhood Management Services since December 2002, considerable progress has now been made both in terms of re housing and demolition. In February 2004 the second and third decant phases was declared and in June 2004 following representations at Area Committee the wider estate was granted decant status with the declaration of decant phases four and five.
Neighbourhood Management Officers have worked with residents and developers to ensure this has been undertaken with efficiency and sensitivity to need. They have supported individuals both in terms of appropriate relocation and dealing directly with environmental and anti-social behaviour issues that can impact on community cohesion and individual well being. A number of community information events and fun days have been organised, including effective community clean up campaigns. This work has involved community and voluntary sector groups as well as LCC and its service delivery partners.
2.3Whilst clearance is underway the estate continues to suffer blight and major problems including environmental crime, vandalism and anti social behaviour. However the Alt Valley Neighbourhood Management Services team and wardens continue to work to stabilise and improve conditions for residents living within the area.
Several reports have been presented to members in the past and this report is to update members on progress being made.
3. Key issues
Demolition and Rehousing
3.1Across the estate a total of 553 properties have been demolished. Of these 164 were demolished in this financial year.
The pace of the demolition slowed down earlier this year due to delays associated with Utility disconnection. Repairs Consultancy worked with the service providers and an agreed protocol has now dramatically decreased the time taken to disconnect newly instructed blocks.
A new contractor, B&B Demolitions, started on site in May 2004 and is making good progress. The previous contractor, Tisdales, left the site in June after completing demolition of property included in their contract but held up by the disconnection issue. The impact of having two contractors on site for a short period meant that clearance was stepped up a gear and blight minimised.
3.2The last family living within the initial development area vacated on December 14, 2004. 3.3 A pre–allocation exercise of the new build for rent has been carried out with Cobalt Housing which will be the new landlord. Early indications are, all remaining families in Phases 1A/1/1Extension (including those in temporary tenancies), and some families in Phase 2 who have expressed an interest in new build, will be made an offer of a new build property suitable to their families needs.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Norris Village (Boot Estate) UpdateReport | 7 pages | DownloadRead as text |
Follow Housing and Community Safety Select Committee 2005/2006 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Apr 2006 | Minutes of the Last MeetingAgreed that the minutes of the last meeting of this Select Committee held on 7 February 2006 , be approved as a true ... | Agreed | Open |
| 3 Apr 2006 | Minutes of Scrutiny PanelsAgreed that;- the Minutes from the meeting of the Building Maintenance Scrutiny Panel held on 3 March 2006; be approv... | Agreed | Open |
| 3 Apr 2006 | Question TimeAgreed that the information requested be submitted to a future meeting of this Committee .. | Agreed | Open |
| 3 Apr 2006 | Gateacre Neighbourhood Committee - Lanfranc Close/Castletown CloseIt was agreed that: a) The Neighbourhood Committee are in full support of the residents and request that Officers and... | Agreed | Open |
| 3 Apr 2006 | Equalities Impact Assessment Statement, Community SafetyAgreed that;- § the information contained in the report be noted; and § the Community Safety team be thanked for thei... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.