Norris Green Village 'Boot' Estate

Agreed Committee 1 paper

Housing and Community Safety Select Committee 2005/2006 agreed this item on Tuesday 7 February 2006. Below is the council's own wording, with the papers it was decided on.

Item92

Resolved

Agreed that;- · the information in the report be noted; · Councillors Rose Bailey and Alan Walker requested further information in respect of numbers of social housing units that will be available in each phase of the Norris Green Village ‘Boot’ Estate development; and · Councillor Rose Bailey requested further information on Streetcrime Wardens who patrol the Norris Green Village ‘Boot’ Estate area. FMS/04/06
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Housing and Community Safety Select Committee 2005/2006, 4 pages

Reports to select committees

Liverpool City Council

Report to: Housing & Community Safety Select Committee

Subject: Norris Village ' Boot' Estate

Report no: EDR/13/05

Date: 7 February 2006

Reporting officer: Cath Green AED Housing & Neighbourhoods

Contact officer: Angela Forshaw Alt Valley Neighbourhood Manager

Ward: Norris Green

1. Purpose and recommendations

The purpose of the report is to provide Members with a progress update on the redevelopment of the Norris Green 'Boot' estate following on from a detailed report considered in July 2005 and a tour undertaken by Select Committee Members.

It is recommended the report be noted.

2. Relevant background information

Context

The 'Boot' estate in Norris Green comprises 1509 defective properties all of which are included in the Council's Decant Programme. It is an area undergoing significant and challenging change. This brings with it short term disruption and often a less desirable and more difficult residential environment. It is currently the case on the Boot estate.

To minimise the negative effects of disruption, and support residents at times of uncertainty the City Council is working with local community groups and individuals to ensure programmed work is to a high standard and timely and to deliver a number of interventions to support individuals and the neighbourhood as a whole through the change process. A detailed report and presentation was made to Select Committee in July 2005. This report provides a brief update for Members on the following key issues.

• Rehousing & Demolition programme • Redevelopment programme • Extension to Ellergreen Leisure Centre and work to Norris Green Park

3. Key issues

Rehousing & Demolition Programme In summary, of 1509 properties, 758 properties are now demolished and there is a total rehousing commitment at December 2005 of approximately 490 families.

The demolition programme has progressed well in recent months with 758 properties now demolished across the estate. However the perennial problems with Transco disconnections continue to cause delays in the programme and so approximately 70 properties in complete blocks are waiting to be dropped once disconnection certificates are confirmed.

Redevelopment Programme The main legal documents with New City Vision and Cobalt were completed in January 2005. However before the Phase 1 development could start certain conditions precedent had to be met. These were:

• The Council had to deliver vacant possession and prove good title for Phase 1.

• New City Vision had to obtain outline planning permission for Phase 2 and 3.

• New City Vision had to undertake detailed site investigations to ensure that the extent of any ground remediation did not jeopardise the project.

• New City Vision had to obtain road closure orders for highways within Phase 1. This procedure takes a minimum period of 5 months through the Magistrates Courts and could not start until all residents on the roads affected were rehoused by the Council. The Council in turn could not include the land under the roads in its title until closure orders were agreed. All these conditions were complied with by December and New City Vision started to secure the Phase 1 site on 5th December. This will be complete in mid January and construction work will start immediately thereafter.

The development agreement lays down that Phase 1 must be completed within 25 months of start on site i.e. 5/01/07. In fact New City Vision aim to have constructed and sold the 104 properties for sale within 18 months. The construction of the 90 social housing units will take precedence and the New City Vision/Cobalt programme should ensure units are available from October 2006.

Negotiations with Cobalt and New City Vision regarding the provision of further social housing units in Phase 2 are ongoing. The dwelling mix for social housing units is tentatively agreed however some shared ownership is still to be factored in but approximately 50 further units should be available.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Norris Green Village 'Boot' EstateReport 4 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Norris Green Village 'Boot' EstateThis decision
  2. Former nursing home site, Long Lane, Walton, Liverpool L9 6DN (Norris Green Ward)Approved
  3. 183 Scargreen Avenue L11 3BA (Norris Green Ward)Approved
  4. Land at Deanscale Road, Rushmere Road & Bowscale Road, Liverpool 11 (Norris Green Ward)Approved
  5. Land at Branthwaite Crescent/Bowscale Road, Liverpool 11 (Norris Green Ward)Approved
  6. Inliverpool Special Purpose Vehicle - Norris Green Land Transfer (Phase 1b) (L/25)Approved

More from Liverpool Housing and Community Safety Select Committee 2005/2006

All decisions
MeetingDecisionOutcome
3 Apr 2006 Minutes of the Last MeetingAgreed that the minutes of the last meeting of this Select Committee held on 7 February 2006 , be approved as a true ... Agreed Open
3 Apr 2006 Minutes of Scrutiny PanelsAgreed that;- the Minutes from the meeting of the Building Maintenance Scrutiny Panel held on 3 March 2006; be approv... Agreed Open
3 Apr 2006 Question TimeAgreed that the information requested be submitted to a future meeting of this Committee .. Agreed Open
3 Apr 2006 Gateacre Neighbourhood Committee - Lanfranc Close/Castletown CloseIt was agreed that: a) The Neighbourhood Committee are in full support of the residents and request that Officers and... Agreed Open
3 Apr 2006 Equalities Impact Assessment Statement, Community SafetyAgreed that;- § the information contained in the report be noted; and § the Community Safety team be thanked for thei... Agreed Open