Regeneration & Environment Select Cttee 2005/2006 agreed this item on Thursday 13 January 2005. Below is the council's own wording, with the papers it was decided on.

Item48

Resolved

Agreed that the report on the forthcoming Audit Commission Inspection to take place between 28 February and 4 March 2005, be noted.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Regeneration & Environment Select Cttee 2005/2006, 11 pages

Report to Select Committee

Liverpool City Council

Report to: Regeneration & Environment Select Committee

Subject: Street-based Services Inspection

Report no: EDR/7/05

Date: 13th January 2005

Reporting officer: Tom McCabe AED

Contact officer: Mark Smith 225 - 6378

Ward: All

1. Purpose & Recommendations The purpose of this report is to advise Members of:

• The scope and details of the forthcoming Audit Commission Street- based Services Inspection from Monday 28th February to Friday 4th March 2005; • Work being carried out by officers in preparation for the Inspection. 2. Relevant Background Information Members will be aware that a full Audit Commission Inspection of Street- based Services was carried out in summer 2002 covering:

• Highways and Lighting Maintenance; • Refuse Collection, including bulky collections and trade waste; • Street Cleansing; • Grounds Maintenance.

The result of the inspection was that the service was deemed to be “poor – no stars” but with “promising prospects for improvement”.

The Audit Commission were due to carry out a re-inspection of Street-based Services in summer 2004 and this was viewed as the opportunity to convey the hard work and improvements to the Audit Commission and greatly improve the “poor” rating. Unfortunately, the Council had an insufficient allocation of Audit Commission inspection days available so the inspection did not take place.

The Audit Commission now propose to carry out an inspection at the end of February 2005. Even though the scope of the inspection will be different it will encompass the majority of the recommendations for improvement from the 2002 inspection.

3. Scope and Details of Inspection One of the flaws in the original Best Value Review process was that the scope and extent of Review could vary from one Authority to the next making comparisons between Authorities in terms of quality of service more difficult.

As a result, the Audit Commission is now working to a standard scope for inspections as far as reasonably possible. The standard scope which ties-in with Street-based Services is Waste Management (includes refuse collection and street cleansing) and it is proposed that this scope is used for the forthcoming inspection.

The Inspectors will carry out a rigorous assessment of the quality of our services considering factors such as:

• Establishment of policy and strategy; • Business planning; • Performance Indicators; • Views of Members and public; • Views of officers – managers and front-line staff; • Partnership working and views of stakeholders; and • Reality checks of responsiveness and quality of service.

This will be used to form a judgement on Quality of Service between “zero stars – poor” and “three stars – excellent” and the self-assessment guidance on establishing this rating is appended to this report.

The inspectors will also give us a second judgement on Prospects for Improvement between “poor” and “excellent” and our ability to deliver on the recommendations of the 2002 inspection, including highways, will strongly influence this.

A Self-assessment Document and supporting Portfolio of Evidence will be provided to the Inspectors in advance of the five day inspection. The inspection itself will be carried out by Jane Hawkes (involved in the 2002 inspection) and Mike Baker and will involve a schedule of interviews and focus groups, a city tour followed by random site visits and “mystery shopper” exercises and review of supporting documentation.

4. Preparation for Inspection The scope and detail of the inspection were discussed with the Audit Commission on 7th January and a Project Delivery Plan has been produced to prepare for the Inspection. This will involve intensive work by Council officers and service delivery partners and focuses on the following key headings:

• Preparation of Self-assessment and Portfolio of Evidence; • Community Engagement; • Education and Enforcement; • Business Planning; • Demonstrating Value-for-money; • Service Delivery and Operational Readiness.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Street Based ServicesReport 11 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Street Based ServicesThis decision
  2. Street Based Services – Service Improvement Plan – 6 monthly update.Agreed
  3. Update on Delivery of Street Based Services - Service Improvement PlanAgreed

More from Liverpool Regeneration & Environment Select Cttee 2005/2006

All decisions
MeetingDecisionOutcome
30 Mar 2006 Neighbourhood Management Boundary Review - PresentationAgreed that – (a) the report and the views expressed by Members be noted and taken into consideration in the preparat... Agreed Open
30 Mar 2006 Liverpool Plus - Strategic Investment FundAgreed that (a) the report be noted; and (b) a further report be submitted to the Committee in due course Agreed Open
30 Mar 2006 Annual ReportAgreed that the annual report of the Select Committee for 2005/06 be noted. Agreed Open
30 Mar 2006 Carbon Dioxide EmissionsAgreed that (a) the report be noted; and (b) a further report be submitted in 6 months time to include - · the progre... Agreed Open
30 Mar 2006 Response to Council Motion - Pedistrian Crossing Muirhead AvenueAgreed that a report on the results of the traffic survey be submitted to the appropriate Neighbourhood Committee as ... Agreed Open