Called in Item - Kings Waterfront Civic Facilities
AgreedCommittee1 paper
Regeneration & Environment Select Cttee 2005/2006 agreed this item on Thursday 13 January 2005. Below is the council's own wording, with the papers it was decided on.
Agreed that - (a) the recommendation be approved and Councillor Storey be requested to ensure that the future report identified in paragraph (iii) of the recommendation is also submitted to this Committee for scrutiny ; and (b) arrangements be for a seminar for Members of the Select Committee to explain the principals outlined in the ‘Egan’ report and the affect on the types of contract which the Council enters into. Councillor Steve Munby dissenting.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Report to Regeneration & Environment Select Cttee 2005/2006, 7 pages
Background
The Kings Waterfront site extends to some 14.6 hectares located immediately to the south of Albert Dock. The site was reclaimed by the Merseyside Development Corporation in the 1980’s and was inherited by English Partnerships on the demise of the Corporation in 1999. Its current use is for surface car parking and temporary use during the Summer Pops.
The aspirations for the regeneration of the Kings Waterfront site are detailed in the Strategic Regeneration Framework. The core objective identified in the framework is to develop the site into a world class visitor destination. There has been a significant amount of ongoing design development which has resulted in increased definition to the development profile. The proposals briefly comprise residential, community, commercial and the civic facilities, with this report concentrating on the civic elements. These comprise of:
9-10,000 seat arena.
1,350 seat main conference auditorium plus breakout rooms.
Up to 8,000m² of exhibition space.
1,600 space car park.
major areas of public realm space.
Civic Facilities Procurement
The first phase of development comprises the basic servicing of the site (managed by English Partnerships) and construction of the Conference / Arena, Exhibition facilities, Car Parking and Public Piazza.
English Partnerships, as site owner, will be responsible for the provision of the basic site infrastructure, for the provision of the land for the conference / arena facilities and for agreement with all developers of the areas not contained within the Civic Facilities. As approved in the earlier report Liverpool City Council will be contractually responsible for the delivery of the Exhibition space, Conference / Arena facilities, Car Parking and Public Piazza. The funding profile between NWDA, EP, LCC and objective was detailed in the previous report.
The procurement strategy for the construction is by way of Two Stage Design and Build Contract, with maximum risk transference to the contractor. This approach is designed to, at an early stage, minimise the Council’s exposure to risk, whilst ensuring transparency of cost up to the point of risk transfer to the contractor.
Officers have sought professional advice from Davis Langdon in relation to this strategy and are satisfied that it represents the most appropriate procurement route.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
50Called in Item - Kings Waterfront Civic FacilitiesThis decision
Hear about the next one first
Follow Regeneration & Environment Select Cttee 2005/2006 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.