Executive Board, Friday 21 January 2005

Phythian Street/Low Hill (RES/47)

Agreed Executive 1 paper

Executive Board agreed this item on Friday 21 January 2005. Below is the council's own wording, with the papers it was decided on.

Item118b

Resolved

Resolved that the City Council grant Braidwater Limited a new long lease on the land at Phythain Street/Low Hill co-terminus with the lease of their adjoining site, on full repairing and insuring terms at a peppercorn rental, subject to the payment of a premium of £56,000 plus surveyor’s fees of £2,800, the Council’s legal costs of £2,240 and otherwise on terms agreed by 2020 Liverpool Limited and approved by the Operations Manager for Land and Development Services.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 5 pages

Executive summary

This report has been prepared by 2020 Liverpool Limited to seek authority to grant the developers, Braidwater Limited a new long lease on the above land co-terminus with the lease of their adjoining site expiring on 19 March 3001.

The land extends to 600 sq. metres (0.06 hectares) and is subject to a Stopping-Up Order because it is part of the adopted highway, Phythian Street. It is to be incorporated into Braidwater’s development of the adjoining site for residential purposes. The scheme comprises the construction of 67 no. two/three/four/five storeys apartments together with associated car parking, landscaping and ancillary works. Planning and Building Control have advised that Planning permission for the scheme was granted on condition that the subject land is incorporated into the development.

Highways Management have advised that proceedings in Court to obtain the Stopping-Up Order are already in progress.

Following negotiations terms have been provisionally agreed for Braidwater Limited to be granted a new long lease of the land co-terminus with the lease of their adjoining site, on full repairing and insuring terms at a peppercorn rental, subject to the payment of a premium of £56,000 plus surveyor’s fees of £2,800 and the Council’s legal costs of £2,240.

The proposed transaction is recommended by 2020 Liverpool Limited who certify that the terms recommended represent the Best Price reasonably obtainable at the present time and the date of valuation of 18 November 2004. Executive Member/Executive Director recommendation (Councillor Keith Turner/Charlie Parker)

That the City Council grant Braidwater Limited a new long lease on the land co-terminus with the lease of their adjoining site, on full repairing and insuring terms at a peppercorn rental, subject to the payment of a premium of £56,000 plus surveyor’s fees of £2,800, the Council’s legal costs of £2,240 and otherwise on terms agreed by 2020 Liverpool Limited and approved by the Operations Manager for Land and Development Services.

Key Decision?

No Forward Plan/5 days notice/special urgency

No

Implementation effective from

28 January 2005 Timescale for action

The City Solicitor will be instructed to complete documentation at the earliest opportunity. Reason(s) for Recommendation

1. The proposed residential development will contribute to the ongoing regeneration initiatives taking place within the area under HMRI.

2. If the land is not leased as proposed the Council will be left with the responsibility for its maintenance.

3. A capital receipt will be generated

Alternative options to be considered

Retain the status quo. This would restrict access to funding, deter redevelopment of the adjoining land and the regeneration of the area. Consultation

Highways Management, Planning and Building Control have been consulted and are supportive of the proposed lease of the land.

Financial implications

Capital 2004/2005 Premium £56,000 Revenue 2004/2005 Surveyor’s fees £ 2,800 Legal fees £ 2,240

The premium contributes to the City Council’s capital receipt forecast and the surveyor’s fees and legal costs contribute to existing revenue budget forecast.

Best Value:

The Operations Manager for Land and Development Services considers Best Value to be demonstrated as it will contribute to the regeneration of the area and reduce the maintenance responsibility.

Equality implications

The granting of a new lease will contribute to and encourage the ongoing regeneration of the area to the benefit of all sectors of the community.

Corporate strategy:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Phythian Street/Low Hill (RES/47)Report 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Phythian Street/Low Hill (RES/47)This decision
  2. Kensington Fields Area, Towerlands Street Area, Phythian Estate Area, Queensland Street area and Aigburth Street area Residents' Parking Scheme, Limited Waiting & Prohibition Of Waiting/Loading, Central, Kensington & Fairfield, Princes Park and Picton WardsDecided

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies