Resolved that – (i) the Executive Director (Resources) – · be authorised to progress negotiations for the financing of the capital expenditure required for the Kings Dock and 50 Metre pool developments by way of a leasing arrangement with a special purpose vehicle company; · be authorised to mandate Arllingclose to act as the council’s specialist advisers in negotiating and securing this financing route; and · monitor and minimise the council’s financial exposure arising from the negotiation of this arrangement prior to contractual commitments to the developments and financing arrangements; and (ii) the decision be referred to the Resources Select Committee at its special meeting to be held on Monday 24 January.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
The Council intends contributing significant capital resources to the development of the Kings Dock Arena, Conference & Exhibition Centre and a 50 metre swimming pool to replace the closed pool at Picton. Whilst the schemes will bring in financial support from partners, the required commitment from the Council is substantial ie. circa £12 million and £8 million respectively. There is no external support for the Council’s contribution which means that it will need to be funded through unsupported borrowing. This would represent major commitments and would impact upon the Council’s budgets in future years. More recently, partners in the Kings Dock scheme have made it clear that they expect the Council to fund the Fittings within the scheme. This expenditure could be substantial but in return, officers have suggested that the City Council could take advantage of any potential tax allowances. Partners have agreed this although it is up to the Council to identify the means to achieving this.
In order to potentially help alleviate the financial commitment to the Council, Officers have been working to identify a potential funding vehicle which may provide an advantageous way to provide the capital resources by accessing the tax allowances which are normally only available to the private sector.
Progress
Following discussions with specialist leasing consultants based in the City of London a potential vehicle has been identified. Such tools are used by private sector developers. Provision of the capital resources through a special purpose vehicle enables tax relief available on capital expenditure to be reflected in a reduced leasing rental payable by the council for the facilities. This would result in savings as compared to capital expenditure financed through borrowing. The value of those savings will depend upon the proportion of the development expenditure eligible for capital allowances. Legal Issues
Officers are satisfied on the basis of legal advice and a preliminary discussion with the Audit Commission that this financing route is both viable and cost effective. Use of such a financing route has been agreed in principle by funding partners.
Preferred Route
The route is particularly complex and in large part bespoke to a company known to the Council, Arlingclose. A number of discussions have been held with the Company and in order to progress this financing route, realise the potential savings, and facilitate entry into contracts for the developments it is now necessary to formally mandate Arlingclose to act for the council. Detailed negotiations could then begin with potential funding banks who have expressed interest in the scheme. Development of complex legal documentation to govern the relationships between the various parties to the transaction could begin.
Mandating Arlingclose would require a financial commitment by the Council in the form of an engagement fee to Arlingclose and a commitment to underwrite legal costs. If for any reason the Council subsequently chose not to proceed with the financing route this expenditure would be abortive and would also include a cancellation fee. The value of any such abortive expenditure would be greater dependent upon the extent of legal costs incurred to the stage at which the process was halted.
The Executive Director for Resources has evaluated any risk of abortive expenditure in comparison to the potential savings available through this funding mechanism and would recommend that Arlingclose be immediately mandated to progress this issue. Controls will in any event be put in place to monitor and minimise the council’s exposure.
Executive Director recommendation (Phil Halsall):
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.