Called in Item - Capital of Culture Experience 08 Place

Agreed Committee 1 paper

Resources Select Committee 2005/2006 agreed this item on Friday 25 February 2005. Below is the council's own wording, with the papers it was decided on.

Item82

Resolved

Agreed that it be recommended to the Executive Board, that the Executive Member recommendation L/10, be not approved until after the meeting of the Capital of Culture 08 Scrutiny Panel to be held on 7 March, to allow proper scrutiny of the proposals to take place.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Resources Select Committee 2005/2006, 2 pages

Executive summary

The Executive Board at its meeting of the 28th November 2003 agreed to enter into a lease agreement to develop a Capital of Culture ‘front office’, (‘the 08 Place’). The report also considered the opportunity of integrating the Mersey Partnerships ‘Tourist Information Centre’s’ (TIC’s) into the development. Estimated fit out costs of £900k were included within this report.

A further detailed report outlining the development of the project, integration of TIC’s, operational implications and funding streams totalling £2.2m was submitted to by the Executive Board on 15th October 2004.

Subsequently, contractor sums have been agreed and permission is now sought to commence spend of the £2.2m costs which are made up of £1.4m Neighbourhood Renewal Fund (NRF), £245k SRB and £555k capital resource. The fit out cost being £1,422,400.23.

Leader/Chief Executive recommendation (Councillor Mike Storey, CBE/Sir David Henshaw)

1. The Council’s Capital Programme to be amended to include a project provision of £ 2.2 million;

2. The funding for the Capital Programme to be amended to reflect that the funding is through a combination of £1.4 million NRF, £ 245K SRB and £555k capital resource;

3. The Executive Director be authorised to accept the offer of grants from NRF and SRB; and

4. The Executive Director be authorised to commence spend of project costs totalling £2.2m which includes the fit out of the 08 Place at the cost of £1,422,400.43. Key Decision?

Yes

Forward Plan No – Appropriate Notices will be served under the Constitution

Implementation effective from 11 February 2005

Timescale for action

As NRF and SRB funding streams are time limited to this financial year, it is vital that work commence immediately. Yes, SRB and NRF funding need to be spent in financial year 2004/2005

Reason(s) for Recommendation

As Above

Alternative options to be considered

N/A

Consultation

N/A

Financial implications

Funding will be lost if not spent in this financial year jeopardising the project.

Best Value:

N/A for this report

Equality implications

N/A for this report

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Called in Item: Capital of Culture Experience 08 PlaceReport 2 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Called in Item - Capital of Culture Experience 08 PlaceThis decision
  2. Called-In Cabinet Decision - Revenue and Capital Finance Report 2025/26 (Quarter 3)Approved
  3. Called In Item - Amendments to the Approved Housing Capital Programme 2009/10 at the end of the Third Quarter (SSC/38)Approved
  4. Called In Item: Primary Capital Programme Strategy for Change - Approval (ESE/11)Agreed
  5. Called in Item - 2006/07 Transportation Capital Programme (R&T/30)Agreed
  6. Called in item - picton 50m swimming pool - revenue and capital (l23)Agreed

More from Liverpool Resources Select Committee 2005/2006

All decisions
MeetingDecisionOutcome
5 Apr 2006 Minutes of the Last MeetingsAgreed that the minutes be approved. Agreed Open
5 Apr 2006 Called In Item - Percy Street/Upper Parliament Street/Parliament StreetAgreed that in view of the concerns expressed by members, consideration of this proposal be deferred pending the subm... Agreed Open
5 Apr 2006 Response to Motion - Properties in Newsham ParkAgreed that the Executive Member for Resources be requested to ensure that all long term vacant Council properties in... Agreed Open
5 Apr 2006 Revenues and Benefits Service PerformanceAgreed that the content of the report be noted. Agreed Open
5 Apr 2006 Green Paper - A New Deal For Welfare Empowering People to WorkAgreed that – a) The contents of the report be noted; b) The views of the Committee, particularly in relation to the ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies