Resolved
Agreed that Executive Member recommendation RES/56, be approved for implementation. _____ The meeting then adjourned. _____
Resources Select Committee 2005/2006 agreed this item on Friday 25 February 2005. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that Executive Member recommendation RES/56, be approved for implementation. _____ The meeting then adjourned. _____
Wavertree Customer Focus Centre report was agreed in September 2004 (RES/24) with a pre-tendered estimated project cost of £1.5 million.
It is proposed to create the fourth Customer Focus Centre in this location. Currently based on site is Chatsworth former Housing Office, Wavertree Road Supported Living and The Family Advisory Service building.
These buildings, will be refurbished to full DDA standards with an open plan design, shared meeting/interview facilities and potential to house up to 350 staff. Currently this site houses just 90 staff. More effective ICT and mobility support will be explored, along with assessment for the suitability of teleworking where appropriate, helping to maximise the use of office space, reducing the overall space per head.
The three buildings would be extensively refurbished to provide a ‘back’ office facility for mixed service provision promoting joined up working to the benefit of the customer. These buildings have significant maintenance and security issues and fail DDA standards (with all the associated cost implications, they also provide a poor working environment for staff and this will be address as part of the refurbishment works. 2. Proposal
To approve additional spend of £200,000 from agreed NRF grant allocation, to ensure this site is adequately protected and effectively redeveloped for maximum useage.
Executive Member/ Executive Director (Councillor Keith Turner / David McElhinney)
To confirm that the Family Advisor Center, Chatsworth Former Housing Office and Wavertree Social Services building will be redeveloped as a Customer Focus Centre at an additional cost of £200,000 from agreed NRF funding allocation.
Key Decision?
Yes .
Forward Plan/5 days notice/special urgency
Implementation effective from
11 February 2005
Timescale for action
Officers have commenced procurement process and investigations to refurbish this building in a manner which meets the requirements of contract Standing Orders and Financial Regulations.
Reason(s) for Recommendation
This development contributes to the accommodation strategy allowing us to rationalise buildings leased and owned and comply with DDA obligations
Existing buildings which will be vacated as a result of this development, have significant maintenance issues providing poor working environments, and have major Disability Discrimination Act (DDA) implications. By proceeding with this project these potential costs (estimated at £200,000) will be avoided. Alternative options considered
All existing accommodation across all districts of Liverpool were considered for development as a Customer Contact Site/ Customer Focus Centre. Geographical limitations and height/size restrictions were applied in final selection.
Customers, staff and trade union consultation will continue and is included in the project plan for each customer focus centre (on a project by project basis).
This project was approved by the Executive Board in September 2004 based on a pre-tendered estimated cost of £1.5m. Following a full structural survey and site visit by locally based community police, additional security measures and structural changes are required. An additional £200,000 is therefore required has been agreed as part of Central Services NRF budget allocation.
Revenue Implications
None as a result of this report.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Called in Item: Wavertree Customer Focus CentreReport | 4 pages | DownloadRead as text |
Follow Resources Select Committee 2005/2006 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Apr 2006 | Minutes of the Last MeetingsAgreed that the minutes be approved. | Agreed | Open |
| 5 Apr 2006 | Called In Item - Percy Street/Upper Parliament Street/Parliament StreetAgreed that in view of the concerns expressed by members, consideration of this proposal be deferred pending the subm... | Agreed | Open |
| 5 Apr 2006 | Response to Motion - Properties in Newsham ParkAgreed that the Executive Member for Resources be requested to ensure that all long term vacant Council properties in... | Agreed | Open |
| 5 Apr 2006 | Revenues and Benefits Service PerformanceAgreed that the content of the report be noted. | Agreed | Open |
| 5 Apr 2006 | Green Paper - A New Deal For Welfare Empowering People to WorkAgreed that – a) The contents of the report be noted; b) The views of the Committee, particularly in relation to the ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.