Anfield/Breckfield Regeneration Framework - Anfield Youth Club (Phase 2&3) Revision (LS&C/19)

Approved Executive 1 paper

Executive Board approved this item on Friday 1 April 2005. Below is the council's own wording, with the papers it was decided on.

Item163g

Resolved

Resolved that – (i) the Divisional Manager (Regeneration Programmes) and the Head of Sport & Recreation Services (ELSS) be authorised to continue the delivery of Phase 2 and Phase 3 works for the regeneration of Anfield Youth Club; (ii) authority to be granted for the Executive Director (Regeneration), to accept grants up to £600,000 from Barclays Spaces for Sport funding phased over the financial year 2005/6, to contribute towards the cost of the Anfield Youth Club regeneration. The City Council will thereby accept the role of the Accountable Body and ensure the grant is administered appropriately; (iii) the Divisional Manager (Regeneration Programmes) be appointed as the nominated officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises; (iv) expenditure on this project be only incurred in accordance with Standing Orders and Financial Regulations, after the receipt of confirmation of funding from all the relevant organisations/bodies upon which this project relies for income and the finalisation of all other relevant documents; (v) the City Council’s capital budget be adjusted, and on receipt of formal approval letters for the grant, to reflect expenditure on this project for a sum up to £2.025 Million phased over the financial years 2004/5 (£0.486 Million), 2005/6 (£1.44M) and 2006/7 (£0.06M); and (vi) further reports to be submitted to Members on completion of the building programme.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 8 pages

Executive summary

1.1This report seeks Executive Board approval to receive further grant support to accelerate and evolve the Anfield Youth Club project.

1.2In March 2004 (Report LS&C 25) the Executive Board was informed of the Anfield Breckfield Regeneration Strategy and the positive role of Anfield Youth Club (AYC) in facilitating the wider, holistic regeneration plans. The Executive Board agreed to the inception of Phase 1 improvements at AYC; the vital remodelling of the Sports Pitches on the adjacent Lower Breck Recreation Ground, and were informed of further phased work including improvements to the AYC building and an adjacent multi-use games area. A subsequent report in September 2004 (REG/27) authorised the Head of Sport and Recreation services (ELSS) to progress the detailed design and tendering arrangements for the delivery of Phase 2 and Phase 3 works to the regeneration of Anfield Youth Club using Neighbourhood Renewal Funding.

1.3The September 2004 report also authorised the Divisional Manager for Regeneration Programmes to submit an application for further grant funding to the Football Foundation for Phase 3 investment in this project during financial year 2005/6

1.4Investment in AYC will assist in the continuation of activities currently at Vernon Sangster Community Sports Centre in the two-year period when a new Vernon Sangster facility is being built into the proposed New Anfield stadium. The City Council’s Planning Committee agreed Liverpool Football Club’s Planning Application on 30th July 2004. The new stadium development is currently planned to commence in 2005.

1.5Liverpool Football Club has recently been approached by Premier League Sponsor Barclays Bank regarding support and investment in community based projects. ‘Spaces for Sport’ is a national funding programme sponsored by Barclays Bank (channelled through the Football Foundation). It is aimed at all Premier Football League Clubs supporting a community project of their choice. Football is the specified theme for support but there is an expectation that projects benefit other sports also. Furthermore projects must be developed and delivered through a partnership approach. Barclays Spaces for Sport have acknowledged the importance of the AYC scheme and have commissioned an application for grant (this is not a bidding process) for this project. The City Council is a leading partner in this project with AYC and Liverpool Football Club. As landowner and Accountable Body for existing project funding streams it is proposed that this new funding opportunity be managed in the same way. Permission is therefore sought to be Accountable Body and to accept and manage grant funding from Barclays Spaces for Sport.

2. Anfield Youth Club

2.1Together the costs for the improvement to AYC and Lower Breck are estimated to cost in the region of £1.986M, including the Pitches, building remodelling and access road. Works are underway and will be phased during 2004/5, 2005/6 and 2006/7. Funding is available for this project on the basis that it forms part of the New Anfield Breckfield proposals incorporating the New Anfield Stadium proposal.

2.2Phases 2 and 3 of the project incorporate works to the AYC building and include implementation of the all weather provision and the commencement of building refurbishment. The cost associated with the Phase 2 AYC works will be funded through Neighbourhood Renewal Fund (New Anfield; A Premier Vision for Stanley Park project approval), and Spaces for Sport funding.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Anfield/Breckfield Regeneration Framework: Anfield Youth Club (Phase 2&3) Revision (LS&C/19)Report 8 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 21 attended
MS
Councillor Mike Storey CBEChair, apologies
WB
Councillor Warren BradleyMember, present
JC
Councillor Jeremy ChowingsMember, expected
PC
Councillor Paul CleinMember, present
FC
Councillor Flo Clucas OBEMember, present
MF
Councillor Marilyn FieldingMember, present
RM
Councillor Richard MarbrowMember, present
PM
Councillor Peter MilleaMember, present
RO
Councillor Richard OglethorpeMember, present
KT
Councillor Keith TurnerMember, apologies
SD
Sir David HenshawOfficer, apologies
PH
Phil HalsallOfficer, apologies

All 21 on the meeting page

On this subject at Liverpool

Search all
  1. Anfield/Breckfield Regeneration Framework - Anfield Youth Club (Phase 2&3) Revision (LS&C/19)This decision
  2. Anfield Breckfield Redevelopment Phase 2, Land at Robson Street to Adam Street and St Domingo Vale to Herschell Street, Liverpool 5 (Everton Ward)Approved
  3. Grant for 2009/10 from the Homes and Communities Agency (HCA) for the Anfield and Breckfield Renewal Area (SSC/18)Approved
  4. Anfield/Breckfield Regeneration Area - Land bounded by Sleepers Hill/Robson Street/St. Domingo Vale/Oakfield Road/Back Rockfield Road/Walton Breck Road, Liverpool, L4 Everton WardApproved
  5. Housing Investment in Anfield/Breckfield Renewal Area - City Council 12 July 2006Decided
  6. Anfield/Breckfield Regeneration Area - Land bounded by Sleepers Hill/Robson Street/St. Domingo Vale/Oakfield Road/Back Rockfield Road/Walton Breck Road, Liverpool, L4 (Everton Ward)Approved

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies