Resolved
RESOLVED That the presentation and briefing be noted. ___ The Chairman thanked everyone for their attendance and closed the meeting.
Planning Committee 2010/21 old noted this item on Monday 18 April 2005. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the presentation and briefing be noted. ___ The Chairman thanked everyone for their attendance and closed the meeting.
To brief the Committee on the Building Schools for the Future programme.
That the report be noted.
INFORMATION
The BSF programme announced by the Government in June 2003 gives Liverpool the opportunity to complete the review of its secondary estate. Whilst there has been investment in some secondary schools over recent years a significant number of schools are still in a poor physical condition and many are inappropriate for the delivery of a 21st Century curriculum.
BSF is, however, much more than a school building programme. It enables the Authority to create provision for secondary-age pupils that is: Flexible, offering greater individual learning programmes and styles which will ensure that every child achieves and enjoys learning.
Inclusive, providing for all learners and their community regardless of ability, special need, age or individual social requirements.
Cutting edge, utilising an extensive ICT infrastructure to enhance flexibility of both spaces and the styles of learning and offering anywhere anytime access.
Rooted in their communities, offering a range of linkages beyond learning which will ensure that young people are healthy and able to make a positive contribution to their community.
Part of the City’s profile for international excellence in Capital of Culture 2008 and beyond.
Within healthy, sustainable places which support the City’s environmental agenda.
Most crucially it will enable the Authority to ensure that schools are fit for purpose to deliver the five major priorities in Every Child Matters.
The programme of development through BSF funding will be driven by a strategic vision which will set out in detail expectations in relation to learning and teaching, ICT provision and extended school opportunities. In addition the Vision will look at the organisation of school places and the factors which should drive:
The geographical position of schools
The size of the secondary estate
The phasing of the programme
The Vision is part of the Strategic Business Case, which has to be with the DfES at the end of May 2005. This will include details of the overall priorities which will drive the selection of the schools to be included in the programme. In October 2005 the Outline Business Case has to be produced and this will include details of the schools which are to be developed in this first stage. The allocation which Liverpool has received for this first wave is just under £140 million but further funding, of a similar order should follow in five years time. The funding will not support the rebuilding of all secondary schools in the City and in fact this is not required but it will support about 50% new build and the rest refurbishment of existing buildings, which have not already received significant capital investment. To support the Building Schools for the Future Programme the DfES commissioned 12 exemplar designs and these demonstrate the kind of physical environment, which will support the transformational learning agenda. All the designs have been agreed by CABE who were directly involved in this piece of work. It was originally said that all the designs were affordable within the allocations made by the DfES but in fact this has not proved to be the case and they would need to be modified. They do however provide some models of good school design.
In working up the designs once the Outline Business Case has been accepted CABE will provide some consultancy support and in addition we shall need to identify a design champion who will be independent of the architects. Discussions are well advanced with John Moores University Department of Architecture who are developing a specialism in school design and we hope to work with some post graduate students in developing the design brief with schools.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Building Schools for the FutureReport | 4 pages | DownloadRead as text |
Follow Planning Committee 2010/21 old at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jun 2020 | Minutes of the Last MeetingResolved that the minutes of the Virtual Meeting of 2 June 2020 be approved. | Approved | Open |
| 2 Jun 2020 | Minutes of the Last MeetingResolved that the minutes of the Virtual Meeting of 26 May 2020 be approved. | Approved | Open |
| 26 May 2020 | Minutes of the Last Virtual MeetingsResolved that the minutes of the Virtual Meetings of 5 and 12 May 2020 be approved. | Approved | Open |
| 31 Mar 2020 | Minutes of the Last MeetingAgreed that the minutes of the last meeting held on 10 March 2020 be approved. | Agreed | Open |
| 10 Mar 2020 | Minutes of the Last Meeting 18 February 2020Resolved that the minutes of the last meeting held on 18 February 2020 be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.