Resolved that - (i) Liverpool City Council acts as Accountable Body for Objective One ERDF funding in respect of the Wellington Employment Park Development project; (ii) on the receipt of an offer letter from the Government Office North West that - · authority be granted for the Executive Director (Resources) to accept ERDF grant of up to £2,962,149towards the cost of delivering the project; · the Divisional Manager (Regeneration Programmes) be appointed as the nominated officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises; · the City Council’s capital programme be adjusted to reflect ERDF expenditure on this project of £1,066,614 during the financial year 2005/06, £981,503 during 2006/07, £849,098 during 2007/08, and £64,934 during 2008/09; and · authority be granted to commit expenditure in order to undertake works that will fulfil the terms of the ERDF offer letter; and (iii) further reports to be submitted to Members as and when appropriate to update on progress.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
1. Liverpool City Council as a key partner in the regeneration of the City, and as Accountable Body for Liverpool Land Development Company (LLDC) must act as the Accountable Body for Objective One ERDF funding. The latest scheme requiring agreement to act as Accountable Body is Wellington Employment Park Development, a speculative office / industrial development project to be undertaken on three sites adjacent to Sandhills station. Total eligible project cost is £13,135,266 with £2,962,149 ERDF sought from the Atlantic Gateway SIA allocation.
2. The project will be delivered by Langtree Developments, supported by the City Council as Accountable Body for the Objective One grant. Langtree were selected as preferred developer for the site following a competitive process in which proposals for development of Wellington Employment Park were considered by LLDC. The project sits within the LLDC’s business plan complementary to the City Council's corporate objectives and those of Liverpool First. It is included in the Atlantic Gateway SIA Integrated Development Plan.
3. Appendix 1 describes briefly the project, its funding package, timescale for delivery and anticipated outcomes. The project funding includes separate bids for Objective One funding and NWDA funding – the NWDA funding bid was made directly to the Agency by Langtree. This report seeks authority for LCC to act as Accountable Body for the Objective One funding. There is no requirement for LCC to provide financial contribution to the project costs but the capital budget will need to be adjusted to reflect the ERDF grant.
Executive Member/Director recommendation. Executive Director for Regeneration, Charlie Parker –
That Members approve that: 1. Liverpool City Council acts as Accountable Body for Objective One ERDF funding in respect of the Wellington Employment Park Development project.
2 On the receipt of an offer letter from the Government Office North West that:
(a) Authority be given to the Executive Director Resources to accept ERDF grant of up to £2,962,149 towards the cost of delivering the project.
(b) The Divisional Manager for Regeneration Programmes is appointed as the nominated officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises.
(c) The City Council’s capital programme be adjusted to reflect ERDF expenditure on this project of £1,066,614 during the financial year 2005/06, £981,503 during 2006/07, £849,098 during 2007/08, and £64,934 during 2008/09
(d) Authority be given to commit expenditure in order to undertake works that will fulfil the terms of the ERDF offer letter
3. Further reports to be submitted to Members as and when appropriate to update on progress.
Key Decision:
yes
Forward Plan
yes
Implementation effective from: Date of Decision
Timescale for action:
The construction will take place in two phases. Phase one will start on site in July 2005 and complete April 2006, phase two commencing April 2006 and completing in December 2007. Reason(s) for Recommendation:
To seek formal approval for Liverpool City Council to act as Accountable Body for ERDF grant that will allow the project to proceed.
Alternative options to be considered:
This is not considered to be an option. Neither LLDC nor Langtree are able to apply for the ERDF grant and Liverpool City Council, as a key partner in LLDC, has agreed to act as Accountable Body for projects that are part of the approved LLDC Business Plan LLDC.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.