Resolved that – (i) further work be done to determine the most appropriate structure for the Local Education Partnership; (ii) the proposed structure of the Project Board set out in part 6 of the Executive Summary to the report submitted be approved; (iii) the approvals and authorisations as set out in part 7 of the Executive Summary to the report submitted be approved; (iv) any capital receipts arising as a direct consequence of BSF will be re-invested in the programme as specified within the funding mechanism set by DfES ; and (v) further work be done to demonstrate how the affordability gap can be contained within the Education budget following detailed discussions with schools.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
1. Overall aims of the Building Schools for the Future (BSF) programme The BSF programme announced by the Government in June 2003 gives Liverpool the opportunity to complete the review of its secondary estate. Appendix 1 sets out capital works already undertaken in schools either through the Liverpool Schools PFI scheme or through conventional capital funding. However a significant number of schools are still in a poor physical condition and many are inappropriate for the delivery of a 21st Century curriculum.
BSF is, however, much more than a school building programme. It enables the Authority to create provision for secondary-age pupils that is:
Flexible, offering greater individual learning programmes and styles which will ensure that every child achieves and enjoys learning.
Inclusive, providing for all learners and their community regardless of ability, special need, age or individual social requirements.
Cutting edge, utilising an extensive ICT infrastructure to enhance flexibility of both spaces and the styles of learning and offering anywhere anytime access.
Rooted in their communities, offering a range of linkages beyond learning which will ensure that young people are healthy and able to make a positive contribution to their community.
Part of the City’s profile for international excellence in Capital of Culture 2008 and beyond. Within healthy, sustainable places which support the City’s environmental agenda.
Most crucially it will enable the Authority to ensure that schools are fit for purpose to deliver the five major priorities in Every Child Matters.
The programme of development through BSF funding will be driven by a strategic vision which will set out in detail expectations in relation to learning and teaching, ICT provision and extended school opportunities. In addition the Vision will look at the organisation of school places and the factors which should drive:
The geographical position of schools
The size of the secondary estate
The phasing of the programme
2. Funding
The funding available to Liverpool for the first phase of BSF is £138.7 million. Included within this sum is £14.6 million for ICT infrastructure. At this stage it is not clear how much funding will be in the form of conventional capital either as capital grant or supported borrowing and how much through PFI credits. To an extent the split will be determined by the nature of the first phase programme.
It is a requirement of the BSF programme that any receipts generated as a result of BSF funded schemes are re-invested in the whole programme.
3. Present Position of Secondary Estate
This is set out in Appendix 1. At this stage no decisions have been made or even formulated about which schools should be in Phase 1 of BSF. However it is clear from recent information from the Partnership for Schools (PfS) that the following categories of schools may not qualify for inclusion:
Schools presently in PFI schemes
Schools which have been rebuilt or are new within the last 15 years.
Schools which have received significant capital investment although are not complete new builds
Clarification on the exact meaning of this last point is still being sought. 4. Transformational Vision
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.