Resolved
Agreed that the contents of the annual review be noted.
Resources Select Committee 2005/2006 agreed this item on Wednesday 3 August 2005. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that the contents of the annual review be noted.
INTERNAL AUDIT
ANNUAL REVIEW 2004/05 INTERNAL AUDIT
ANNUAL REVIEW 2004/05
INTRODUCTION There are two elements to this review: • An assessment of Internal Audit service delivery and performance in 2004/05; • A summary of significant issues arising from Internal Audit work during 2004/05. Internal Audit conducted and reported on over 300 exercises and investigations in 2004/05. It is not the purpose of this review to chronicle each of these exercises. The emphasis is to concentrate on significant issues relating to key controls impacting on the control environment, both corporately and at service level. Where appropriate, these are illustrated by selected case studies.
INTERNAL AUDIT SERVICE DELIVERY and PERFORMANCE IN 2004/05 Audit Plan A key requirement of the Audit plan is for it to remain flexible to enable changing circumstances to be responded to effectively during the year. A planned input of 3,891 days was included in the Audit plan with the final outturn amounting to 4,174 days, which represents 107% of planned time (compared to 104% in 2003/04). The number of audit exercises undertaken amounted to 195 against a planned total of 193, which represents 101% of planned audits (compared to 98%in 2003/04). It is worth noting that this was achieved despite the absence of a Lead Audit Manager through sickness for six months. In addition to planned audit exercises, 69 investigations were undertaken, together with 37 other responsive exercises. This is a marked reduction in the number of such cases compared to previous years and is analysed in more detail later in this review. A summary of the planned days and actual days for each portfolio is provided below. Exhibit 1: Audit Plan 2004/05 – Summary Outturn
Audit Plan Days Actual Days Portfolio Programmed Responsive Total Programmed Responsive Total Work Work Work Work Corporate & Cross Cutting 710 103 813 791 119 910
Resources 252 20 272 222 20 242
Central & Customer 91 41 132 61 32 93
LDL 282 40 322 319 69 388
Housing Benefits Specific 218 218 225 225
1 SL&CS 302 123 425 330 197 527
Regeneration 370 279 649 375 312 687
Children’s Services 346 199 545 288 308 596
Schools Specific 330 330 392 392
Other Contracted Work 185 185 114 114
Total 3086 805 3891 3117 1057 4174
In previous reports to this Committee it has been explained that Audit planning is never an exact science and it would be highly unusual for the actual days in all portfolio areas to equate exactly to the planned days. For the most part, the above table shows the outturn to be within reasonable parameters of the planned days. Where there are significant variations, these are commented on later in this review in the sections dealing with individual portfolios. Performance Management Framework Within the Council’s performance management framework the key performance indicators for Internal Audit are set out in the table below, together with the outturn at the year end. Exhibit 2: Internal Audit Performance Indicators
Performance Measure Target Final Outturn – Comments 2004/05 March 2005
Percentage of Productive Time 72% 72.5% Slightly above target.
Completion of Audit exercises 97% 101% Target exceeded consistent with the Audit Plan
Percentage of Audit Reports 87% 80% Below target - see comments issued within time target below
Percentage of three star Audit 80% 93% Target exceeded – see comments recommendations confirmed below as implemented
Percentage of customers 86% 86% Target achieved satisfied with overall value added by Internal Audit work
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Annual Review docReport | 20 pages | DownloadRead as text |
PDF |
Internal Audit Annual Review 2004/05Report | 2 pages | Download |
Follow Resources Select Committee 2005/2006 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Apr 2006 | Minutes of the Last MeetingsAgreed that the minutes be approved. | Agreed | Open |
| 5 Apr 2006 | Called In Item - Percy Street/Upper Parliament Street/Parliament StreetAgreed that in view of the concerns expressed by members, consideration of this proposal be deferred pending the subm... | Agreed | Open |
| 5 Apr 2006 | Response to Motion - Properties in Newsham ParkAgreed that the Executive Member for Resources be requested to ensure that all long term vacant Council properties in... | Agreed | Open |
| 5 Apr 2006 | Revenues and Benefits Service PerformanceAgreed that the content of the report be noted. | Agreed | Open |
| 5 Apr 2006 | Green Paper - A New Deal For Welfare Empowering People to WorkAgreed that – a) The contents of the report be noted; b) The views of the Committee, particularly in relation to the ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.