Executive Board, Friday 9 December 2005

Consultation on Reorganisation of Provision for Pupils with Complex Learning Difficulties Phase 3 (CHS/28)

Decided Executive 3 papers

Executive Board decided this item on Friday 9 December 2005. Below is the council's own wording, with the papers it was decided on.

Item110d

Resolved

Resolved that that the Local Authority begins formal consultations on proposals to – (i) close Ashfield School with effect from 31 August 2006; (ii) amalgamate Meadowbank and MerseyView through the closure of the two schools on the 31 st of August 2006 and opening of one school on the current sites as a split site school with effect from 1 st September 2006 ensuring that – · the new secondary special school would make provision for 200 pupils age 11 to 16 with complex learning difficulties (i.e. moderate learning difficulties plus additional special needs); and · the new school would retain provision for the small number of existing primary pupils, plus a Speech and Language Unit – for pupils at Key Stages one and two accommodated on the Sherwoods Lane site, which was established as an interim measure, by a decision of the School Organisation Committee in July 2005; and (iii) establish reserved SEN provision for 80 pupils with complex learning difficulties (i.e. moderate learning difficulties plus additional special needs) at Childwall Specialist Sports College with effect from 1 st September 2006 – utilising premises of the former Ashfield School.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 4 pages

CITY STATUS – PUBLIC LL/38 Portfolio: Education and lifelong Executive Member: Learning Service Councillor Paul Clein

Date of submission: Subject: Reorganisation of Primary 26 January 2005 Provision for Pupils with CLD – Phase 2 Report No: DE/06/05 Contact Officer: Colette O’Brien Background papers: 233 2864 SEN Strategy, Policy into Practice, Post Ofsted Action Plan

Executive summary: This paper seeks approval to consult on the possible closure of Watergate School for pupils with complex learning difficulties (CLD) and its replacement with resourced places for pupils with special educational needs (SEN) at Beaufort Park CP School. As part of the same process, the Speech and Language Units (Sp&L units) currently based at Watergate School would be relocated to mainstream sites.

Over the last two years there has been a dramatic reduction in the number of pupils with CLD placed in the primary special sector, from 140 to 67 across Watergate’s 2 sites; Sherwoods Lane in the North of the City and Upper Essex Street in the South/Centre.

The reduction is a direct result of the combined impact of the SEN and Disability Act 2001 and the national and local Inclusion Agenda. Mainstream schools have an anticipatory duty to admit all pupils from their local community whatever their SEN or disability, and to make reasonable adjustments to provide appropriate physical and curriculum access. Increasingly parents are seeking mainstream education for their children, which has resulted in a steady decline in the numbers admitted to Watergate School.

In July 2005, 16 children across the 2 sites will transfer to secondary schools. The reduction in funding to the school for the next academic year will result in a deficit budget and an unviable situation. The proposal would consult on the closure of the school and the relocation of the Sp&L units to mainstream schools, with immediate effect from September 2005. The level of support delivered to the pupils would be replicated in the mainstream environment, with the advantage of opportunities for inclusion with mainstream peers.

Pupils currently attending the Upper Essex Street Site would be allowed to remain there, with exactly the same level of support; taking advantage of the 24 resourced places at Beaufort Park CP.

The remaining older pupils who currently attend the Sherwoods Lane site would be transferred to the adjacent Meadow Bank School, with the same pupil: teacher ratio and specialist support.

Watergate School currently employ teaching staff who deliver outreach support to primary schools commissioned through the Provider Panel. This practice would continue and be enhanced by the addition of teaching and non- teaching staff made available by the contraction in the CLD special school pupil numbers. The service would be run from the Sherwoods Lane site. The budget for the outreach staff and Sherwoods Lane site would be delegated to and managed via Meadow Bank Special School.

Executive Director recommendation: Colin Hilton recommends that –

1. the LEA begins formal consultation to close Watergate Special School and purchase reserved SEN Provision at Beaufort Park CP School. In addition, that Speech and Language Units currently based at Watergate School are relocated to mainstream schools; and

2. Officers begin discussions with parents, staff and governors at the mainstream schools affected to secure their agreement to the proposal to redeploy the speech and language units there.

Key Decision: Yes – involves the closure of a school and affects all wards.

Forward Plan: Yes

Implementation effective from: 11 February 2005

Timescale for action: If the recommendation is approved, consultations would be held immediately with a view to closure of the school for 31st August 2005 –

Mid February to Mid March 2005 - Statutory Consultation April 2005 - Decision of City Council following Consultation Mid April to Mid June 2005 - Publication of Statutory Notices End of June 2005 - Decision of SOC

Reason(s) for Recommendation:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CHS.028 consult re.org cld phase 3 DE.06.05Report 4 pages DownloadRead as text
PDF
CHS.028 consult re.org cld phase 3 DE.19.05Report 7 pages Download
PDF
Consultation on Reorganisation of Provision for Pupils with Complex Learning Difficulties Phase 3 (CHS/28)Report 5 pages Download

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Consultation on Reorganisation of Provision for Pupils with Complex Learning Difficulties Phase 3 (CHS/28)This decision
  2. Consultation on Reorganisation of Voluntary Aided Primary Schools in GarstonAgreed
  3. Consultation on Reorganisation of Voluntary Aided Primary School Provision in Garston (CHS/23)Approved

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open