Resolved that – (i) the Liverpool LDF Annual Monitoring Report as submitted be endorsed and approved for publication and submission to the Secretary of State; and (ii) the proposals for making amendments to the Local Development Scheme in early 2006, to be subject of a separate report, be noted.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
1. Section 35 of the Planning and Compulsory Purchase Act 2004 requires every local planning authority to make an Annual Monitoring Report (AMR) to the Secretary of State (to be submitted by 31st December each year). It covers the period from the 1st April 2004 to 31st March 2005 and contains information on the implementation of the Local Development Scheme (LDS) and the extent to which the policies set out in documents forming the Local Development Framework (LDF) are being achieved.
Background
2. Local Development Frameworks should be continually reviewed and revised and the Annual Monitoring Report will be the main mechanism for assessing the LDF’s performance and effects. This reflects the concept of ‘plan, monitor, and manage’, whereby the findings of monitoring feed directly into any review of policy that may be required.
3. Through the AMR, the City Council is required to:
• Review actual progress in terms of local development document preparation against the timetable and milestones in the local development scheme;
• Assess the extent to which policies in local development documents are being implemented;
• Where policies are not being implemented, explain why and set out what steps are to be taken to ensure that the policy is implemented; or whether the policy is to be amended or replaced;
• Identify the significant effects of implementing policies in local development documents and whether they are as intended; and
• Set out whether policies are to be amended or replaced. 4. It should also be noted that the submission of the AMR to the Secretary of State is a requirement of Best Value (BVPI 200c) and is a determinant of Planning Delivery Grant allocations.
Developing a Framework of Indicators for Monitoring
5. The indicators used in this AMR have been included because they relate specifically to the policies outlined (or to be outlined) in the LDF or because they are national core indicators defined by the Office of Deputy Prime Minister (ODPM). All of the indicators are felt to be easily understandable, technically robust and capable of being monitored over future years. Where possible indicators have been used that are already being collected via other monitoring processes such as Best Value, Community Strategy, RSS and the plan-making processes of Sustainability Appraisal and Strategic Environmental Assessment.
AMR 2004-2005: Key Findings
Demonstrating the Success of Liverpool’s Planning Policies
6. As this is the first AMR to be produced it is inevitably limited in its coverage because no new policies have yet been produced and the existing UDP sets out its policies in a way which makes the type of detailed monitoring now required more difficult.
7. Although over time AMRs will build up their content and coverage. They must however be produced in accordance with government guidelines. This has the advantage of ensuring a degree of consistency and continuity over time and also between the AMRs produced by different local council’s.
8. As a result the AMR contains a wide range of “contextual “indicators including some such as the degree of limiting long-term illness, which are only indirectly linked to planning policies. Many of these are being used on Merseyside wide basis however to provide a key backdrop to policy implementation and development. And it is an important objective that planning policy is developed that does not exacerbate adverse conditions and where possible contributes to their improvement, for example by encouraging good design, protecting from pollution, improving accessibility and access to key services and facilities and many other physical changes that could benefit neighbourhoods and communities.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.