Resolved that – (i) the land at Grovehurst Avenue, shown verged on the plan submitted, be declared surplus to requirements; (ii) the Head of Property and Asset Management Services be authorised to negotiate the disposal of the land to the Central Liverpool Primary Care Trust for use as a health centre and report back on the terms; and (iii) in the event that heads of terms for the sale cannot be concluded within six months from the date of Executive Board approval to negotiate with the Central Liverpool PCT then the Head of Property and Asset Management Services be authorised to market the land.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
1.1The properties at Stonefield Road (4 units), Longreach Road (4 units) and Grovehurst Avenue (64 units) were demolished between June 2002 and March 2003 as being unsustainable. The resultant site was excluded from the Eastern Fringe stock transfer to Berrybridge Housing Association as the Primary Care Trust (PCT) had expressed an interest in developing the site as a health centre.
1.2Restructuring of the PCT, together with other land options being investigated in the Dovecot area by the PCT, had meant that the PCT were unable to fully commit to the Grovehurst scheme. In recent months the newly formed Central Liverpool PCT have renewed their interest and have now given a firm commitment that they wish to proceed with the project.
1.3The facilities planned for the site include:
• local general practices including an out of hours surgery; • audiology outreach clinic; • community dental practice; • diagnostic centre (for x-rays, ultrasound and ECG); • minor surgery; and • pharmacy
1.4The site is currently fenced – although this is regularly breached through vandalism which leads to repeated incidents of fly tipping which requires the response of Enterprise Liverpool. This fly tipping is a potential fire hazard and response to it is a priority for Eastern Link Neigbourhood Management Service. The site is also overgrown and would be very costly to clear and maintain on a managed basis. The site was previously gated to enable access to the site but co- ordination of access to the site was problematic leading to a local decision to weld the gates closed. The area surrounding the site has also been subject to a variety of measures to address youth disorder – linked to the vandalism issue – and culminated in the introduction of a Section 30 dispersal order.
1.5The Highways Manager has been consulted and is of the view that a health facility here is workable in transport terms. Pedestrian linkages are available through the existing community centre on Dovecot Parade, which in turn has links to public transport services. Depending upon the scale of the development and the resultant traffic impact, improvements to roads leading to the site may be necessary to provide legibility, avoid traffic conflict, control parking and enhance pedestrian links to surrounding residential areas. The Highways Manager also advises that the enclosed portion of Grovehurst Avenue remains as an adopted public highway and will have to be formally stopped up prior to any development taking place.
1.6The Planning Manager has been consulted and considers that a development of the site for a health facility could be acceptable in principle, particularly given the possible links to other community facilities at the rear of Dovecot Parade. However he considers much would depend upon the size and scale of the proposal. Issues such as impact on traffic will be particularly important and the Planning Manager notes the comments of the Highways Manager. Other issues such as opening times and the height, massing and design of the building would also need to be carefully considered given the proximity of residential properties.
1.7To minimise the length of time the Council retains ownership of the land it is recommended that should approval be granted to negotiate with the PCT for the site that those negotiations are time-limited, to say six months, and should heads of terms have not been concluded then authority be granted for the Head of Property and Asset Management Services to market the site.
Executive Member Councillor Flo Clucas OBE/Executive Director recommendation (Charlie Parker)
That -
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.