Resolved that – (i) authority to be given to the Assistant Executive Director (Regeneration Policy and Programmes) to accept external grant of £610,907 (comprising an NWDA grant totalling £179,868; SRB totalling £235,000; Objective 1 monies of £196,039) over the period 2005/6 to 2008/9. The City Council will thereby accept the role of the accountable body and ensure the grant is administered appropriately; (ii) the Divisional Manager (Regeneration Policy and Programmes) be appointed as the nominated officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises; (iii) expenditure on this programme be only incurred after the receipt of confirmation of funding from all the relevant organisations/bodies upon which this project relies for income and the finalisation of all other relevant documents; (iv) the City Council’s revenue budget be adjusted, on receipt of confirmation of funding to reflect additional expenditure and income on this project totalling £610,907 over the financial years 2005/6 (£110,000), 2006/7 (£223,000),2007/8 (£222,000) and 2008/09 (£55,900); (v) a future report to be submitted to Executive Board in due course to agree Operational details and staffing arrangements associated with the MCI; (vi) the Council agrees to forward fund Construction for Merseyside on a quarterly basis, for grant funding for which the Council is the accountable body; and (vii) regular reports on the progress of this and other related projects be forwarded to the Regeneration and Environment Select Committee.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Portfolio: Regeneration Executive Member: Councillor Peter Millea
Date of submission: November 2005 Subject: Merseyside Construction Initiative – Accountable Body for funding
Report No./Background papers Contact officer: Report EDR/315/05 Julia McNally - 233-5323 Kim Griffiths-Parry – 233 5334
Executive Summary The purpose of this report is to seek Executive Board approval for Liverpool City Council to act as the accountable body on behalf of Construction for Merseyside Ltd. to deliver the Merseyside Construction Initiative (MCI). The grant package to support the MCI includes funding from the North West Development Agency (NWDA), Single Regeneration Budget (SRB6) and European Regional Development Fund (ERDF).
Background The MCI will be delivered by Construction for Merseyside Ltd (CfM) . It has been established to support the development of a competitive and sustainable construction sector in Merseyside that will create wealth and provide employment opportunities for local people. The initiative, which is already partially operational, will undertake a range of key actions including the following:
• It will capture and analyze information and intelligence on the volume and nature of construction activity in Merseyside and use and share this information as the basis for workforce planning and workforce development.
• It will engage with employers and identify and articulate their skills needs
• It will advise the public agencies and training providers on the construction sector’s skills and capacity requirements to tailor provision.
• It will deliver a skills match service for suitably skilled individuals signposted from other agencies to ensure they are equipped to enter the industry at the right level and develop their employment in a sustainable manner. • It will operate a recruitment agency to provide an effective service to employers and continuity of training and other support to site ready construction workers and appropriately skilled school leavers.
• It will promote the take-up of training opportunities by Merseyside SMEs. It will negotiate and monitor Training Agreements, which client organisations will require all employers in the contract chain to sign up to.
• It will assist local people, particularly those outside the labour market to gain employment in construction.
Current Position
The Merseyside construction boom offers a unique window of opportunity to capture economic benefits for local businesses and people, and to provide new career pathways for young people. With 90% of construction firms employing fewer than 5 people, improving SME competitiveness and growth will be critical to ensuring employers have an adequate infrastructure to invest in training and employment.
The timing of the MCI is crucial. There is already a substantial amount of additional construction activity on Merseyside. In October 2004, the £800m Paradise Street retail development commenced, adding to the volume of City Centre activity, such as the City Centre Movement Strategy contract. Development of the Kings Waterfront and the Housing Market Renewal Initiative are now underway, and there are major infrastructure, education and healthcare schemes due to take place.. Partners involved in the MCI are working on an integrated approach to ensure that employers are properly supported in establishing on-site training and that local SMEs are able to access sub-contracting opportunities.
The MCI approach fits well with the emerging NW Regional Construction Strategy and an early start will help to ensure some quick wins for the region. Without an initiative of this kind, not only will a substantial opportunity to achieve real benefits for local business and individuals be lost, but the capacity of the construction sector to deliver the major regeneration, renewal and other development activity forecast for the sub-region will be potentially undermined.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.