Resolved that – (i) The Year 6 Neighbourhood Renewal Fund (NRF) programme be approved for implementation from 1 April 2006 subject to the specific projects identified in annex 4 submitted receiving Executive Board approval or Executive Member briefings being provided as appropriate; and (ii) the overall impact of the NRF programme on the budget of the City Council be noted and that the detailed implications setting out the capital and revenue expenditure to be financed from NRF resources, be the subject of a further report.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
1) To inform Council Members of (i) achievements from the year 4 programme (ii) the progress to date of the year 5 programme (iii) the process adopted to develop the year 6 programme
2) To seek approval to the year 6 NRF programme outlined in annex 4 of the main report
3) To agree implementation from 1 April 2006.
Background
Liverpool has been allocated £30,998,897 Neighbourhood Renewal funding for year 6 (2006/07) and £31,069,066 for year 7(2007/08). NRF Funding after year 7 is the subject of the Comprehensive Spending Review due next year.
The Neighbourhood Renewal Fund is a targeted grant to tackle deprivation in the most deprived neighbourhoods. The fund aims to assist the delivery of a number of nationally and locally-set Public Service Agreements (PSAs) in relation to education, employment, crime, health and housing, together with other action to improve the quality of life of residents in the most deprived neighbourhoods. It is intended as time-limited funding to kick-start more effective long-term targeting of mainstream resources to tackle deprivation in the most deprived areas.
Information
The Liverpool Strategic Partnership (LSP) received notification of the NRF year 6 and 7 allocations in the summer. At the same time GONW had publicly stated that the LSP would be the subject of enhanced scrutiny in respect of additionality, bending mainstream spending and making a direct impact on PSA targets. The notification of additional funding for two years stated, “where an LSP faces particular challenges to meet one or more key national floor target, the government expects that the LSP should direct these new resources towards meeting those targets and bridging the gap between the most deprived neighbourhoods and the rest of the country”. The LSP was graded as “Green” in our annual assessment. However, there was concern that the employment and health-related targets may be out of our reach within the timescales available. It should be noted that although employment and health have been identified as areas for intervention, Liverpool still has a number of other challenging targets and care must be taken that a balanced programme in respect of theme and geography is established.
The process for developing the year 6 programme has been arranged around a number of key activities in respect of changes to the targeting of resources, more inclusive consultation and identification of investment priorities.
Building on the systems and processes used to establish the year 5 programme, the year 6 process began in the summer and consisted of the following steps:
Consultations took place with key stakeholders including LPG Members, Executive Members, Chairs of the Strategic Issue Partnership involved in NRF, the Executive Management Team, AEDs and relevant officers across LCC. A presentation was given to Regeneration and Environmental Select Committee, three elected members seminars were held and presentations were given to LPG and Strategic Issue Partnerships, Liverpool Community Network (Chairs meeting) and year 5 project officers. In depth work was undertaken with Neighbourhood Managers and the Chairs of the SIPs.
The consultations assisted in identifying common investment priorities resulting in the production of the NRF year 6 commissioning document.
Emphasis has been placed on performance management and, in particular, additional links have been made with the Corporate Performance Plan (CPP), Best Value Performance Indicators (BVPI) and local and national Public Service Agreement (PSA) Targets.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.