Housing and Community Safety Select Committee 2005/2006 agreed this item on Tuesday 7 February 2006. Below is the council's own wording, with the papers it was decided on.
Agreed that the following recommendation be noted. Members note that forecast overall spending at the year-end for: · revenue services provided by the Regeneration Portfolio through the general fund are anticipated to be in line with available budgetary resources; and · the Regeneration Portfolio capital programme is also anticipated to be in line with resources available . FMS/06/06
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Report to Housing and Community Safety Select Committee 2005/2006, 6 pages
Liverpool City Council
Report to: Regeneration & Environment Select Committee Housing & Community Safety Select Committee
Subject: Regeneration General Fund Financial Review Quarter 3 2005/06
Report no: FMS 04 06
Date: 9 February 2006 7 February 2006
Reporting officers: Ben Dolan – AED (Performance & Business Management Robert Corbett – AED (Financial Management Services)
Contact officer: Anne Ryans - Lead Finance Manager Tel: 0151 233 4634 e-mail: [email protected]
Ward: City wide
1. Purpose and recommendations
1. This report provides an update on the financial position for the Regeneration Portfolio general fund revenue services, and the financial position of the capital programme delivered through the Regeneration Portfolio on the basis of the best information available. 2. A separate report is prepared for Housing Revenue Account (HRA) services delivered through the Regeneration Portfolio. Recommendations 3. Members note that forecast overall spending at the year-end for: • revenue services provided by the Regeneration Portfolio through the general fund are anticipated to be in line with available budgetary resources. • the Regeneration Portfolio capital programme is also anticipated to be in line with resources available.
2. Relevant Background Information Revenue 4. Based on information from the latest budget monitoring exercise of 2005/06, it is anticipated that overall spending at the year-end for services provided by the Regeneration Portfolio will be within allocated budgetary resources. However, the Portfolio has faced a range of budget pressures which have required corrective management action. Members should note that during the financial year, budgetary positions and forecasts are subject to change as income and expenditure trends and service delivery issues become more established. 5. The total net revenue budget for the Regeneration Portfolio for the current financial year is £86.689 million, as indicated in Appendix A. Capital 6. As indicated in Appendix B, the Regeneration Capital Programme is currently forecast at £191,432 million in 2005/06. 7. Variances are currently indicated when comparing outturn gross expenditure forecasts to current gross expenditure budgets, but all of these variances are contained within the financing available as indicated in Appendix B. 8. To resolve these variances, Divisional Managers have been and are requesting approvals from the Executive Board to realign the approved programme so that budgets reflect forecast delivery plans and both are contained within available resources. The outcome of these requests will be reflected in subsequent monitoring reports.
3. Key Issues
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Housing and Community Safety Select Committee 2005/2006 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.