Resolved that – (i) the amendments to the Edge Lane Improvements and Liverpool Science Park Infrastructure Works projects, be noted; (ii) Liverpool City Council will act as Accountable Body for Objective 1 ERDF funding in respect of the two projects, and that grant receipt and monitoring conditions set out in the previous reports will apply; (iii) The City Council’s capital programme be adjusted to reflect the revised ERDF expenditure on these projects for a sum up to £12,560,500 phased over the financial years 2005/06 (£202,000), 2006/07 (£8,618,900), 2007/08 (£2,483,550) and 2008/09 (£1,256,050); (iv) authority be given to commit expenditure in order to undertake works that will fulfil the terms of the ERDF offer letter; and (v) it be noted that a separate report will be brought back by Officers identifying whether the shortfall in grant income can be made good by utilising income for the car parking service, and if not, that the Highways Capital Programme is examined and options and priorities brought forward to the Executive Board as soon as possible; and (vi) further reports will be submitted to Members as and when appropriate to update on progress RT/8
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
1. In 2005 Liverpool City Council agreed to act as the Accountable Body for Objective 1 ERDF towards the cost of the “Edge Lane Improvements” and “Liverpool Science Park Infrastructure Works” projects that are to be delivered by Liverpool Land Development Company (LLDC). The amount of ERDF for Edge Lane was £7.660 million and the amount for Liverpool Science Park was £5.155 million – a total of £12.815 million for the two projects.
2. The two ERDF applications have now been reconfigured. The Edge Lane project has been extended to include Edge Lane West (as well as Edge Lane Drive and Central that were in the original application) and also now includes the new access on to Edge Lane for the Liverpool Science Park. The ERDF sought from the revised Edge Lane application is £8,262,000. The Science Park application is essentially the same, except that the access works have been taken out, and the revised ERDF sought is £4,298,500. The total ERDF sought from the two revised projects is £12,560,500, a decrease of £254,500 on the original approvals.
3. Authority is sought through this report to accept the revised ERDF funding, commit the expenditure, and amend the City Council’s capital budget accordingly.
Executive Member/Interim Director recommendation. Cllrs Peter Millea/Keith Turner – Ben Dolan
That Members:
1. Note the amendments to the Edge Lane Improvements and Liverpool Science Park Infrastructure Works projects
2. Confirm that Liverpool City Council will act as Accountable Body for Objective 1 ERDF funding in respect of the two projects, and that grant receipt and monitoring conditions set out in the previous reports will apply
3. The City Council’s capital programme be adjusted to reflect the revised ERDF expenditure on these projects for a sum up to £12,560,500 phased over the financial years 2005/06 (£202,000), 2006/07 (£8,618,900), 2007/08 (£2,483,550) and 2008/09 (£1,256,050)
4. Authority be given to commit expenditure in order to undertake works that will fulfil the terms of the ERDF offer letter; and
5. Note that a separate report be brought back by Officers identifying whether the shortfall in grant income can be made good by utilising income for the car parking service, and if not, that the Highways Capital Programme is examined and options and priorities brought forward to the Executive Board as soon as possible
Further reports to be submitted to Members as and when appropriate to update on progress.
Key Decision: Yes
Forward Plan Yes
Implementation effective from: 24 March 2006
Timescale for action:
Project to be delivered between February 2005 and December 2008.
Reason(s) for Recommendation:
To seek formal approval to accept revised ERDF grant, for Liverpool City Council to act as Accountable Body for Objective 1 ERDF grant for two projects supported by LLDC and NWDA, and to amend the Capital programme as appropriate.
Alternative options to be considered:
The City Council has already agreed to act as Accountable Body for these two projects and no alternative options are therefore appropriate.
Consultation
Consultation has taken place with Officers from Regeneration Portfolio and LLDC. Individual comments where received have been taken on board in the writing of the report.
The Head of Finance (Regeneration) has input into the financial implications.
Discussions / negotiations have taken place with the Objective 1 Secretariat, NWDA and LLDC.
Consultation with Ward Councillors
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.