Resolved that subject to revised offer letters - (i) the revised grant offers as outlined in the financial implications section of the report submitted, be accepted; (ii) the capital programme be amended to reflect the offers; (iii) all areas of work on Edge Lane including works on Liverpool Science Park site covered by the ERDF grant allocation shall be maintained to the refurbished upgraded standard for a minimum of ten years from Practical Completion. Maintenance shall be in accordance with an agreed maintenance plan and shall include - · prompt repairs to any damaged infrastructure within the adopted highway including paving, street furniture, lighting and any public art; and · maintenance of trees and other landscaped areas. NH/17
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
1. ERDF contributions have always been an element of the overall Edge Lane funding package. Due to the delays in the Edge Lane West scheme it has now been decided that no ERDF funding should be used on that particular scheme. The portion of the suggested funding allocation for Edge Lane West should be reallocated to the other Edge Lane schemes. This course of action has been agreed by the funding body. 2. Authority is sought through this report to accept the revised ERDF funding distribution and amend the City Council’s capital budget accordingly. 3. There is a requirement by the funding body (ERDF) to have a City Council resolution confirming that the works as constructed will be maintained by Liverpool City Council for a period of ten years from completion.
Executive Member/Director recommendation (names to be inserted): Cllr M Storey CBE, Cllr K Turner and John Kelly, Executive Director for Regeneration –
That subject to revised offer letters Members;
1. Accept the revised grant offers as outlined in the financial implications section of the report. 2. Amend the capital programme to reflect the offers. 3. Confirm that all areas of work on Edge Lane including works on Liverpool Science Park site covered by the ERDF grant allocation shall be maintained to the refurbished upgraded standard for a minimum of ten years from Practical Completion. Maintenance shall be in accordance with an agreed maintenance plan and shall include: • Prompt repairs to any damaged infrastructure within the adopted highway including paving, street furniture, lighting and any public art • Maintenance of trees and other landscaped areas
Key Decision: Yes
Forward Plan: No Reason if not in Forward Plan: Urgent decision required to release funding from ERDF within the next 3 months
Implementation effective from: 2 January 2008
Timescale for action: Immediate to enable ERDF to release funds being withheld pending Executive Board resolution as described above. The delivery programme for Edge Lane Drive, Edge Lane Central and Liverpool Science Park is unaffected by this change. However, Edge Lane West has been delayed due to a objections to the CPO process and this led to the ERDF funding being withdrawn from that scheme. It is still the intention that Edge Lane West will be constructed, but this depends on a successful outcome to the CPO Inquiry to acquire properties along the Edge Lane corridor.
Reason(s) for Recommendation: To seek formal approval to accept the redistribution of the ERDF grant from Edge Lane West to the other schemes on Edge Lane.
To enable the funding from ERDF to be paid to Liverpool City Council following the formal acceptance that the works will be maintained for a period of ten years from the date of handover or substantial completion.
Alternative options considered: No alternative options have been considered since there is a payment of £5m pending and due to be paid over the next three months if the resolution is agreed.
Performance Indicators are not affected by this recommendation. Consultation: Consultation has taken place with Officers from Regeneration Portfolio and LLDC.
Consultation with Ward Councillors and outcome: None
Financial implications
Revised funding allocation to Edge Lane schemes:-
Actual Forecast Total Scheme 2006/07 2007/08 Forecast Edge Lane Drive 1,164,876 171,124 1,336,000
Edge Lane Central 3,805,177 1,883,923 5,689,100
Edge Lane West 236,900 0 236,900
Total 5,206,953 2,055,047 7,262,000
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.