Resolved that : approval be given to - (i) the procurement of replacement Parking Service Software and supporting hardware at a cost of £452,000 financed by – · the available capital resources of £250,000 in 2006/07; and · £202,000 of unsupported borrowing from the 2006/07 invest to save capital programme; (ii) amend the 2006/07 capital programme for the inclusion of a £452,000 capital scheme and the forward commitment of the revenue and capital resources to facilitate software and hardware procurement; (iii) the procurement and construction of Parking Services operational/ administrative accommodation at Mount Pleasant Car Park at a cost of £500k financed from a 2006/07capital resources; and (iv) amend the capital programme of 2006/07 to reflect the accommodation works at Mount Pleasant car park and the forward commitment of the capital scheme to facilitate the procurement and construction of the accommodation. RT/14
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
• Members will be aware of the initiatives currently being pursued to improve the provision of parking facilities and services. This report covers 2 particular aspects i.e. IT facilities and operational accommodation at the Mount Pleasant car park.
• The IT software currently used within parking services was introduced by Vinci Park during the Citilink operation. It no longer meets the needs of the service. With the assistance of LDL, a preferred software solution has now been identified. In addition to improving existing applications the preferred solution provides a platform for enforcement of other aspects of the Traffic Management Act and other environmental enforcement activities.
• Acquisition of the software and related hardware will considerably improve collection rates for penalty charge notices and ensure effective collection of charges for other traffic management infringements. The estimated cost of the solution is £452,000. It is therefore proposed that the acquisition be progressed partly although the use of 2006/07 capital resources (£250,000) and partly as an Invest to Save initiative in 2006/07 (£202,000).
• Currently parking services is delivered through 2 sites: the enforcement activity being located at Mount Pleasant and the Appeals and Representations team being located at Crosshall Street. Both locations are unsatisfactory for efficient and cost effective service delivery. The Crosshall Street site is to be vacated in any event to facilitate the disposal of Tinlings Buildings.
• Building consultants, with the assistance of Premises Management have reviewed the accommodation at Mount Pleasant Car Park and have developed an outline proposal to build single storey office accommodation on the corner section of the roof of the car park. This will not only be an effective solution but will also free up parking spaces not currently available due to the current position of the temporary mobile office accommodation set up by Vinci Park.
• The estimated cost of the proposal is £500,000. It is recommended that this be financed by available capital resources of £500,000 in 2006/07.
• Members are asked to approve the above initiatives.
Executive Member/Director recommendation: Councillors Peter Millea and Keith Turner/ Phil Halsall
That: approval be given to -
1. The procurement of replacement Parking Service Software and supporting hardware at a cost of £452k financed by a) the available capital resources of £250,000 in 2006/07 ; b) £202,000 of unsupported borrowing from the 2006/07 invest to save capital programme
2. Amend the 2006/07 capital programme for the inclusion of a £452,000 capital scheme and the forward commitment of the revenue and capital resources to facilitate software and hardware procurement
3. The procurement and construction of Parking Services operational/administrative accommodation at Mount Pleasant Car Park at a cost of £500k financed from a 2006/07capital resources.
4. Amend the capital programme of 2006/07 to reflect the accommodation works at Mount Pleasant car park and the forward commitment of the capital scheme to facilitate the procurement and construction of the accommodation.
Key Decision: Yes
Forward Plan: No – appropriate notices will be published in accordance with the constitution
Implementation effective from: Approval of recommendations Timescale for action:
Subject to approval of the Executive Members the time scales for
• Implementation of the new IT solution is 4 months from date of approval.
• Construction of new accommodation is 6 months from date of approval
Reasons for recommendation
Introduction of the new Integrated Parking IT system will provide the platform for
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.