Parking Services - Improvements to IT Systems and Accommodation (RT/13)

Approved Executive 1 paper

Executive Board approved this item on Friday 31 March 2006. Below is the council's own wording, with the papers it was decided on.

Item184h

Resolved

Resolved that : approval be given to - (i) the procurement of replacement Parking Service Software and supporting hardware at a cost of £452,000 financed by – · the available capital resources of £250,000 in 2006/07; and · £202,000 of unsupported borrowing from the 2006/07 invest to save capital programme; (ii) amend the 2006/07 capital programme for the inclusion of a £452,000 capital scheme and the forward commitment of the revenue and capital resources to facilitate software and hardware procurement; (iii) the procurement and construction of Parking Services operational/ administrative accommodation at Mount Pleasant Car Park at a cost of £500k financed from a 2006/07capital resources; and (iv) amend the capital programme of 2006/07 to reflect the accommodation works at Mount Pleasant car park and the forward commitment of the capital scheme to facilitate the procurement and construction of the accommodation. RT/14
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 6 pages

Executive summary

• Members will be aware of the initiatives currently being pursued to improve the provision of parking facilities and services. This report covers 2 particular aspects i.e. IT facilities and operational accommodation at the Mount Pleasant car park.

• The IT software currently used within parking services was introduced by Vinci Park during the Citilink operation. It no longer meets the needs of the service. With the assistance of LDL, a preferred software solution has now been identified. In addition to improving existing applications the preferred solution provides a platform for enforcement of other aspects of the Traffic Management Act and other environmental enforcement activities.

• Acquisition of the software and related hardware will considerably improve collection rates for penalty charge notices and ensure effective collection of charges for other traffic management infringements. The estimated cost of the solution is £452,000. It is therefore proposed that the acquisition be progressed partly although the use of 2006/07 capital resources (£250,000) and partly as an Invest to Save initiative in 2006/07 (£202,000).

• Currently parking services is delivered through 2 sites: the enforcement activity being located at Mount Pleasant and the Appeals and Representations team being located at Crosshall Street. Both locations are unsatisfactory for efficient and cost effective service delivery. The Crosshall Street site is to be vacated in any event to facilitate the disposal of Tinlings Buildings.

• Building consultants, with the assistance of Premises Management have reviewed the accommodation at Mount Pleasant Car Park and have developed an outline proposal to build single storey office accommodation on the corner section of the roof of the car park. This will not only be an effective solution but will also free up parking spaces not currently available due to the current position of the temporary mobile office accommodation set up by Vinci Park.

• The estimated cost of the proposal is £500,000. It is recommended that this be financed by available capital resources of £500,000 in 2006/07.

• Members are asked to approve the above initiatives.

Executive Member/Director recommendation: Councillors Peter Millea and Keith Turner/ Phil Halsall

That: approval be given to -

1. The procurement of replacement Parking Service Software and supporting hardware at a cost of £452k financed by a) the available capital resources of £250,000 in 2006/07 ; b) £202,000 of unsupported borrowing from the 2006/07 invest to save capital programme

2. Amend the 2006/07 capital programme for the inclusion of a £452,000 capital scheme and the forward commitment of the revenue and capital resources to facilitate software and hardware procurement

3. The procurement and construction of Parking Services operational/administrative accommodation at Mount Pleasant Car Park at a cost of £500k financed from a 2006/07capital resources.

4. Amend the capital programme of 2006/07 to reflect the accommodation works at Mount Pleasant car park and the forward commitment of the capital scheme to facilitate the procurement and construction of the accommodation.

Key Decision: Yes

Forward Plan: No – appropriate notices will be published in accordance with the constitution

Implementation effective from: Approval of recommendations Timescale for action:

Subject to approval of the Executive Members the time scales for

• Implementation of the new IT solution is 4 months from date of approval.

• Construction of new accommodation is 6 months from date of approval

Reasons for recommendation

Introduction of the new Integrated Parking IT system will provide the platform for

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Parking Services: Improvements to IT Systems and Accommodation (RT/13)Report 6 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 20 attended
WB
Councillor Warren BradleyChair, present
DA
Councillor Dave AntrobusMember, present
PC
Councillor Paul CleinMember, present
FC
Councillor Flo Clucas OBEMember, present
MF
Councillor Marilyn FieldingMember, present
RM
Councillor Richard MarbrowMember, present
PM
Councillor Peter MilleaMember, present
MS
Councillor Mike Storey CBEMember, present
BT
Councillor Berni TurnerMember, present
KT
Councillor Keith TurnerMember, apologies
SD
Sir David HenshawOfficer, expected
PH
Phil HalsallOfficer, present

All 20 on the meeting page

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open